Lander v. Phoenix Indemnity Co.

329 S.W.2d 951, 1959 Tex. App. LEXIS 2255
CourtCourt of Appeals of Texas
DecidedNovember 19, 1959
DocketNo. 3676
StatusPublished
Cited by2 cases

This text of 329 S.W.2d 951 (Lander v. Phoenix Indemnity Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lander v. Phoenix Indemnity Co., 329 S.W.2d 951, 1959 Tex. App. LEXIS 2255 (Tex. Ct. App. 1959).

Opinion

TIREY, Justice.

Appellee grounded its cause of action on a contract of suretyship evidenced by a contract between appellee and appellant whereby appellee bound itself to be surety on appellant’s bond for certain construction work to be done in Louisiana and known as contract No. 4619. The controlling factual situation does not yield to a simple statement. At the conclusion of the evidence appellee presented its motion for instructed verdict, which was overruled; thereafter the Court submitted two issues to the jury:

“(1) Do you find from a preponderance of the evidence that the plaintiff, Phoenix Indemnity Company, did not exercise good faith in paying out any of the itemized sums of money listed in Exhibit 15 ?
“Answer: ‘It did not,’ or ‘It did.’
“If you have answered Special Issue No. 1, ‘It did not,’ then answer the following issue; otherwise, do not answer it.
“(2) From a preponderance of the evidence which, if any, of the items listed in Exhibit 15, do you find were not paid in good faith by the plaintiff company?
“Answer by designating the party, if any, and the amount, if any.”

The jury being unable to reach a verdict the Court discharged the jury and thereafter granted appellee’s motion for judgment. In the judgment we find this recital :

“After considering said special issues the jury returned into court on the 5th day of August, 1958, stating they all were unable to agree upon the verdict in said cause, and were unable to answer the special issues submitted to them by the Court, and the Court being of the opinion that said jury could not answer the issues so submitted discharged the jury. After discharge of the jury, the plaintiff filed its motion for judgment re-urging the grounds set forth in its motion for instructed verdict, and the Court having considered same [953]*953is of the opinion, and now so finds, that the Motion for Instructed Verdict should have been granted against the defendant, and that the plaintiff is now entitled, as a matter of law, to a Judgment in this case for the amount of the principal, interest and attorney’s fees on the note sued upon, together with a foreclosure of the lien upon the property hereinafter described.” The Court decreed that plaintiff recover against defendant the sum of $2,319.69, with interest and attorneys’ fees as provided in the decree. It also decreed foreclosure of a mortgage lien on certain personal property. Defendant duly excepted to the Court’s action and gave notice of appeal and duly perfected his appeal and the case is here on transfer. The defendant assails the judgment on three points, and they are substantially to the effect that the Court erred in the following particulars :
(1) In withdrawing the case from the jury and granting judgment for the appel-lee, because the jury was unable to reach a verdict on the submitted special issues and where disputed fact questions had been raised by the evidence;
(2) In granting judgment on promissory note because there was no competent evidence to show the extent of defendant’s liability, if any, under the note;
(3) In admitting into evidence over timely objections, the affidavit executed by Hickman (being Exhibit 15) which affidavit set out expenses that appellee had charged against appellant.

Appellee’s counterpoints are:

(1) That the Court did not err in withdrawing the case from the jury and granting its motion for judgment;
(2) In admitting into evidence the affidavit of Hickman;
(3) That the evidence sustains the judgment.

A comprehensive statement is necessary.

Appellee went to trial on its first amended original petition. It alleged that its contract with defendant is embodied in the application for contract or bid bond, and that defendant executed the application for contract and pursuant thereto ap-pellee executed the bond as surety for the defendant whereby said contract of surety-ship enabled the defendant to make a contract to do certain construction work in the State of Louisiana known as contract 4619; that by the provisions of the contract between plaintiff and defendant, defendant agreed to indemnify plaintiff for all loss, costs, damages, expenses and attorney’s fees whatsoever, and any and all liability therefor sustained or incurred by plaintiff by reason of execution of said bond, in making of any investigation on account thereof, in prosecuting or defending any action brought in connection therewith, in obtaining a release therefrom, and in enforcing any of the agreements contained in said contract; that subsequent to the making of said bond defendant entered upon the performance of his contract, and thereafter breached it, and the plaintiff was called upon as surety to complete same and pay certain bills of the defendant in connection with said contract and construction work; that in so doing plaintiff incurred certain losses, itemizing the same, that he alleged to be the sum of $9,849.63; that plaintiff collected the sum of $7,529.94 from defendant which it applied to the foregoing expenses as part of the indemnity for said expenses, leaving the balance now due and owing of $2,319.69 under the terms of plaintiff and defendant’s contract embodied in the application here referred to for contract and bond; that the plaintiff was authorized to demand collateral from the defendant for the above expenses which it incurred, or might incur in the future as a result of being surety on defendant’s bond; that plaintiff made such demand and defendant acquiesced thereto and put up collateral for the foregoing expenses; that said collateral was in the form of a chattel mortgage on certain personal property [954]*954fully described, and it prayed for foreclosure of said mortgage; for its debt, and for reasonable attorneys’ fees. The foregoing in effect constitutes first count in plaintiff’s pleadings. In the second count it alleged that when defendant breached his construction contract on which plaintiff was surety, and on which plaintiff as surety was called upon to pay certain bills incurred by defendant and to complete such contract, that it appeared at such time that the expenses that plaintiff might have to pay might amount to around $4,000; that plaintiff demanded and defendant acceded to its demand and executed a promissory note in the amount of $4,000 to cover contingent expenses which plaintiff might be out in accordance with the terms of plaintiff and defendant’s contract embodied in said application for contract or bid bond in plaintiff’s first count in the amount of $9,849.63, and that plaintiff has been indemnified for only $7,529.94, leaving a balance due on said note of $2,319.69, plus legal interest and attorneys’ fees. Plaintiff set out the note in detail and the execution and delivery of the chattel mortgage on the bulldozer, and it prayed that it have judgment in the sum of $2,319.69, either under its first count or under its second count. Defendant went to trial on his second amended original answer.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
329 S.W.2d 951, 1959 Tex. App. LEXIS 2255, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lander-v-phoenix-indemnity-co-texapp-1959.