Lampkin Construction Co., Inc. v. Sand Specialties & Aggregates, LLC

179 So. 3d 1095, 2015 Miss. LEXIS 607, 2015 WL 9225099
CourtMississippi Supreme Court
DecidedDecember 17, 2015
Docket2014-CA-01615-SCT
StatusPublished
Cited by1 cases

This text of 179 So. 3d 1095 (Lampkin Construction Co., Inc. v. Sand Specialties & Aggregates, LLC) is published on Counsel Stack Legal Research, covering Mississippi Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lampkin Construction Co., Inc. v. Sand Specialties & Aggregates, LLC, 179 So. 3d 1095, 2015 Miss. LEXIS 607, 2015 WL 9225099 (Mich. 2015).

Opinion

COLEMAN, Justice,

for the Court:

¶ 1. Sand Specialties & Aggregates, LLC, and Lampkin Construction Company entered into a contract under which Sand Specialties was to sell certain sand mining equipment to Lampkin Construction for $350,000.' The equipment was delivered, but the full contract price was never paid. Sand Specialities filed suit against Lamp-kin Construction.' After a trial, the judge entered a directed verdict in favor of Sand Specialities as to ownership of the equipment, and the jury awarded Sand Specialities $92,000 in damages. Lampkin Construction appeals.

FACTUAL BACKGROUND AND PROCEDURAL HISTORY

¶ 2. In January 2012, Sand Specialties, Lampkin Construction, and CSWS Mineral Resources entered into a Sale Agreement under which Sand Specialties agreed to sell gravel and sand-mining equipment to Lampkin Construction and CSWS for $350,000. The agreement was for eleven pieces of equipment; the largest piece of equipment was an Eagle Sand Classifier. Lampkin Construction made the initial payment of $100,000, and the remaining $250,000 would be tendered within thirty days of delivery of the equipment. The Eagle Sand Classifier had been delivered when the contract was signed, and the buyers were to arrange for delivery of the rest of .the equipment. The agreement provided that Sand Specialties would hold title to the equipment until the $350,000 was paid in full and, if the buyers failed to pay,, they were required to return the equipment and forfeit the $100,000 payment. The rest- of the equipment was delivered by the end of January. Lampkin Construction failed to pay the remaining $250,000. Lampkin Construction maintains that it did not receive all of the parts needed for the equipment to work; however, the particular pieces Lampkin Construction, wanted were not listed in the contract.

¶3. In August 2012, Sand Specialities filed a Petition for Replevin and Complaint for Damages against Lampkin Construction, CSWS, and several individuals. Lampkin Construction filed an Answer and Counterclaim, seeking return of its $100,000 payment. Lampkin Construction claimed that the $100,000 payment actually was only, an advance, made on behalf of CSWS and that, when the rest of ,the equipment was delivered, CSWS was to pay Sand Specialties the remaining $250,000 and pay back Lampkin Construction’s $100,000 advance. Lampkin Construction also filed a cross-claim against CSWS. .

¶ 4. The trial court held a hearing on the petition for replevin in January, 2013. In August 2013, the trial court entered an order denying Sand Specialities’ petition, and ruling that Sand Specialities must repay Lampkin Construction’s $100,000 and could retake possession of the equipment at, its own expense. Sand Specialities filed a petition for interlocutory appeal, which the Court denied. In November 2013, Lampkin Construction filed a motion for contempt, alleging that Sand Specialities was in contempt for not paying Lampkin *1098 Construction $100,000 pursuant to the court’s order. Naturally, Sand Specialties opposed the contempt motion, claiming that the order did not set a time by which to comply' and that it was not a final judgment because it did not dispose of all of the issues and parties! Sand Specialties also filed a motion to reconsider, asserting that the trial court should not have awarded monetary damages when it ruled on the replevin action. '

¶ 5. In January 2014, the trial court set' aside its August 2013 order denying the motion for replevin, holding that its “ruling should have been limited to the issues of rightful possession and title.” The trial court entered a new order denying Sand Specialties’ motion for replevin, holding that there were “factual and legal issues requiring adjudication before the writ may issue.” A few months later, Lampkin Construction filed a motion for partial summary judgment, seeking a judgment in its favor on the intentional tort claims and partial summary judgment on the breach-of contract claims. The trial court denied Lampkin Construction’s motion for summary judgment, finding that genuine- issues of fact existed for trial.

¶ 6. Trial was held in July 2014. Brad Robin, owner of Sand Specialities, testified that the equipment had been left out in the open since 2012 and it had deteriorated; he testified that the equipment was now worth about $150,000 less than when it was delivered. Lampkin'Construction objected to the testimony but did not dispute it or offer evidence in the alternative. It appears that all of the' equipment listed in the contract was delivered, however, Lampkin Construction claims that certain pieces that were required to operate the machinery were not delivered. Robin testified that the pieces Lampkin Construction wanted were extra pieces that had been built and added for convenience, and the equipment was functional without them.

¶ 7. Ronnie Lampkin of Lampkin Construction also testified. He claimed that he had paid the $100,000 as an advance to CSWS because he was present when Sand Specialities delivered the Eagle Sand Classifier, and Sand Specialities had demanded payment at that time. Lampkin testified that CSWS could not get $100,000 quickly, so he advanced the money for CSWS from a line of credit, but he did not have anything to do with the agreement between CSWS and Sand Specialties. Several days later, Lampkin received the contract from Sand Specialties that listed Lampkin Construction as a buyer with CSWS. Lampkin claims that he signed the contract only because, if he did not sign it, Sand Specialties would not deliver any more equipment, and he signed it because “they already had [his] $100,000.” Lampkin claims that he was “duped” into signing the agreement and that he signed it “under duress with no basically other choice.” Lampkin Construction has not made any formal claims of fraud or duress.

¶8. After both sides rested, the trial court directed a verdict on the issue of possession and ownership of the equipment and awarded the equipment to Sand Specialties. The ruling was made outside the presence of the jury. Lampkin Construction first asked the court not to tell the jury about the ruling, but then changed its mind and asked the judge to instruct the jury that the court had awarded possession and ownership to Sand Specialties. Lampkin Construction also requested a limiting instruction, which directed the jury that the court’s ruling should not be construed as a finding- for either party on the breach of contract claim or on the issue of damages. The court gave the requested instructions.

*1099 ¶ 9. The jury returned a verdict in favor of Sand Specialties and awarded damages in the amount of $92,000. Lampkin Construction filed a motion for judgment notwithstanding the verdict (JNOV) or for a new trial, which the court denied. Lamp-kin Construction appeals.'

DISCUSSION

¶ 10. Lampkin Construction asks the Court to reverse and order a new trial. Sand Specialties asks the. Court to affirm the trial court’s directed verdict and the jury’s award of damages. Lampkin Construction, raises four assignments of error.

1. Whether the trial court erred in granting a directed verdict as to possession of the equipment.

¶ 11. A trial judge’s decision on a motion for directed verdict is reviewed de novo. Kennedy v. Illinois Cent. R.R. Co., 30 So.3d 333, 335 (¶6) (Miss.2010).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
179 So. 3d 1095, 2015 Miss. LEXIS 607, 2015 WL 9225099, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lampkin-construction-co-inc-v-sand-specialties-aggregates-llc-miss-2015.