Lake D'Arbonne Properties, L.L.C. v. Digco Utility Construction, Inc.

949 So. 2d 590, 2007 La. App. LEXIS 106, 2007 WL 258286
CourtLouisiana Court of Appeal
DecidedJanuary 31, 2007
DocketNo. 41,671-CA
StatusPublished
Cited by2 cases

This text of 949 So. 2d 590 (Lake D'Arbonne Properties, L.L.C. v. Digco Utility Construction, Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lake D'Arbonne Properties, L.L.C. v. Digco Utility Construction, Inc., 949 So. 2d 590, 2007 La. App. LEXIS 106, 2007 WL 258286 (La. Ct. App. 2007).

Opinion

DREW, J.

11 Lake D’Arbonne Properties and Cen-terPoint Energy Arkla appeal a judgment finding that CenterPoint’s installation of a gas pipeline caused a roadbed failure in a Union Parish subdivision. We amend the judgment to increase the amount of damages awarded to Lake D’Arbonne Properties by $2,550.00, and we affirm the judgment as amended.

FACTS

Lake D’Arbonne Properties (“LDAP”) is the developer of a residential subdivision, Eagle Point Subdivision, that is along Lake D’Arbonne in Union Parish. Nathan Futch was hired by LDAP to clear the land and to construct the subdivision roads.

The road at issue measured approximately 6,000 feet in length. It contained several curves and undulated over several small hills before ending at a cul-de-sac. LDAP relied on Futch for the specifications of the road, and a surveyor, Jerry Ruggs, assisted in determining where to place the road. No engineer was consulted about the road.

The roadbed was built by Nathan Futch using clay in six-inch lifts. Futch took clay that was available on the job site and sloped it toward what would be the center of the road. The clay was then compacted by heavy equipment being driven across it. The next step in the process was to be the application of asphalt as the pavement structure for the road.

[592]*592LDAP contracted with CenterPoint’s predecessor, Reliant Energy Arkla (“Cen-terPoint”), to provide natural gas service to Eagle Point. In order for this service to be provided, a gas main pipeline needed to be installed along an easement that ran on the right side of the road, at a cost of 1 a$13,530.00 to LDAP. CenterPoint assigned the task to Digco Utility Construction (“Digco”), with which CenterPoint had a blanket construction contract. In September of 2002, Digco laid approximately 6,115 feet of gas pipeline along this road.

Thomas McCloud was a general foreman for Digco at the time of the project, although he was not present when the pipeline was being laid. McCloud described how a trenching machine dug a trench that was approximately three feet deep, and then a two-inch gas line was laid. The trench was backfilled by a backhoe, which then ran over the dirt to compact it. This compaction method was done according to Digco’s general procedure.

John Wortham was CenterPoint’s inspector on this particular job. His duty was to ensure that the contractor followed CenterPoint’s specifications. The original plan was to bore under several culverts in one section of the road. That was not possible, so Wortham contacted John Crow, an owner of LDAP, about trenching into the road’s shoulder in the area of the culverts. Crow then called Johnny Dollar, the other owner of LDAP. At first Dollar would not give his consent to this variation from the original plan, but he ultimately agreed when told that Wortham said he would make it good. Wortham measured the pipeline as being approximately 24 feet from the center of the road in the area over the culverts. McCloud measured the pipeline as being no closer than nine or ten feet from the edge of the road.

Futch recalled that the dirt used by Digco to backfill the trench collapsed in an area across the culverts during a heavy rainstorm that | ¡¡occurred the day after the pipeline was laid.1 Some of the newly-laid pipeline was even exposed. Futch stated that CenterPoint was contacted about the problem, but nothing was done, so he drained the water from the trench, allowed it to dry, and then backfilled the trench. Futch also stated that on one occasion before the asphalt was poured, Center-Point returned to add soil to the trench, but the soil washed out.2 Futch estimated he backfilled certain areas of the pipeline ditch two or three times.

LDAP hired Lincoln Asphalt Paving to lay two inches of asphalt on the roadbed that had been prepared by Futch. Lincoln did not guarantee its work in this instance, which was its typical practice when it had not constructed the roadbed. Lincoln normally used soil cement when building a roadbed. In November of 2002, as the asphalt was being laid on the left side of the road, Lincoln’s heavy dump trucks traveled over the right side of the road. Soon, areas on the right side of the roadbed began failing. Michael Bryan, Lincoln’s supervisor on the job, recalled that ruts that were four to five inches deep [593]*593had formed on the outside of the right side of the roadbed. Bryan thought these problems began in one of the culvert areas and continued past it. Bryan stopped the job, and alerted Futch.3 Futch described some of the roadbed shifting into an area where the trench was 1 ¿located. Dollar described the problem as being six-and eight-inch drops in the right travel lane of the roadbed as it went across the culverts and continued past the culverts around a curve. McCloud recalled that the roadbed was rutted with tire tracks from the asphalt trucks.

It was suggested by Lincoln that soil .cement be added to the roadbed in order to stabilize the roadbed for the application of the asphalt. This suggested remedy cost $22,283.53 and was accepted by LDAP. The addition of the soil cement was limited to the right side of the road in the areas that failed. Dollar thought the soil cement went into an area from just before the culverts to an area after the bend following the culverts.

LDAP filed suit against CenterPoint and Digco asserting that substandard practices had been used in digging and installing the gas line, including digging too closely to the roadway and not properly compacting the dirt removed during the excavation process.

Cloyce Darnell, an expert witness on behalf of defendants and the only expert witness who testified at trial, blamed the roadbed failure on the material chosen by Futch to build the roadbed and on what Darnell considered to be insufficient compaction by Futch of the soil around the culverts. The trial court rejected Darnell’s conclusions and rendered judgment against CenterPoint and in favor of LDAP, awarding damages of $22,283.53. The claims against Digco were dismissed. CenterPoint and LDAP have appealed.

I .DISCUSSION

CenterPoint argues that the trial court was clearly wrong in assigning fault to it as the evidence demonstrated that the reason the road failed was because Futch used an insufficient material when building the roadbed and then did not properly compact the material. CenterPoint further contends that the trial court was clearly wrong in not assigning any fault to Futch. CenterPoint additionally argues that the trial court erred in failing to find that LDAP did not mitigate its damages. LDAP complains that it is entitled to additional damages, and that Digco should be held solidarily liable with CenterPoint for LDAP’s damages.

Liability

An appellate court may not set aside a trial court’s finding of fact in the absence of manifest error or unless it is clearly wrong, and where two permissible views of the evidence exist, the fact finder’s choice between them cannot be manifestly erroneous or clearly wrong. Cole v. Department of Public Safety & Corrections, 01-2123 (La.9/4/02), 825 So.2d 1134; Stobart v. State, Dept. of Transp. and Dev., 617 So.2d 880 (La.1993).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Thomas v. Boyd
245 So. 3d 308 (Louisiana Court of Appeal, 2017)
Harp v. Autrey
121 So. 3d 1260 (Louisiana Court of Appeal, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
949 So. 2d 590, 2007 La. App. LEXIS 106, 2007 WL 258286, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lake-darbonne-properties-llc-v-digco-utility-construction-inc-lactapp-2007.