Lambert Gravel Company, Inc. v. J.A. Jones Construction Company

835 F.2d 1105, 1988 WL 281
CourtCourt of Appeals for the Fifth Circuit
DecidedFebruary 8, 1988
Docket87-4008
StatusPublished
Cited by4 cases

This text of 835 F.2d 1105 (Lambert Gravel Company, Inc. v. J.A. Jones Construction Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lambert Gravel Company, Inc. v. J.A. Jones Construction Company, 835 F.2d 1105, 1988 WL 281 (5th Cir. 1988).

Opinion

CAROLYN DINEEN KING, Circuit Judge:

Lambert Gravel Company, Inc. appeals from the district court’s grant of J.A. Jones Construction Company’s motion for partial summary judgment on Lambert’s claims for an equitable price adjustment and additional costs incurred during the performance of its contract to provide sand and fine concrete aggregate to Jones. Finding no error in the district court’s decision, we affirm.

I.

In December of 1979, J.A. Jones Construction Company (“Jones”), a general contractor, entered into an agreement (“Prime Contract”) with the United States Army Corps of Engineers (“Corps”) to construct a portion of “the elaborate and massive lock and dam improvements on the Red River” in the southern tip of Catahou-la Parish, Louisiana (“the Project”). The Project involved the construction of (1) a channel and lock across the neck of an oxbow loop in the river to shorten the river’s course for navigation (“Construction Project”) and (2) an earthen dam (“Closure Dam”) at the upper end of the oxbow loop to close the loop and divert the river through the new channel and lock. In the Prime Contract, Jones was required to backfill the lock structure with a specified *1107 quantity of “select sand.” 1 In July of 1980, Lambert Gravel Company, Inc. (“Lambert”) signed a purchase order contract with Jones (“Lambert Contract”) in which it agreed to supply select sand and fine concrete aggregate for the Construction Project. 2 The Lambert Contract incorporated by reference all the provisions, specifications, maps, and drawings of the Prime Contract.

The Prime Contract also required Jones to provide sand fill for the Closure Dam after the lock was built. The fill material for the Closure Dam was specified to be “a sandy material from the existing streambed as shown on the drawings and as directed by the Contracting Officer.” On the left descending bank of the river in the upper end of the oxbow loop there was a large sand bar (“Disputed Bar”) which was shown on the appropriate plan sheets as blocked by a right-of-way line and captioned “Borrow Area for Closure Dam (sand fill).” The Disputed Bar lay below the high water mark of the river. Lambert was aware of the legend printed over the Disputed Bar on the plan sheets.

To fulfill its obligation to provide fill materials, Lambert entered into a surface lease agreement with Louisiana Delta Plantation (“Delta”), the owner of the land riparian to the Disputed Bar. Under the lease agreement, Delta granted Lambert the right to extract sand from the Disputed Bar. Lambert began extracting that sand in August of 1980. Lambert’s activities did not go unnoticed and, on May 12, 1981, the Corps notified Jones by letter that Lambert was extracting sand from a reserved “borrow area.” The letter stated that “[i]n accordance with [the] drawings, the material in this borrow area is to be used for the Closure Dam. Contrary to the drawings you and your supplier are using this material for something other than the Closure Dam.” 3 The letter ended by commanding Jones and its “supplier” to cease operations in the area immediately. Jones’ project manager wrote Lambert immediately and directed Lambert to stop removing sand from the Disputed Bar and seek suitable materials elsewhere. 4 Lambert was also furnished with a copy of the Corps’ letter. A few days later, Lambert acknowledged receipt of the order directing it to stop removing sand from the Disputed Bar. In its acknowledgement letter to Jones, Lambert protested the order and promised to take legal action against Jones for its “breach of contract.” While Lambert *1108 agreed to abide by the order, it reserved all legal rights and claims it might have against Jones and stressed its exclusive rights to the sand from the Disputed Bar. That same day, Lambert wrote a similar letter of protest to the Corps. By a letter dated May 29, 1981, Jones offered to “make available to [Lambert] all of the contract rights that exist in [the Prime Contract] to dispute this directive and to file a claim for additional compensation.” Lambert declined this invitation to seek legal recourse against the Corps through Jones as prime contractor.

Cognizant of the fact that no further materials would be accepted from the Disputed Bar, Lambert sought and eventually secured an alternate source of materials, approximately seven miles further away. Prior to securing this alternate excavation site, Lambert was forced to procure an interim source of materials, some thirty miles further away, from which to satisfy its obligations under the Lambert Contract. Upon completion of operations, Lambert calculated its additional costs and expenses occasioned by its ouster from the Disputed Bar and served “notice of its damages” on Jones. Lambert claimed to have incurred additional costs in the amount of $2,153,-148.00.

Pursuant to the Miller Act, 5 Lambert filed a civil action in the United States District Court for the Western District of Louisiana against Jones and its six sureties. 6 Lambert subsequently filed its “Amended and Supplemental Complaint” on January 17, 1985. As summarized by the district court, Lambert presented four claims: (1) a claim for the payment of six unpaid invoices, in the sum of $7,625.81, representing materials delivered to Jones which were not paid for (“invoice claim”); (2) a claim for payment of the retainage balance, amounting to $20,812.50, representing a percentage of the price of materials delivered to Jones (“retainage claim”); (3) a claim for alleged increased costs of materials delivered to Jones, including increased production costs amounting to $720,328.00 and additional equipment costs of $1,432,820.00, all totalling $2,153,148.00 (“increased costs claim”); and (4) a claim for payment of the unit contract price under Lambert’s lease agreement with Louisiana Delta Plantation for sand allegedly removed from the sand bar by Jones’ subcontractor after Lambert was ordered to cease mining operations on the sand bar, which claim amounted to $6,210,000.00 (“unit price claim”).

On September 24, 1985, Jones filed a motion for summary judgment. Lambert responded with its own motion for summary judgment on October 28, 1985. The district court held a hearing on the parties’ motions on February 3, 1986. During the hearing, Lambert’s counsel correctly pointed out that the invoice and retainage claims would not be affected by either motion. Therefore, the district court treated the motions as ones for partial summary judgment. On April 3, 1986, the district court entered a judgment granting Jones' motion for partial summary judgment. The district court concluded that since the Disputed Bar lay below the high water mark of the river, it was subject to the federal navigational servitude. The district court found that Congress neither intended to forego the servitude completely with respect to the Project, nor authorized the Corps to waive the servitude. Therefore, the Corps had the right in the instant case to bar Lambert from extracting sand from the Disputed Bar.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Palm Beach Isles Associates v. United States
42 Fed. Cl. 340 (Federal Claims, 1998)
Opinion Number
Louisiana Attorney General Reports, 1996

Cite This Page — Counsel Stack

Bluebook (online)
835 F.2d 1105, 1988 WL 281, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lambert-gravel-company-inc-v-ja-jones-construction-company-ca5-1988.