Lake Wylie Water Resources Protective Ass'n v. Rodgers Builders, Inc.

621 F. Supp. 305, 1985 U.S. Dist. LEXIS 14752
CourtDistrict Court, D. South Carolina
DecidedOctober 21, 1985
DocketCiv. A. 85-856-15
StatusPublished

This text of 621 F. Supp. 305 (Lake Wylie Water Resources Protective Ass'n v. Rodgers Builders, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lake Wylie Water Resources Protective Ass'n v. Rodgers Builders, Inc., 621 F. Supp. 305, 1985 U.S. Dist. LEXIS 14752 (D.S.C. 1985).

Opinion

ORDER

HAMILTON, District Judge.

The plaintiff, an unincorporated association of property owners, brought this action to prevent the defendant Rodgers Builders, from conducting dredging opera *306 tions and constructing a boat docking facility for ten boats at Lake Wylie in Clover, South Carolina. Plaintiff originally claimed violations of the Federal Clean Water Act, 33 U.S.C. § 1251 et seq., and the Rivers and Harbors Act of 1899, 33 U.S.C. § 403, arising from Rodgers Builders’ failure to obtain all requisite state and federal permits. Plaintiff further alleged that neither Rodgers Builders, nor any appropriate governmental body, had prepared an environmental impact statement (hereinafter “EIS”) as purportedly required by law. See the National Environmental Policy Act, 42 U.S.C. § 4321 et seq. (hereinafter “NEPA”). Although this court originally entered a preliminary injunction restraining Rodgers Builders from continuing operations because the appropriate permits had not yet been obtained, on August 27, 1985, this court dissolved the preliminary injunction on the ground that, by that date, all necessary permits had been obtained. 1 Also on August 27, 1985, the court granted plaintiff leave to amend its complaint to name the United States Army Corps of Engineers (hereinafter “Engineers”) as a party defendant. The plaintiff alleged that the Engineers erred in issuing a permit without the preparation of an EIS. On the same date, Rodgers Builders moved for summary judgment. The court concluded, however, that Rodgers Builders’ motion should be held in abeyance until the Engineers had been served and could participate in the litigation on the merits of the suit.

On September 13, 1985, the plaintiff filed a motion for preliminary injunction to restrain Rodgers Builders from proceeding with dredging and construction operations until a final determination of this lawsuit. See Fed.R.Civ.P. 65(a). Basically, the plaintiff argues that because the permit issued by the Engineers was allegedly issued without compliance with NEPA, the permit is invalid. Further, counsel for plaintiff advised this court on October 8, 1985, that Rodgers Builders had already resumed dredging and construction activities. 2 The plaintiff thus argues that its members will suffer irreparable injury if further construction activities are not enjoined. On September 26, 1985, the defendant Engineers submitted its memorandum in opposition to plaintiff’s motion for preliminary injunction. 3 The Engineers contend that it fully complied with NEPA, and all applicable regulations, in issuing the permit to Rodgers Builders. This court held a hearing on plaintiff’s motion for a preliminary injunction on October 11, 1985.

Notwithstanding that the court has been informed that the dredging and construction activities at issue here may have reached an advanced stage of completion, the court concludes that this does not render plaintiff’s motion for a preliminary injunction moot. This court retains the equitable power to order the removal of all offending materials should plaintiff prevail on its motion for a preliminary injunction. See Richland Park Homeowners Association v. Pierce, 671 F.2d 935 (5th Cir.1982); Columbia Basin Land Protection Association v. Schlesingner, 643 F.2d 585 (9th Cir.1981). In Columbia Basin the court concluded that although towers and electric transmission lines had been in operation for several years, the responsible agency might still have to correct the decision-making process and remove the lines if the court found the EIS to be inadequate. Thus, this court will proceed to review the merits of plaintiff’s motion.

In this circuit the standard for interlocutory injunctive relief is the “balance-of-hardship” test set out in Blackwelder Furniture Co. v. Seilig Manufacturing Co., 550 F.2d 189, 196 (4th Cir.1977). This test *307 requires a “flexible interplay” among four factors: the likelihood of irreparable harm to the plaintiff if the preliminary injunction is denied; the likelihood of harm to the defendant if the requested relief is granted; the likelihood that plaintiff will succeed on the merits; and the public interest. The award of a preliminary injunction is, however, an extraordinary remedy, to be granted only if the moving party clearly establishes entitlement to the relief sought. Federal Leasing v. Underwriters of Lloyds, 650 F.2d 495 (4th Cir.1981).

Blackwelder directs that this court’s first task is to balance the likelihood of irreparable harm to the plaintiff against the likelihood of harm to the defendant. Id. at 196. “If that balance is struck in favor of plaintiff, it is enough that grave or serious questions are presented; and plaintiff need not show a likelihood of success.” Id. Conversely, a weaker showing of irreparable injury to the plaintiff will necessitate a stronger showing of probability of success; and if irreparable injury is merely “possible,” probability of success may be decisive. Id. at 195-96.

In determining whether this project poses the requisite irreparable injury to the plaintiff’s members, or indeed to the environment, this court is mindful of plaintiff’s counsel’s own admission, in arguing the mootness aspect, see ante, that the completed work could be undone if necessary. Thus, plaintiff’s protestations of great and imminent irreparable injury are undercut somewhat when considered against the facility with which this project could be reversed. This court also notes the relatively small magnitude of the operation here; the proposed operation is to accommodate only ten boats. Further, in assessing the degree of irreparable injury threatening plaintiff, this court cannot ignore the reports of the various federal and state agencies, detailed below, that the proposed project would not significantly affect the environment. Thus, the court is hard pressed to find considerable support for plaintiff’s claims of irreparable injury.

There is evidence that the issuance of the preliminary injunction threatens injury to the defendant Rodgers Builders. The affidavit of T.L.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
621 F. Supp. 305, 1985 U.S. Dist. LEXIS 14752, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lake-wylie-water-resources-protective-assn-v-rodgers-builders-inc-scd-1985.