Lamoreux v. Langlotz

757 P.2d 584, 1988 Alas. LEXIS 156, 1988 WL 62895
CourtAlaska Supreme Court
DecidedJune 3, 1988
DocketS-2064
StatusPublished
Cited by12 cases

This text of 757 P.2d 584 (Lamoreux v. Langlotz) is published on Counsel Stack Legal Research, covering Alaska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lamoreux v. Langlotz, 757 P.2d 584, 1988 Alas. LEXIS 156, 1988 WL 62895 (Ala. 1988).

Opinion

OPINION

BURKE, Justice.

This appeal raises two questions. The first is whether a developer’s suit to enforce restrictive covenants was premature. The second is whether the superior court erred in enforcing the covenants.

I. FACTS AND PROCEEDINGS

Appellee Robert J. Langlotz is the original subdivider of the Marian Hills Subdivision, which comprises about 20 acres of land in the Fairbanks recording district. In September 1984, he recorded restrictive covenants regulating the use of land in the subdivision.

*585 The covenants restrict the subdivision to residential uses. The minimum dwelling size is 1,000 square feet; for a dwelling with two or more levels, the minimum ground floor area is 800 square feet. The exterior of each dwelling must be completed within two years after construction commences. All dwellings must be constructed and designed in conformance with FHA minimum standards and local building code requirements. No temporary structure may be used as a residence.

In May 1985, appellant Stacy “Sand” La-moreux bought a lot in Marian Hills. He received a copy of the covenants at closing. In August 1985, appellee David Whitmore purchased a neighboring lot.

Lamoreux began building a home on his lot on May 20, 1986. Rather than use a traditional continuous concrete foundation, Lamoreux built a “pad and post” foundation. 1 He then started building the house. The structure was approximately 22.5 feet by 18.5 feet, or 420 square feet.

Langlotz learned of the construction about a week after it began. He visited the site and measured the building. When Langlotz tried to discuss the covenant minimum size requirements with Lamoreux, La-moreux ordered him off the property.

On June 18, Langlotz and Whitmore sued Lamoreux to enjoin him from building a house which does not comply with the covenants. Specifically, they alleged that La-moreux violated the size and FHA minimum standard requirements and was living in a temporary structure. Lamoreux answered, alleging that he had two years to complete the exterior and bring his house into compliance with the size and standard restrictions, and that the covenants did not forbid him from living in the house while he built it.

Following a bench trial, Superior Court Judge James R. Blair entered judgment for Langlotz and Whitmore. Judge Blair ruled that Lamoreux must substantially comply with the minimum size requirements and FHA foundation standards by June 15, 1987. If he does, Lamoreux must then substantially complete the exterior by September 1, 1987. If Lamoreux does not substantially comply with the size and foundation requirements by June 15, he must remove the structure by July 1, or Langlotz may have it removed. 2 This appeal followed.

II. WAS LANGLOTZ’ CLAIM FOR DECLARATORY AND INJUNCTIVE RELIEF RIPE FOR JUDICIAL DETERMINATION?

Lamoreux argues that Langlotz’. claim was not ripe because the covenants gave Lamoreux two years in which to complete the exterior of his dwelling. Langlotz contends that, had he not acted immediately, his claim might well have been barred by the defense of laches. 3

Ordinarily, a cause of action accrues when all the essential elements forming the basis for the claim have occurred. See Russell v. Municipality of Anchorage, 743 P.2d 372, 375 (Alaska 1987); Hanebuth v. Helicopter International, 694 P.2d 143, 146 (Alaska 1984). If a suit is commenced before the claim is ripe, the suit is premature and must be dismissed. See Linck v. Barokas & Martin, 667 P.2d 171, 173-74 (Alaska 1983) (complaint alleged actual present damage and therefore stated valid claim for relief).

Courts sometimes take a different approach when the claimant seeks to enjoin violations of restrictive covenants. For example, when one neighbor sued to enjoin a setback violation four months after the vio *586 lator laid his foundation and began construction, the court ruled that the plaintiff neighbor was guilty of laches. Smith v. Spencer, 81 N.J.Eq. 389, 87 A. 158, 159 (1913). Although plaintiff had immediately informed the violator of the suspected violation and had corresponded extensively with him, the court concluded that plaintiff had a duty to file legal proceedings immediately, before there was a substantial expenditure of money. Id.

Similarly, in McRae v. Lois Grunow Memorial Clinic, 40 Ariz. 496, 14 P.2d 478, 481-82 (1932), the court ruled that plaintiff was guilty of laches when it filed suit to enforce a residential-use-only restriction ten days after defendant began excavation for the foundation. Plaintiff failed to request a temporary restraining order, and defendant completed construction a month before trial. Id. Since injunctive relief was not feasible plaintiff was limited to recovery of damages. Id.

More recent decisions reflect a willingness to allow the complaining neighbor some time to pursue extra-judicial avenues of redress. For example, in Leaver v. Grose, 610 P.2d 1262 (Utah 1980), the court enforced a “single-family dwelling only” restriction against a homeowner who built an apartment in her basement. The court ruled that the homeowner proceeded at her own risk when she continued building after her neighbors complained. Id. at 1264. The neighbors having informed the homeowner of the existence of the controversy, the court ruled that equity did not require them to file suit immediately. Id.

Similarly, in Dickstein v. Williams, 93 Nev. 605, 571 P.2d 1169 (1977), the court enforced a building height restriction. The complaining neighbor learned of the violation in January and filed suit a month later. Id., 571 P.2d at 1170. The court ruled that the complaining neighbor acted diligently and the violating homeowner acted at his own risk after he knew of his neighbor’s complaint. Id. at 1171. Thus, the homeowner was required to remove the offending addition, even though it was completed three months before final judgment was entered. Id.; accord Smith v. Nelson, 149 Colo. 200, 368 P.2d 566 (1962).

We have never addressed this precise issue. However, in City and Borough of Juneau v. Breck, 706 P.2d 313

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dominic Wenzell, D.M.D. P.C. v. Ingrim
228 P.3d 103 (Alaska Supreme Court, 2010)
Kohl v. Legoullon
936 P.2d 514 (Alaska Supreme Court, 1997)
Mariscal v. Watkins
914 P.2d 219 (Alaska Supreme Court, 1996)
Wright v. Wright
904 P.2d 403 (Alaska Supreme Court, 1995)
Kalenka v. Taylor
896 P.2d 222 (Alaska Supreme Court, 1995)
Arizona Biltmore Estates Ass'n v. Tezak
868 P.2d 1030 (Court of Appeals of Arizona, 1993)
Shaw v. State, Department of Administration
861 P.2d 566 (Alaska Supreme Court, 1993)
Gordon v. Brown
836 P.2d 354 (Alaska Supreme Court, 1992)
Ogle v. Craig Taylor Equipment Co.
761 P.2d 722 (Alaska Supreme Court, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
757 P.2d 584, 1988 Alas. LEXIS 156, 1988 WL 62895, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lamoreux-v-langlotz-alaska-1988.