LAHR Construction Corp. v. J. Kozel & Son, Inc.

168 Misc. 2d 759, 640 N.Y.S.2d 957, 1996 N.Y. Misc. LEXIS 80
CourtNew York Supreme Court
DecidedJanuary 11, 1996
StatusPublished
Cited by3 cases

This text of 168 Misc. 2d 759 (LAHR Construction Corp. v. J. Kozel & Son, Inc.) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
LAHR Construction Corp. v. J. Kozel & Son, Inc., 168 Misc. 2d 759, 640 N.Y.S.2d 957, 1996 N.Y. Misc. LEXIS 80 (N.Y. Super. Ct. 1996).

Opinion

OPINION OF THE COURT

Kenneth R. Fisher, J.

This is an action brought by a general contractor (LeCesse) against a subcontractor (Kozel) for damages resulting from the subcontractor’s failure to perform work on a project for which it had submitted an oral bid. The general contractor seeks [760]*760recovery under theories of breach of contract and promissory estoppel. The subcontractor moves for summary judgment. For the following reasons, Kozel’s motion for summary judgment is granted and the complaint is dismissed.

BACKGROUND

In September of 1992, LeCesse prepared to bid on the so-called Omega Upgrade Project, a multimillion dollar renovation of an existing building at the University of Rochester. LeCesse requested a number of subcontractors to bid for various parts of the job. Kozel, a subcontractor in the business of supplying steel products to the construction trade, submitted bids to LeCesse in response to the solicitation. Kozel supplies both structural steel, called "Division 5” work, and reinforcing steel, called "Division 3” work. Kozel submitted a written bid to LeCesse for the Division 3 reinforcing steel work on the Omega project. This Division 3 bid is relevant, but not directly implicated by the complaint. Kozel also submitted an oral bid of $55,000 for the Division 5 structural steel work on the project.1 LeCesse incorporated the figures received from Kozel for the Division 3 work and the Division 5 work into its final bid for the general contract, and was subsequently awarded the contract by the University of Rochester.

On October 7, 1992, shortly after the award, LeCesse employee Daniel Lanni telephoned Jeffrey Loeffler of Kozel and advised him that LeCesse was awarded the general contract for the Omega project. Lanni then told Loeffler that he "would like to talk to them about doing a deal for both the reinforcing and the structural steel.” When asked at his deposition [761]*761whether he told Loeffler that Kozel was awarded the subcontract, Lanni conceded that he did not. Lanni testified that the "deal” he envisioned was "an agreement on price and scope for both divisions and write a contract.” The subcontract contemplated might "possibly” involve a change in scope or price for each division, but Lanni’s purpose, according to his testimony, "was to do both structural and reinforcing [steel] together” and "[c]ome to an agreement” with Kozel.

At the time, Loeffler was unaware that Kozel submitted an oral bid for the Division 5 structural steel work, and therefore he told Lanni that someone from Kozel would get back to him. Shortly thereafter, Raymond Benoit, vice-president of Kozel, called Lanni. Benoit advised Lanni that Kozel would not perform the work, and Benoit explained his reasons for the refusal. Lanni told Benoit that LeCesse had relied upon their bids and, therefore, it was too late for Kozel to refuse the work.

On October 13,1992, Lanni sent Kozel a letter that purported to serve as a letter of intent to enter into LeCesse’s "standard” form of contract for Division 5 work as bid by Kozel on September 29, 1992, and as a notice to proceed with the preliminary work pending receipt of the contract. In the letter, Kozel was instructed to sign and return a copy to LeCesse. Kozel did not sign the letter, because it contained a waiver of its right to file a mechanic’s lien and also required Kozel to purchase additional insurance, and Kozel again notified LeCesse that it would not perform the work under the new terms demanded.

Because Kozel refused to perform the work, LeCesse was required to hire another subcontractor at a higher price. LeCesse brought this action to recover the difference between Kozel’s bid and the amount paid by LeCesse to the substitute subcontractor.

BREACH OF CONTRACT CLAIM

[The portion of the opinion analyzing whether there was an acceptance of the bid at the time Lanni spoke with Loeffler, or subsequently when Lanni sent Kozel the so-called letter of intent, and concluding that there was no agreement under traditional principles of contract law, has been deleted for purposes of publication.]

PROMISSORY ESTOPPEL CLAIM

The second cause of action is based on the theory of promissory estoppel. Recovery under this theory is not dependent on [762]*762the existence of a contract or the particulars of consideration in the classic sense. A promissory estoppel action, in contexts in which it is recognized, arises out of a breached promise in circumstances under which it is fair to hold the promisor to the terms of his promise. (Restatement [Second] of Contracts § 90 [1] ["A promise which the promisor should reasonably expect to induce action or forbearance on the part of the promisee or a third person and which does induce such action or forbearance is binding if injustice can be avoided only by enforcement of the promise”].) The doctrine is often thought of in terms of detrimental reliance, but more recently has been seen as grounded in a theory of promise (see generally, Yorio & Thel, The Promissory Basis of Section 90, 101 Yale LJ 111 [1991]), which has found more general application to the law of contracts in Fried, Contract as Promise (1981). (See also, Gold-stick v ICM Realty, 788 F2d 456, 463-464 [7th Cir 1986] [Posner, J.] ["the value of the promise is the presumptive measure of damages for promissory estoppel, to be rejected only if awarding so much would be inequitable”]; cf, Gordley, Enforcing Promises, 83 Cal L Rev 547, 568-569, 612-613 [1995] [for exploration of a third so-called Aristotelian theory based on a principle of equality].)

Applied to commercial or business settings like this one, two leading and much discussed cases present contrasting views on the applicability of the doctrine. (Compare, Baird Co. v Gimbel Bros., 64 F2d 344, 346 [2d Cir 1933] [Hand, J.] [rejecting promissory estoppel as a basis for subcontractor liability to the general in the bidding context], with Drennan v Star Paving Co., 51 Cal 2d 409, 333 P2d 757 [1958] [promissory estoppel is available to bind the subcontractor to its bid used by the general contractor to obtain the prime contract]; see generally, Feinman, Promissory Estoppel & Judicial Method, 97 Harv L Rev 678, 680-681, 692-694, 700-701 [1984]; Knapp, Reliance in the Revised Restatement: The Proliferation of Promissory Estoppel, 81 Colum L Rev 52, 63-64 [1981]; Kessler & Fine, Culpa In Contrahendo, Bargaining in Good Faith, and Freedom of Contract: A Comparative Study, 77 Harv L Rev 401, 422-424 [1964] [all discussing the James Baird Co.-Drennan debate].)

In New York, promissory estoppel has had only tentative application. (Farash v Sykes Datatronics, 59 NY2d 500, 510, 511 [1983] [Jasen, J., dissenting] ["promissory estoppel, a theory which * * * this court has heretofore declined to adopt”]; Weiner v McGraw-Hill, Inc., 57 NY2d 458, 465, n 6 [1982]; Allegheny Coll, v National Chautauqua County Bank, 246 NY [763]*763369, 373-375, 379 [1927].)2 The Court of Appeals has not adopted it explicitly, and has had no occasion to apply it in the construction contract context, but at least two trial courts have employed it to grant recovery to a general contractor. (Nory Constr. Co. v Genesee LeRoy Stone Corp., Sup Ct, Monroe County, Feb. 5, 1993, index No. 1499/92, mod 207 AD2d 969 [4th Dept 1994];

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Andrew R. Mancini Assoc., Inc. v. Murphy Excavating Corp.
2019 NY Slip Op 3859 (Appellate Division of the Supreme Court of New York, 2019)
Bunkoff General Contractors, Inc. v. Dunham Electric, Inc.
300 A.D.2d 976 (Appellate Division of the Supreme Court of New York, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
168 Misc. 2d 759, 640 N.Y.S.2d 957, 1996 N.Y. Misc. LEXIS 80, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lahr-construction-corp-v-j-kozel-son-inc-nysupct-1996.