Lakloey, Inc. v. University of Alaska

141 P.3d 317, 2006 Alas. LEXIS 90, 2006 WL 1720080
Alaska Supreme Court·Decided June 23, 2006·No. S-11624·Published·Cited by 2 cases

Opinion

OPINION

EASTAUGH, Justice.

I. INTRODUCTION

The University of Alaska Fairbanks issued an addendum to a bid solicitation on the day scheduled for opening bids and after Lak-loey, Inc. had submitted its bid. Lakloey filed a bid protest that argued that irregularities in the bidding process entitled it to recover its bid preparation costs. The university eventually rejected all bids as exceeding.project funds and then denied Lakloey’s bid protest. When Lakloey appealed, the superior court rejected Lakloey’s argument that it was denied due process, and affirmed the university’s decision.

Because Lakloey has neither argued nor demonstrated that any bidding irregularities wasted costs already expended in bid prepa *319 ration or caused it to incur additional costs, we affirm the denial of its claim for bid preparation costs.

II. FACTS AND PROCEEDINGS

On March 5, 2003 the University of Alaska published a “Notice of Invitation for Bids” for improving an existing facility at the Yukon Flats Training Center Extension (YUTE) and for other miscellaneous work. Bids were to be opened at 2:00 p.m. on March 20. The Instructions to Bidders explained the procedure for submission and evaluation of bids. The instructions also specified that addenda to the bid solicitation would be issued no later than the day before the scheduled bid opening, and that additional time would be granted to submit bids if an addendum were issued within one week of the scheduled bid opening. 1

Lakloey, Inc. submitted a bid before 2:00 p.m. on March 20. Also before 2:00 p.m. on March 20, but after Lakloey submitted its bid, the university issued Addendum #2. Addendum #2 changed several bid criteria and adjusted the amount of required builder’s insurance from $1.5 million to the “Value of Completed Project.” It also changed the date for the bid opening from March 20 to April 1.

On March 24 Lakloey sent the university a protest letter that alleged that Addendum #2 violated “the conditions of the solicitation, the procurement regulations of the University, [and] the procurement code of the State of Alaska.” The protest also argued that Addendum # 2 was “without merit” and speculated that the addendum might “represent the expression of a conflict of interest.” Lakloey requested that only those parties who had submitted bids before the university issued Addendum #2 be allowed to submit bids for the project as modified by the addendum. Lakloey alternatively requested that the entire solicitation be cancelled and that Lakloey be awarded its bid preparation costs.

The university procurement officer rejected Lakloey’s protest on March 28. Her rejection letter stated that Addendum #2 violated neither the applicable university regulations nor the state procurement code, and that the instructions’ representation concerning the timing and content of addenda was not binding on the procurement officer.

By letter of March 31 Lakloey appealed the procurement officer’s denial of its protest. Lakloey’s appeal argued that Addendum #2 (1) violated the instructions to bidders; (2) violated AS 36.30.150(a) by introducing a “subjective and nebulous” insurance requirement; (3) violated AS 36.30.130(a)’s requirement that any determination that a shortened bidding period is advantageous be in writing; and (4) had theoretically reduced competition.

On April 1 — the bid opening date set by Addendum #2 — Lakloey submitted another bid. On April 10 the university notified Lak-loey that the bids of Lakloey and its sole competitor (Nenana Lumber) exceeded project funds and were therefore rejected.

Because the university concluded that there were no contested issues of material fact, it decided Lakloey’s protest appeal without a hearing. The university concluded that (1) Lakloey had received the relief it requested because only it and Nenana Lumber submitted bids by Addendum # 2’s deadline; (2) the appeal was moot because Lakloey was not the apparent low bidder and would not have been awarded the contract; (3) Lakloey was not an “interested party” under AS *320 36.30.699; 2 (4) Lakloey could not raise new issues on appeal; (5) Lakloey’s protest was vague and non-specific; and (6) the instructions were superseded by state law and university regulations.

Lakloey filed a superior court appeal from the denial of its bid protest. Lakloey also argued that the university violated Lakloey’s due process rights by deciding its appeal without a hearing.

The superior court rejected each of Lak-loey’s arguments. It pointed out that under the instructions, Lakloey could have asked the university for clarification or interpretation of the allegedly ambiguous term “Value of Completed Project.” The court, observing that the university rejected Lakloey’s bid because it exceeded the amount budgeted for the project, could not find a connection between Addendum # 2 and the disparity. The court also noted the lack of causation between the university’s non-compliance with AS 36.30.130 and any damages Lakloey might have suffered. It therefore affirmed the university’s decision.

Lakloey appeals.

III. DISCUSSION

A. Standard of Review

When the superior court acts as an intermediate court of appeal, we review its decision de novo. 3 We use two standards of review when reviewing the statutory interpretation of administrative agencies. When statutory interpretation “involves agency expertise or the determination of fundamental policies within the agency’s statutory function,” we use the “rational basis” test. 4 But “when the statutory interpretation does not involve agency expertise, or the agency’s specialized knowledge and experience would not be particularly probative,” we substitute our own judgment. 5

B. Lakloey Is Not Entitled to Its Bid Preparation Costs.

Lakloey argues that AS 36.30.585 entitles it to recover its bid preparation costs. Subsection .585(a) provides that “[i]f the procurement officer sustains a protest in whole or in part, the procurement officer shall implement an appropriate remedy.” 6 Subsection .585(c) limits a successful bid protester’s damages “to reasonable bid or proposal preparation costs.”

In King v. Alaska State Housing Authority we held that a bid solicitation is not an offer, but merely “a request for offers.” 7 A bid solicitation does, however, create an obligation to consider all bids fairly and honestly. 8 We concluded that

in exchange for a bidder’s investment of the time and resources involved in bid preparation, a government agency must be held to an implied promise to consider bids *321

Free access — add to your briefcase to read the full text and ask questions with AI

Lakloey, Inc. v. University of Alaska, 141 P.3d 317, 2006 Alas. LEXIS 90, 2006 WL 1720080 (Ala. 2006).

141 P.3d 317 (Lakloey, Inc. v. University of Alaska) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Stanley v. Lemire
2006 MT 304 (Montana Supreme Court, 2006)