Lake Ozark/Osage Beach Joint Sewer Board v. Missouri Department of Natural Resources

326 S.W.3d 38, 2010 Mo. App. LEXIS 1109
CourtMissouri Court of Appeals
DecidedAugust 31, 2010
DocketNo. WD 71299
StatusPublished
Cited by6 cases

This text of 326 S.W.3d 38 (Lake Ozark/Osage Beach Joint Sewer Board v. Missouri Department of Natural Resources) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lake Ozark/Osage Beach Joint Sewer Board v. Missouri Department of Natural Resources, 326 S.W.3d 38, 2010 Mo. App. LEXIS 1109 (Mo. Ct. App. 2010).

Opinion

JAMES EDWARD WELSH, Judge.

The Missouri Land Reclamation Commission, under the Missouri Department of Natural Resources (referred to collectively as “the Commission”), approved Magruder Limestone Company’s application for a permit to expand its quarry operations. The Joint Sewer Board for the cities of Lake Ozark and Osage Beach and thirty-two citizens opposed the expansion permit and sought judicial review of the Commission’s decision in the circuit court. The circuit court reversed the Commission’s decision after finding that the Commission placed the burden of proof on the wrong party, improperly relied upon evidence outside the record, and erroneously determined that Magruder’s application was complete when it was originally filed. Ma-gruder and the Commission appeal.1 We reverse the Commission’s decision and remand the cause for a new hearing.

Magruder operates several quarries under a Land Reclamation permit. On April 23, 2007, Magruder filed an application with the Commission to expand its permit to a new site in Miller County. The new site, referred to as the Bowlin Hollow Quarry, consisted of a tract of 212 acres. Magruder requested that it be permitted to engage in surface mining on 205 of those acres, with the proposed mining area set back fifty feet from the tract’s boundaries.

The Land Reclamation Program’s staff notified Magruder on May 14, 2007, that Magruder’s application for the expansion permit met all statutory requirements and that it considered the application complete. The staff further advised Magruder to provide public notice as required by 10 CSR 40-10.020(2)(H). This regulation says that, when the Director of the Land Reclamation Program (“Director”) deems an application complete, the applicant “shall publish a notice of intent to operate a surface mine in any newspaper qualified ... to publish legal notices in any county where the mine plan is located.” Id. The [40]*40notice is to run once a week for four consecutive weeks, beginning no later than ten days after the application is deemed complete. Id. Magruder published its notice in The Miller County Autogram-Sen-tinel, a weekly newspaper published in Tuscumbia, the Miller County seat, for four consecutive weeks beginning on May 17, 2007.

On June 15, 2007, the Land Reclamation Program began receiving letters from the public requesting a public meeting regarding Magruder’s application. The letters were from several citizens who resided or owned property or businesses in the area surrounding the proposed quarry site. The citizens expressed concern over the effects of the proposed quarry on their homes, health, and businesses. They, along with the mayors of the cities of Lake Ozark and Osage Beach, also expressed concern that the quarry’s blasting operations could damage the Joint Sewer Board’s waste water treatment plant. The plant is located on land to the north of the proposed Bowlin Hollow Quarry. Additionally, two force main sewer lines, which serve the city of Osage Beach, run through the center of the proposed quarry to the sewer plant.

On June 26, 2007, the Director sent reply letters advising that Magruder had declined to hold an informal public meeting but that recipients had an additional fifteen days to petition for a formal hearing.2 Thirty-two citizens and the Joint Sewer Board (referred to collectively as “Petitioners”) timely requested a formal hearing.3

Pursuant to section 444.773.1, RSMo Cum.Supp.2009, the Director issued his formal recommendation to grant Magruder the expansion permit on July 13, 2007. During the Commission’s September 27, 2007 meeting, the Commission considered and granted Petitioners’ requests for a formal hearing. The Commission subsequently appointed a hearing officer to conduct the hearing.

The formal hearing in this matter was conducted over seven days in March, April, May, and June 2008. Following the hearing, the hearing officer issued a recommended order containing findings of fact and conclusions of law. The hearing officer found that Petitioners failed to prove that their health, safety, or livelihood would be unduly impaired by the impact of Magruder’s proposed quarrying operations in the Bowlin Hollow Quarry. The hearing officer further found that Petitioners failed to prove that, during the five years immediately preceding the date of Magru-der’s permit application, Magruder demonstrated a pattern of noncompliance with environmental law that suggested a reasonable likelihood of future acts of noncompliance. The hearing officer recommended that Magruder’s application for an expansion permit be approved, with special conditions,4 for the area west of the sewer [41]*41line easement and denied for the area east of the sewer line easement. The approved mining area was limited to approximately fifty-two acres. The Commission approved the hearing officer’s recommended order and adopted the hearing officer’s findings of fact and conclusions of law as its decision.

Petitioners subsequently filed a petition for judicial review of the Commission’s decision in the circuit court. The circuit court determined that the Commission misapplied the burden of proof during the formal hearing and improperly relied upon unscientific evidence that was outside the record. The court further found that Ma-gruder’s application was incomplete as originally filed. The court, therefore, reversed the Commission’s decision granting the expansion permit and ordered the Commission to hold a new hearing. Ma-gruder and the Commission appeal.

On appeal from the circuit court’s review of an agency’s decision, we review the agency’s actions and not those of the circuit court. Albanna v. State Bd. of Registration for Healing Arts, 293 S.W.3d 423, 428 (Mo. banc 2009). Our review is limited to determining whether the agency’s decision was constitutional; was within the agency’s statutory authority and jurisdiction; was supported by competent and substantial evidence upon the whole record; was authorized by law; was made upon lawful procedure with a fair trial; was not arbitrary, capricious or unreasonable; and was a proper exercise of discretion. Lagud v. Kansas City Bd. of Police Comm’rs, 136 S.W.3d 786, 791 (Mo. banc 2004); § 536.140.2, RSMo Cum.Supp.2009. In reviewing the agency’s decision, we must consider the entire record and not simply the evidence that supports the agency’s decision. Coffer v. Wasson-Hunt, 281 S.W.3d 308, 310 (Mo. banc 2009). “If the evidence permits either of two opposing findings, deference is afforded to the administrative decision.” Id. We do not defer to the agency’s decision on questions of law. Vivona v. Zobrist, 290 S.W.3d 167, 171 (Mo.App.2009).

We will address first Petitioners’ claim in their third point, which is that the Commission’s decision was improper and illegal because Magruder’s application was incomplete as originally filed. Magruder’s original application packet did not include a map showing the utility easements and identifying the easement holders as required by section 444.772.3, RSMo Cum. Supp.2006, and 10 CSR 40-10.020(2)(E)2.A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
326 S.W.3d 38, 2010 Mo. App. LEXIS 1109, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lake-ozarkosage-beach-joint-sewer-board-v-missouri-department-of-natural-moctapp-2010.