Lakeshore Investment LLC v. Now Solutions, Inc.

California Court of Appeal·Decided August 24, 2026·No. B343435·Published

Opinion

Filed 8/24/26 (see dissenting opinion)

CERTIFIED FOR PUBLICATION

IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA

SECOND APPELLATE DISTRICT

DIVISION EIGHT

LAKESHORE INVESTMENT LLC, B343435

Plaintiff and Respondent, (Los Angeles County Super. Ct. No. 19STCV15381)

v.

NOW SOLUTIONS, INC, et al.,

Defendants and Appellants.

APPEAL from a post-judgment order of the Superior Court of Los Angeles County, Tony L. Richardson, Judge. Reversed with directions.

TencerSherman and Philip C. Tencer for Defendants and Appellants.

Gilbert & Nguyen and Jonathan T. Nguyen for Plaintiff and Respondent.

INTRODUCTION

This case addresses the enforceability of a liquidated damages provision within a settlement agreement. Plaintiff Lakeshore Investments (Lakeshore) and Defendants NOW Solutions, Inc. and Vertical Computer Systems (together, NOW) entered into an agreement to settle a lawsuit Lakeshore had brought against NOW Solutions, Inc. The settlement agreement provided that if defendants defaulted on their promise to pay $450,000, they had to pay plaintiff $1.5 million as damages for breaching the settlement agreement. Defendants failed to pay as required. The trial court granted plaintiff’s application for an order that defendants pay $1.5 million for the breach, plus interest. On appeal, defendants argue the $1.5 million represents an unenforceable penalty rather than plaintiff’s true liquidated damages as required by law. We agree and reverse the trial court’s order with directions to determine an amount that represents plaintiff’s damages for the breach.

FACTUAL AND PROCEDURAL BACKGROUND A. The Complaint On January 9, 2013, plaintiff Lakeshore Investments loaned $1,759,000 to NOW Solutions Inc. The loan was documented in a promissory note with an interest rate of 11 percent, secured by an agreement pledging as collateral NOW Solutions’s intellectual property. NOW Solutions defaulted on the loan, leading to eight amendments to the payment schedule. The last amendment dated December 11, 2017, added Vertical Computer Systems (NOW Solutions’s parent company) as a codebtor and guarantor. This amendment set a monthly payment at $31,564 and raised the default interest rate to 16 percent.

On May 2, 2019, Lakeshore filed a complaint alleging defendants breached the promissory note and security agreement by failing to remit the required monthly payments since January 2018. The complaint sought damages for breach of contract. The prayer for relief sought general, consequential and special damages; prejudgment interest from January 9, 2013, legal fees and costs. B. The Settlement Agreement On November 3, 2023, counsel for the parties reported the parties had entered into a written Settlement Agreement and Mutual Release. Defendants agreed to pay plaintiff $450,000 in three installments over a period of approximately 10 months. The first installment of $30,000 was due on or before December 1, 2023; the second installment of $50,000 was due on or before March 31, 2024; and the third installment of $370,000 was due on or before September 30, 2024. (Plaintiff took on obligations as well which it fully performed.) Defendants admitted no liability with respect to the allegations of the complaint. All parties were represented by counsel who reviewed and approved the agreement as to form. The Settlement Agreement provided that if defendants failed to timely pay an installment and failed to cure the default within 10 business days of receiving a notice to cure, plaintiff would be entitled to a stipulated judgment for damages in the amount of $1.5 million plus interest at the legal rate. The pertinent language of the Settlement Agreement for our purposes is the following: “Defendants shall have ten (10) business days from the date of e-mail notice to cure the default. At any time after the tenth business day following the notice of default, Plaintiff may notify the court of the default. In the event Defendants default, and such default is not cured within ten (10)

business days, Defendants hereby agree and stipulate to the entry of a judgment against them in the amount of $1,500,000 (one million, five hundred thousand dollars) to bear interest at the legal rate.”

Defendants timely paid $80,000. They failed, however, to pay the remaining balance due of $370,000 and failed to cure the default after receiving the required notice. C. Hearing and Entry of Judgment On November 1, 2024, Plaintiff filed an ex parte application for entry of default and default judgment. On November 5, 2024, defendants filed written opposition to plaintiff’s application for entry of default. Defendants argued the proposed judgment of $1.5 million “is an unenforceable penalty because the amount claimed bears no relationship to the damages Lakeshore could have suffered resulting from failure to pay the original settlement amount.” On November 6, 2024, the parties appeared and argued the application for default and default judgment, which the trial court granted. The court made no specific findings in its judgment other than, “The Court is satisfied with the supporting evidence demonstrating Defendants’ default on October 1, 2024.” Defendants timely appealed.

DISCUSSION

On appeal, defendants argue the trial court erroneously enforced the stipulated damages award of $1.5 million in the settlement agreement, which constitutes an unlawful penalty under California law. We agree.

A. Applicable Law Civil Code section 1671, subdivision (b) provides: “[A]

provision in a contract liquidating the damages for the breach of the contract is valid unless the party seeking to invalidate the provision establishes that the provision was unreasonable under the circumstances existing at the time the contract was made.”

“A liquidated damages clause will generally be considered unreasonable, and hence unenforceable under [Civil Code] section 1671[, subdivision] (b), if it bears no reasonable relationship to the range of actual damages that the parties could have anticipated would flow from a breach. The amount set as liquidated damages ‘must represent the result of a reasonable endeavor by the parties to estimate a fair average compensation for any loss that may be sustained.’ [Citation] In the absence of such relationship, a contractual clause purporting to predetermine damages ‘must be construed as a penalty.’ ” (Ridgley v. Topa Thrift & Loan Assn. (1998) 17 Cal.4th 970, 977 (Ridgley); Morris v. Redwood Empire Bancorp (2005) 128 Cal.App.4th 1305, 1314; Greentree Financial Group, Inc. v. Execute Sports, Inc. (2008) 163 Cal.App.4th 495, 499 (Greentree Financial).) The “amount of the judgment must reasonably relate to the damages likely to arise from the breach of the stipulation, not the alleged breach of the underlying contract, because it is the breach of the stipulation that allows” judgment to be entered against the defaulting party. (Vitatech Internat., Inc. v. Sporn (2017) 16 Cal.App.5th 796, 810 (Vitatech); Greentree Financial, at p. 499 [the relevant breach to be analyzed is the breach of the stipulation, not the breach of the underlying contract].)

When a stipulated judgment amount is not reasonably related to damages arising solely from the failure to pay the stipulated judgment, it constitutes an unenforceable penalty. (Purcell v. Schweitzer (2014) 224 Cal.App.4th 969, 974 (Purcell).) B. Standard of Review Whether “the amount to be paid upon breach of a contractual term should be treated as liquidated damages or as an unenforceable penalty is a question of law, which we review de novo.” (Greentree Financial, supra, 163 Cal.App.4th at p. 499.)

Free access — add to your briefcase to read the full text and ask questions with AI

Lakeshore Investment LLC v. Now Solutions, Inc., (Cal. Ct. App. 2026).

Lakeshore Investment LLC v. Now Solutions, Inc. (Lakeshore Investment LLC v. Now Solutions, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Garrett v. Coast & Southern Federal Savings & Loan Ass'n
511 P.2d 1197 (California Supreme Court, 1973)
Ridgley v. Topa Thrift & Loan Assn.
953 P.2d 484 (California Supreme Court, 1998)
Sybron Corp. v. Clark Hospital Supply Corp.
76 Cal. App. 3d 896 (California Court of Appeal, 1978)
In Re Marriage of Friedman
122 Cal. Rptr. 2d 412 (California Court of Appeal, 2002)
Greentree Financial Group, Inc. v. Execute Sports, Inc.
163 Cal. App. 4th 495 (California Court of Appeal, 2008)
Morris v. Redwood Empire Bancorp
27 Cal. Rptr. 3d 797 (California Court of Appeal, 2005)
Zengen, Inc. v. Comerica Bank
158 P.3d 800 (California Supreme Court, 2007)
Purcell v. Schweitzer CA4/1
224 Cal. App. 4th 969 (California Court of Appeal, 2014)
Krechuniak v. Noorzoy
11 Cal. App. 5th 713 (California Court of Appeal, 2017)
Egedi v. Egedi
88 Cal. App. 4th 17 (California Court of Appeal, 2001)
Vitatech Int'l, Inc. v. Sporn
224 Cal. Rptr. 3d 691 (California Court of Appeals, 5th District, 2017)