Lake Michigan Contractors, Inc. v. Manitowoc Co.

225 F. Supp. 2d 791, 2002 WL 34705609, 2002 U.S. Dist. LEXIS 25522
CourtDistrict Court, W.D. Michigan
DecidedMay 29, 2002
Docket1:00-cv-00787
StatusPublished
Cited by2 cases

This text of 225 F. Supp. 2d 791 (Lake Michigan Contractors, Inc. v. Manitowoc Co.) is published on Counsel Stack Legal Research, covering District Court, W.D. Michigan primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lake Michigan Contractors, Inc. v. Manitowoc Co., 225 F. Supp. 2d 791, 2002 WL 34705609, 2002 U.S. Dist. LEXIS 25522 (W.D. Mich. 2002).

Opinion

OPINION

QUIST, District Judge.

Plaintiff, Lake Michigan Contractors, Inc. (“LMC”), has sued Defendants, The Manitowoc Company, Inc. and Bay Shipbuilding Company (“BSC”), alleging that Defendants breached an agreement to construct a dredge (the “Dredge”) by failing to adhere to the schedule, failing to perform the work in an enclosed facility, and failing to perform the work in a timely, cost effective manner. Defendants have filed a motion in limine to exclude the expert testimony of LMC’s expert, Leonard Willis, P.E., who has issued two reports, both of which conclude that BSC overcharged LMC by significant amounts for its work on the Dredge. On May 7, 2002, the Court received testimony from Willis and heard oral arguments regarding Defendants’ motion. The Court now issues its Opinion and, for the reasons below, concludes that the motion should be granted.

I. Background

During the fall of 1999, LMC decided to acquire a new dredge in order to expand its dredging business. BSC expressed an interest in doing the work. LMC’s original plan was to have BSC convert a barge it owned into a dredge. After further consideration, LMC decided to construct an entirely new dredge. In early November, the parties agreed that BSC would construct the hull of the Dredge for $1.00 per pound and the deckhouse for $1.15 per pound. BSC arrived at its costs based upon a drawing produced by Tim Graul, LMC’s naval architect. LMC did not have a set of plans and specifications at that time which would enable BSC to arrive at a fixed price to construct the Dredge. Therefore, work beyond construction of the hull and deckhouse was to be performed on a time and materials (“T & M”) basis. BSC began work in December after LMC wired it approximately $1 million.

In January 2000, BSC recommended that LMC consider converting the agreement to a T & M basis due to the large number of changes that were occurring in the design of the Dredge. LMC agreed to convert to a T & M basis and from that point on, all of BSC’s work was billed on a T & M basis. In March 2000, BSC decid *793 ed to move the Dredge out of BSC’s covered fabrication shop, where it was being constructed. LMC objected, and BSC agreed to delay the move to mid-May. LMC contends that BSC agreed to construct the Dredge entirely within its covered fabrication shop and that BSC’s decision to move the Dredge from the shop to the graving docks, where it was exposed to the elements, was a breach of their agreement. BSC completed its work on the Dredge in September 2000. By that time, LMC had billed and LMC had paid approximately $7.7 million. After taking possession of the Dredge, LMC filed this lawsuit, claiming that BSC overcharged LMC for the Dredge due to BSC’s inefficiencies, failure to adhere to the schedule, and failure complete the work in the enclosed facility.

In support of its claims, LMC has retained Leonard Willis (“Willis”), a licensed professional engineer, to serve as an expert witness. Willis issued a written report dated February 20, 2001 (“Initial Report”), and a supplemental report dated July 6, 2001 (“Supplemental Report”). According to the Initial Report, Willis was retained “to provide factual and expert testimony concerning the damages LMC believes it sustained in connection with construction” of the Dredge. (Initial Report at 2, Defs.’ Br. Supp. Ex. A.)

In the Initial Report, Willis stated that he was advised by the parties that “the Dredge was being constructed under an oral, time and materials, contract between LMC and BSC, and LMC was paying BSC’s charges on a demand basis.” (Id. at 3-4.) Willis concluded that BSC overcharged LMC $1,120,779 for construction of the Dredge. (Id. at 17.) This figure is based on Willis’ conclusions that: (1) under the T & M agreement BSC should have been charging LMC a composite hourly rate of $32.73 instead of a rate in excess of $36.00 per hour, which results in an overcharge of $449,649, (id. at 7-8); (2) BSC improperly charged LMC $5,303 for work BSC performed incorrectly, (id. at 9); (3) the early move-out of the covered fabrication shop resulted in extra and unnecessary charges to LMC, including $12,748 for extra manhours and production materials caused by lost productivity as a result of the move; weather-related losses of $34,504 for the period of May 16, 2000, through June 30, 2000; $23,211 for additional protective measures and clean-up work due to rain; and $44,423 for additional hours spent cleaning up loose materials turned into slurry by rain water that entered the Dredge, (id. at 10-13); and (4) a $555,941 reduction for BSC’s inefficiency from April 19 through August 26 based upon Willis’ determination that BSC was 30% inefficient during that period, with 10% of that inefficiency being caused by LMC, (id. at 13-16).

Willis’ factual predicate for his Supplemental Report is significantly altered from that in the Initial Report. In that report, he opines that there was not a T & M contract. (Supplemental Report at 4, Defs.’ Br. Supp. Ex. B.) Instead, he states that BSC agreed to build the hull and deckhouse of the Dredge for a fixed price of $1,266,200 and that there was no T & M agreement in place for the remaining construction. (Id. at 4, 16.) Because BSC ultimately charged LMC $2,145,708 for its work on the hull and deckhouse, Willis concludes that BSC overbilled LMC $879,508 ($2,145,708-$1,266,200). (Id. at 16-17.) Willis also concludes that despite his previous use of the Price Schedule for his calculation of BSC overcharges, there is no basis to conclude that the parties agreed that the Price Schedule would apply to BSC’s work. (Id. at 9.) Instead of using the Price Schedule, Willis applies “U.S. Average Shipyard Industry Rates.” (Id. at 12.)

*794 Willis’ conclusions with respect to adjustments for BSC improper work and early move-out of the Dredge from the covered fabrication shop are essentially the same. His analysis regarding BSC’s efficiency is significantly different. After identifying several factors that contributed to BSC’s reduced efficiency, Willis opines that BSC was significantly inefficient in all hours spent on the Dredge, citing: (1) BSC’s own recognition that it was experiencing unacceptable levels of productivity; (2) BSC’s efficiency rate of 68% for the work performed on the hull and deck-house; and (3) BSC’s grossly inefficient labor and supervision application patterns. (Id. at 25-32.) Based upon the identified factors, Willis concludes that BSC was no more than 60% efficient for the entire project and that LMC was responsible for no more than 25% of that inefficiency, requiring a 30% reduction for all hours for inefficiency. (Id. at 33.) After making all of his deductions, Willis determines that fair market value of labor, material and other charges, and the original fixed-price contract for the hull and deckhouse is $5,444,434. (Id. at 43.)

Willis also includes three alternate valuations in his Supplemental Report. The first valuation is based upon an alleged promise by BSC to complete the work known to be required when the Dredge was moved out of the fabrication shop for $4 million.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Weitz Co. v. MH WASHINGTON
631 F.3d 510 (Eighth Circuit, 2011)
Johnson v. Manitowoc Boom Trucks, Inc.
406 F. Supp. 2d 852 (M.D. Tennessee, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
225 F. Supp. 2d 791, 2002 WL 34705609, 2002 U.S. Dist. LEXIS 25522, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lake-michigan-contractors-inc-v-manitowoc-co-miwd-2002.