Land Group, Inc. v. Palmieri

1 A.3d 234, 123 Conn. App. 84, 2010 Conn. App. LEXIS 355
CourtConnecticut Appellate Court
DecidedAugust 3, 2010
DocketAC 30741
StatusPublished
Cited by5 cases

This text of 1 A.3d 234 (Land Group, Inc. v. Palmieri) is published on Counsel Stack Legal Research, covering Connecticut Appellate Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Land Group, Inc. v. Palmieri, 1 A.3d 234, 123 Conn. App. 84, 2010 Conn. App. LEXIS 355 (Colo. Ct. App. 2010).

Opinion

Opinion

SULLIVAN, J.

The plaintiff, The Land Group, Inc., appeals from the judgment of the trial court in favor of the defendants, Carl J. Palmieri, as trustee and in his individual capacity, Frank Palmieri, as trustee and in his individual capacity, Mary Gai, 1 Florence Palmieri and Marie Palmieri, executrix of the estate of Vincent Palmieri. The court found that the defendants did not breach the parties’ contract for the purchase and sale of the real estate at issue. The plaintiff, however, did breach the contract, and, therefore, the defendants were entitled to liquidated damages and attorney’s fees. The plaintiff claims that the court improperly held that (1) the contract required the plaintiff to pursue zoning permits and approvals with due diligence, (2) the plaintiff breached the contract, (3) the defendants had the right to terminate the contract, (4) the defendants did not anticipatorily breach the contract, (5) the defendants did not commit a breach of contract, (6) article two of the contract should be interpreted in an overall restrictive manner, (7) the defendants prevailed on the first count of their counterclaim, (8) the plaintiff was not entitled to attorney’s fees for prevailing on the third count of the defendants’ counterclaim and in a separate action brought by the defendants, and (9) the award of attorney’s fees to the defendants was reasonable.

*87 The plaintiff instituted a three count complaint against the defendants, the record owners of a parcel of land in Westport, alleging anticipatory breach of the contract, breach of contract and breach of the implied covenant of good faith and fair dealing.

The following facts are relevant to the resolution of the appeal. On April 8, 2005, the plaintiff and the defendants entered into a contract for the sale of real property owned by the defendants. They agreed that the plaintiff would pay a purchase price of $1.6 million, with a $50,000 deposit paid at signing, of which $25,000 was released immediately to the defendants and the remainder held in escrow. The contract provided that the purchase price would be based on the plaintiff receiving the town approval for the building of between thirteen and sixteen condominium units. If fewer than thirteen units were approved, the purchase price would be reduced by $125,000 per unit fewer than thirteen units, and if greater than sixteen units were approved, the purchase price would be increased by $125,000 per unit in excess of sixteen units. The court found that the parties were aware that the applicable zoning regulations only permitted five units to be built on the subject property and that any changes to the zoning regulations needed to be approved by the local zoning authority. The contract required the plaintiff to pursue the required zoning approvals and gave the plaintiff ninety days to do so, subject to six month extensions at the discretion of the defendants.

Upon expiration of the initial ninety day period, the plaintiff had not yet obtained the necessary approvals, nor did it attempt to terminate the contract; rather, the plaintiff indicated its willingness to proceed. The plaintiff also released to the defendants the remaining $25,000 from escrow. Satisfied that the plaintiff was proceeding in good faith, the defendants approved a *88 six month extension, with a new closing date of March 23, 2006.

The plaintiff intended to pursue zoning approval for the construction of affordable housing on the property and began to monitor the progress of another application for zoning approval of affordable housing at a nearby site. The other application was denied, but the plaintiff nonetheless decided to pursue that option on the subject property. The court found that the plaintiff had commissioned an updated survey and some architectural drawings and performed some other minor activities to prepare for seeking the necessary zoning approvals. The plaintiff did not, however, file an application with the zoning authority, a clear prerequisite to achieving zoning approval.

At a meeting between a representative of the plaintiff and the defendants in February, the defendants’ representative expressed dissatisfaction with the progress made by the plaintiff toward obtaining zoning approval for the site. The plaintiff offered an up-front payment of $625,000 toward the purchase price, which the defendants rejected. In February, the plaintiff notified the defendants that it was considering pursuing an application for affordable housing, and then, on March 13, 2006, the plaintiff notified the defendants that it would pursue the affordable housing strategy. On March 15, 2006, eight days before the new closing date, the defendants’ attorney notified the plaintiff that the defendants immediately were terminating the contract and would seek other potential buyers.

The contract also provided a license for the plaintiff to store equipment on the subject property. On April 20,2006, the defendants gave notice to the plaintiff that its license was revoked, and they requested that the plaintiff remove its personal property. When the plaintiff refused to do so, the defendants brought an entry *? and detainer action in the Superior Court. The action was dismissed without prejudice as procedurally improper.

I

The plaintiff first claims that the court incorrectly interpreted the contract by holding that the contingency provision was both a condition and a contractual promise. The court held that “[t]he duty to pursue the zoning approvals was a promise and the duty to do so with ‘due diligence’ was both a promise and a condition of obtaining any additional extension of the closing date. . . . The effect of the ‘due diligence’ condition was to induce the [plaintiff] to move promptly to obtain the necessary approvals while giving the [defendants] the right to terminate the agreement at the end of any six month extension if the [plaintiff] failed to do so.” (Citation omitted.) The plaintiff argues that the relevant language constitutes a mere condition, the fulfillment of which would have given it the right to enforce the contract, but which imposed no affirmative duty. We disagree.

“We begin by setting forth our standard of review. The standard of review for the issue of contract interpretation is well established. When, as here, there is definitive contract language, the determination of what the parties intended by their contractual commitments is a question of law. . . . Accordingly, our review is plenary. . . . The reviewing court must decide whether [the trial court’s] conclusions are legally and logically correct and find support in the facts that appear in the record.” (Citation omitted; internal quotation marks omitted.) Genua v. Logan, 118 Conn. App. 270, 273-74, 982 A.2d 1125 (2009).

Contract language must be given its plain and ordinary meaning. Article two provides in relevant part: *90 “The [plaintiff] shall, at its sole expense, pursue approvals and obtain permits for the construction of a minimum of (13) condominium units at the Real Property.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

R/C Theatres Management Corp. v. Metro Movies, LLC
44 F. Supp. 3d 626 (D. Maryland, 2014)
Wifiland, LLP v. R.V.C., Inc.
564 F. App'x 612 (Second Circuit, 2014)
Conservation Commission of Fairfield v. Red 11, LLC
43 A.3d 244 (Connecticut Appellate Court, 2012)
ANDY'S OIL SERVICE, INC. v. Hobbs
9 A.3d 433 (Connecticut Appellate Court, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
1 A.3d 234, 123 Conn. App. 84, 2010 Conn. App. LEXIS 355, Counsel Stack Legal Research, https://law.counselstack.com/opinion/land-group-inc-v-palmieri-connappct-2010.