Lalangan v. Pennington

District Court, D. Arizona·Decided July 13, 2022·No. 4:20-cv-00292·Unknown

Opinion

WO

Ireno Lalangan, No. CV-20-00292-TUC-JCH

Plaintiff, ORDER

v.

Greg Pennington, et al.,

Defendants. This case concerns a contract for the sale and installation of 75 HVAC units at two apartment complexes in Sierra Vista, Arizona. (Doc. 22.) On April 13, 2022, the Court entered an Order determining that Plaintiff was entitled to an award of $85,500.00 in contract damages. (Doc. 44.) On June 28, 2022, the Court held an evidentiary hearing on Plaintiff’s claim for an award of lost profit damages and took the matter under advisement. (Doc. 45.) On July 7, 2022, Plaintiff moved for an award of attorney’s fees and costs. (Doc. 48.) The Court now rules. On March 9, 2018, Plaintiff and Defendant Pen-Tek LLC entered into a contract for the purchase and installation of 75 HVAC units that were to be installed at Plaintiff’s two apartment complexes in Sierra Vista, Arizona. At the evidentiary hearing, Plaintiff testified that he purchased the two apartment complexes in 2018. The two apartment complexes have a combined occupancy of 440 units. The apartment complexes had a 70% occupancy rate at the time Plaintiff purchased them. The contract provides, inter alia, that “Pen-Tek LLC will install [the 75 HVAC] units over the next 24 months when [it is] notified of which units need to be replaced.” (Doc. 22 at 12.) Plaintiff testified that at the end of the two year period only 30 HVAC units had been replaced. Plaintiff initially testified that when he entered into the contract, none of the 75 HVAC units that were to be replaced were working. On further questioning, Plaintiff testified that when he entered into the contract some of the 75 HVAC units that were to be replaced under the contract were functioning. However, on additional questioning, Plaintiff changed his testimony again and claimed that when he entered into the contract all of the 75 HVAC units that were contemplated to be replaced under the contract were not working. In his Amended Sum Certain Affidavit Pursuant to Rule 55(b)(1), Plaintiff avowed that “[w]hen the remaining HVAC units were not installed, tenants canceled leases and the rental units could not be leased again without operating HVAC units.” (Doc. 43 at 3, ¶ 8.) Consistent with his affidavit, Plaintiff testified that he has been unable to rent 45 apartment units because they do not have air conditioning as a result of Defendants’ failure to replace the HVAC units in the 45 apartment units. However, Plaintiff offered no explanation for the claimed simultaneous termination of 45 leases. Plaintiff testified that he spoke with Defendant Greg Pennington about the replacement of the HVAC units during the course of performance of the contract. Plaintiff testified that he told Greg Pennington that he was losing $750.00 per month for two- bedroom apartment units and $650.00 per month for one-bedroom units as a result of Pen- Tek LLC’s failure to replace the HVAC units. Relying upon information contained in exhibit 8,1 Plaintiff testified that his gross receipts for the rental of 30 two-bedroom apartment units for 26 months would have been $585,000.00 and that his gross receipts for the rental of 15 one-bedroom apartment units for 26 months would have been $253,000.00. Paul Lalangan, Plaintiff’s son, also testified. 1 Although Plaintiff did not move for the admission of any exhibit that he offered at the evidentiary hearing, the Court will refer to an exhibit that was discussed at the hearing when relevant to this Order. Mr. Paul Lalangan testified that he is familiar with the books and records of the two apartment complexes in issue. He testified that the two apartment complexes have a higher than normal vacancy rate as a result of many apartment units needing work, including needing HVAC units. Mr. Paul Lalangan testified that after his review of the books and records of the company for the year 2021, the operating expenses for the two apartment units were 46% of gross income. “The well-established rule in Arizona is that the damages for breach of contract are those which arise naturally from the breach itself or which may reasonably be supposed to have been within the contemplation of the parties at the time they entered into the contract.” S. Ariz. School for Boys, Inc. v. Chery, 580 P.2d 738, 741 (Ariz. App. Div. 2 1978). “Referred to as ‘expectation damages,’ contract damages are most often based on the party’s expected value of the contract that was unfulfilled due to the other party’s nonperformance.” Moore v. First Transit Bus Co., No. CV-20-00790-PHX-JJT, 2020 WL 9347648, at *2 (D. Ariz. Sept. 23, 2020). Lost profit damages are available for breach of contract if they are within the contemplation of the parties. See Short v. Riley, 724 P.2d 1252, 1254-55 (Ariz. App. Div. 2 1986) (lost profits sustained as damages naturally flowing from breach of contract and within contemplation of parties). Plaintiff hass not established that he is entitled to an award of lost profits for two reasons. First, there is insufficient evidence that lost profit damages were contemplated by the parties at the time of contracting. Second, the fact and amount of lost profits have not been sufficiently established. a. There is Insufficient Evidence that at the Time of Contracting the Parties Contemplated an Award of Lost Profit Damages “Arizona law comports with general principles of contract which dictate that ‘[d]amages are not recoverable for loss that the party in breach did not have reason to foresee as a probable result when the contract was made.’” Arizona Precious Metals, Inc. v. Accept Erste Rohstoff Beteiligungs KG, 407 Fed. Appx. 216, 217 (D. Ariz. Jan. 3, 2011) (quoting RESTATEMENT (Second) of Contracts § 351 (1981)). No evidence was presented on the parties’ negotiations prior to entering into the contract. Plaintiff testified that he called Greg Pennington during the course of the performance of the contract and told him that he was losing $750.00 per month for two-bedroom units and $650.00 per month for one-bedroom units as a result of Pen-Tek’s failure to perform. Because no evidence was presented on the parties’ negotiations prior to entering into the contract and the contract is silent on either parties’ remedies in the event of a breach, the Court finds Plaintiff is not entitled to an award of lost profit damages under Arizona law. b. The Fact and Amount of Lost Profit Damages are not Sufficiently Established Arizona law does not provide for the recovery of damages unless they are reasonably certain. Hubbard v. Shelton, No. CV-08-623-TUC-DCB, 2011 WL 13183092, at *7 (D. Ariz. Nov. 23, 2011) (citing Rancho Pescado, Inc. v. Northwestern Mut. Life Ins. Co., 680 P.2d 1235, 1244 (Ariz. App. Div. 1 1984)). “Courts will award damages for loss of profits in an established business ... if they are proved with certainty. Such certainty is provided where the plaintiff devises some reasonable method of computing his net loss.” Hubbard, 2011 WL 13183092, at *7 (quoting Liniger v. Dine Out Corp., 639 P.2d 350, 352-53 (Ariz. Capp. Div. 2 1981)). “The requirement of ‘reasonable certainty’ in establishing the amount of damages applies with added force where a loss of future profits is alleged.” Hubbard, 2011 WL 13183092, at *7 (quoting Gilmore v. Cohen, 386 P.2d 81, 83 (Ariz. 1963)). It is “well settled that conjecture or speculation cannot provide the basis for an award of damages. The evidence must make an approximately accurate estimate possible.” Hubbard, 2011 WL 13183092, at *7 (quoting Rancho Pescado, 680 P.2d at 1247). Plaintiff testified that at the time he purchased the two apartment complexes in 2018, the complexes had a combined total of 440 apartment units and a combined occupancy rate of 70%. In other words, the two complexes had

Free access — add to your briefcase to read the full text and ask questions with AI

Lalangan v. Pennington, (D. Ariz. 2022).

Lalangan v. Pennington (Lalangan v. Pennington) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Gilmore v. Cohen
386 P.2d 81 (Arizona Supreme Court, 1963)
State v. Solano
724 P.2d 17 (Arizona Supreme Court, 1986)
Rancho Pescado, Inc. v. Northwestern Mutual Life Insurance
680 P.2d 1235 (Court of Appeals of Arizona, 1984)
Cox v. Mountain Vistas, Inc.
639 P.2d 12 (Idaho Supreme Court, 1981)