Laight v. Idaho First National Bank

697 P.2d 1225, 108 Idaho 211, 1985 Ida. App. LEXIS 589
CourtIdaho Court of Appeals
DecidedMarch 27, 1985
Docket15128
StatusPublished
Cited by14 cases

This text of 697 P.2d 1225 (Laight v. Idaho First National Bank) is published on Counsel Stack Legal Research, covering Idaho Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Laight v. Idaho First National Bank, 697 P.2d 1225, 108 Idaho 211, 1985 Ida. App. LEXIS 589 (Idaho Ct. App. 1985).

Opinion

SWANSTROM, Judge.

A subcontractor sued Barry and Renate Laight to foreclose the lien he had filed against their new home when the builder failed to pay for the work. The Laights brought this cross-claim against Idaho First National Bank (hereinafter IFNB) to recover for breach of a contractual duty to secure lien waivers from various subcontractors prior to disbursing loan proceeds. IFNB denied that it had such a duty under the construction loan agreement entered into by the parties. The district court granted summary judgment to IFNB. The Laights appeal, raising five issues: (1) Was the construction loan agreement ambiguous? (2) Were the clauses in the agreement concerning lien waivers repugnant to each other? (3) Was the agreement subsequently modified by the conduct of IFNB? (4) Did IFNB breach its duty of due care by failing to secure the lien waivers? and (5) Are the Laights entitled to attorney fees on appeal? We affirm.

Wishing to build a home in Idaho Falls, the Laights approached IFNB in the spring of 1981 for a loan to finance their venture. On April 24, the Laights and IFNB signed a construction loan agreement. Under the terms of this agreement, the loan proceeds and cash supplied by the Laights were deposited in a special account. They were disbursed in the form of cashier’s checks made payable jointly to the Laights and the builder, with the Laights’ funds disbursed first. The agreement required that disbursement “occur immediately upon receipt by the BANK of a written ‘Report of Expenditure’ from either the OWNER or the BUILDER.” The Report of Expenditure was to include, among other things, receipts of payment and lien waivers from the subcontractors, laborers and material-men.

In June construction began. IFNB made periodic disbursements, however, without first obtaining receipts of payment and lien waivers. When construction was completed in November, one of the subcontractors had not been paid. In January 1982 that subcontractor filed his claim of lien and in June filed a foreclosure complaint, naming the Laights, IFNB and others as defendants. The Laights answered the complaint and later filed a cross-claim against IFNB alleging negligence, breach of contract and breach of fiduciary duty. The gist of their claim was that IFNB should have secured lien waivers prior to making disbursements and, failing that, should be liable for any liens filed against the property. IFNB *213 moved for summary judgment on the cross-claim. The motion was granted and this appeal followed.

The first issue on appeal is whether the construction loan agreement was ambiguous. The district court held that it was not and that IFNB had no duty under the agreement to secure lien waivers before making disbursements. The Laights contend on appeal that the agreement was ambiguous as to IFNB’s duties and thus summary judgment was inappropriate. Whether a contract is ambiguous is a question of law. See Clark v. St. Paul Property and Liability Ins. Companies, 102 Idaho 756, 639 P.2d 454 (1981). Thus, we are not bound by the holding of the district court that the agreement was ambiguous. Nevertheless, we agree with that holding.

A contract is ambiguous if it is “reasonably subject to conflicting interpretation.” Rutter v. McLaughlin, 101 Idaho 292, 293, 612 P.2d 135, 136 (1980). We must construe the contract as a whole and consider it in its entirety to determine whether it is reasonably subject to conflicting interpretations. Beal v. Mars Larsen Ranch Corporation, Inc., 99 Idaho 662, 586 P.2d 1378 (1978). The agreement provides in pertinent part:

4. Lien Waivers. In addition to the descriptions and certifications required to be contained in the Report of Expenditure as described in paragraph 3 above, the Report of Expenditure shall also contain receipts of payment and lien waivers from subcontractors, laborers and materialmen. It shall be the BUILDER’S responsibility to insure the prompt payment of sub-contractors, laborers and materialmen in installments which correspond to the construction work completed as certified in the Report of Expenditure, and to simultaneously therewith, secure on behalf of the OWNER/BORROWER, all necessary lien waivers, so that no mechanic’s or materialmen’s liens are filed against the construction premises. THE BANK DOES NOT WARRANT TO THE OWN-ÉR/BORROWER THAT THE DWELLING AND PREMISES ARE NOW FREE FROM LIENS OR CLAIM OR RIGHT OF LIEN GRANTED UNDER ANY APPLICABLE LAW OR WILL BE FREE OF SUCH LIENS WHEN CONSTRUCTION IS COMPLETED. IN THIS REGARD, IT SHALL BE THE OWNER/BORROWER’s SOLE RESPONSIBILITY TO ASCERTAIN TO HIS SATISFACTION, THE PROGRESS OF THE CONSTRUCTION PROJECT AND THE STATUS OF CORRESPONDING SUBCONTRACTOR PAYMENTS PRIOR TO ENDORSEMENT OF ANY DISBURSEMENT CHECKS. [Capitalization original.]

The Laights insist that IFNB had an implied duty to insure that lien waivers from the subcontractors were actually obtained because each “Report of Expenditure” was to include lien waivers. The agreement, however, explicitly relieves IFNB of any responsibility at all in regard to the lien waivers. It clearly places the responsibility for ascertaining the status of payments to the subcontractors upon the Laights. In the face of this explicit language, emphasized in the agreement itself, we cannot imply a duty upon IFNB as the Laights request. We hold that, read as a whole, the agreement was not ambiguous. We will not render it ambiguous by implying a duty which is contrary to the explicit language of the agreement.

This discussion also serves to answer the Laights’ second issue — that the clause requiring a “Report of Expenditure” contain lien waivers and the clause relieving IFNB of liability for any liens are repugnant to each other. The plain language of the agreement simply does not support this assertion. Only by implying a duty in the first clause contrary to the clear language of the second clause would the two clauses be repugnant to each other. By so implying a duty we would be creating an ambiguity where none existed before.

The Laights further argue that, in construing the agreement, we should consider statements made by the loan officer *214 in her deposition. These statements allegedly shed a different light upon the intent of the parties than what is revealed by the language of the agreement. “The primary objective of construction of a contract is to discover the intention of the parties____” Beal v. Mars Larsen Ranch Corporation, Inc., 99 Idaho at 668, 586 P.2d at 1384. Normally, however, “the intent of the parties must be derived from the language of the instrument itself if that instrument is unambiguous.” Bailey v. Ewing, 105 Idaho 636, 640, 671 P.2d 1099, 1103 (Ct.App. 1983). Since we have held that the agreement was unambiguous, the intent of the parties must be determined solely from the language of the agreement. The meaning and legal effect of an unambiguous agreement is a question of law.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Skinner v. U.S. Bank Home Mortgage
365 P.3d 398 (Idaho Supreme Court, 2016)
GMAC v. John Nicholas Bach
Idaho Court of Appeals, 2011
Alpine Bank v. Hubbell
506 F. Supp. 2d 388 (D. Colorado, 2007)
Madrid v. Roth
10 P.3d 751 (Idaho Court of Appeals, 2000)
Beco Construction Co. v. City of Idaho Falls
865 P.2d 950 (Idaho Supreme Court, 1993)
Wooden v. First Security Bank of Idaho
822 P.2d 995 (Idaho Supreme Court, 1991)
Pocatello Railroad Employees Federal Credit Union v. Galloway
791 P.2d 1318 (Idaho Court of Appeals, 1990)
Vail v. Vail
789 P.2d 208 (Idaho Court of Appeals, 1990)
Chittenden & Eastman Co. v. Leasure
783 P.2d 320 (Idaho Court of Appeals, 1989)
Beco Corp. v. Roberts & Sons Construction Co.
760 P.2d 1120 (Idaho Supreme Court, 1988)
Murr v. Selag Corp.
747 P.2d 1302 (Idaho Court of Appeals, 1987)
First Security Bank of Idaho, N.A. v. Mountain View Equipment Co.
730 P.2d 1078 (Idaho Court of Appeals, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
697 P.2d 1225, 108 Idaho 211, 1985 Ida. App. LEXIS 589, Counsel Stack Legal Research, https://law.counselstack.com/opinion/laight-v-idaho-first-national-bank-idahoctapp-1985.