Laha Holdings v. Professional Service Industries, Inc.

CourtCourt of Appeals of Kansas
DecidedApril 12, 2024
Docket125934
StatusUnpublished

This text of Laha Holdings v. Professional Service Industries, Inc. (Laha Holdings v. Professional Service Industries, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Laha Holdings v. Professional Service Industries, Inc., (kanctapp 2024).

Opinion

NOT DESIGNATED FOR PUBLICATION

No. 125,934

IN THE COURT OF APPEALS OF THE STATE OF KANSAS

LAHA HOLDINGS, Appellee,

v.

PROFESSIONAL SERVICE INDUSTRIES, INC., Appellant.

MEMORANDUM OPINION

Appeal from Johnson District Court; RHONDA K. MASON, judge. Oral argument held March 6, 2024. Opinion filed April 12, 2024. Affirmed.

Mark E. McFarland, of Hinkle Law Firm, LLC, of Lenexa, for appellant.

Daniel R. Zmijewski, of DRZ Law, LLC, of Leawood, for appellee.

Before WARNER, P.J., ATCHESON and BRUNS, JJ.

PER CURIAM: Professional Service Industries, Inc. (PSI) appeals from a jury verdict rendered in favor of Laha Holdings, LLC for breach of contract. Although PSI admitted liability at trial, it disputed the amount of the damages caused by its breach. After a three-day jury trial, the jury awarded the full amount of damages claimed by Laha Holdings. Subsequently, PSI filed a motion for a new trial, which was denied by the district court.

On appeal, PSI contends that the district court erred in denying its motion for new trial. It also contends that the jury's verdict was not supported by the evidence or the jury

1 instructions. Based on our review of the record, we conclude that the jury's verdict is supported by sufficient evidence and that the district court did not err in denying PSI's motion for new trial. Thus, we affirm.

FACTS

On June 27, 2005, Laha Holdings entered into a Design-Build Agreement with Turner Construction Company (Turner) for the construction of an office building in Overland Park. Upon completion of the building in 2007, Laha Holdings leased a portion of the property to its principal, Dr. David Laha, for his podiatry practice. The rest of the building remains unfinished. In 2007, Dr. Laha had plans to use the unfinished space as a surgery center.

Unfortunately, the building has experienced significant water intrusion issues since the completion of construction. Although Turner attempted to correct these issues for several years, it was unable to resolve them to the satisfaction of Laha Holdings. As a result, Laha Holdings filed a lawsuit against Turner for alleged construction defects. The lawsuit was ultimately settled, and the parties agreed to jointly retain an engineering consultant to evaluate the office building. They further agreed that Turner would pay a contractor to perform the repairs to the building that the consultant found to be necessary to resolve the water intrusion problems.

In a letter agreement dated May 15, 2015, PSI agreed to serve as an independent expert on behalf of Laha Holdings and Turner in connection with the office building. The engagement letter provided that PSI would "identify the causes of water intrusion occurring at the [building], identify any property damaged by water intrusion on the [building], and detail the repairs needed to: (1) eliminate the water intrusion occurring at the [building]; and (2) repair or replace any property damaged by water intrusion on the [building] . . . ." In addition, the engagement letter provided that upon receipt of the

2 specified repairs recommended by PSI, Laha Holdings and Turner would jointly select a qualified contractor to complete the repairs that PSI determined were needed to eliminate the water intrusion and to repair water-damaged property.

Over the next several months, PSI visited the site and prepared a report setting out the repairs it deemed to be necessary to resolve the water intrusion issues and to repair the property. Laha Holdings and Turner then selected Haren and Laughlin Restoration Company, Inc. (HLR) to perform the repairs identified by PSI. It appears from the record that HLR began its work at the office building in mid to late 2016. On March 1, 2017, Laha Holdings received a punch list from PSI that listed tasks to be performed by HLR to complete the project. However, on May 1, 2017, Laha Holdings advised PSI that water intrusion was still occurring at the office building. It appears that PSI never returned to the building after that date.

On November 14, 2017, HLR contacted Carl Martin, a professional engineer, to inspect the office building for water intrusion and to prepare a remediation report. The following month, Martin delivered a report to HLR listing his recommendations. Based on these recommendations, HLR then provided a proposal to Laha Holdings. However, the proposal from HLR was not accepted by Laha Holdings at that time. Instead, Laha Holdings continued to seek assistance from PSI based on its guarantee in the letter agreement to detail the repairs needed to eliminate the water intrusion.

Because the water intrusion had not been resolved, Laha Holdings filed a lawsuit against PSI and HLR on February 13, 2019. In its petition, Laha Holdings asserted a breach of contract claim and a negligence claim against PSI. Additionally, it asserted a breach of contract claim and negligence claim against HLR. During the course of the litigation, Laha Holdings resolved its claims against HLR and HLR was voluntarily dismissed as a defendant. HLR then returned to perform repairs on the office building that were previously recommended by Martin.

3 Likewise, Martin returned to the office building in October 2020 to perform additional evaluations in an attempt to determine the various sources of the water intrusion. No additional repairs were recommended at that time because Martin advised that more testing was needed. Nevertheless, on March 16, 2021, Martin again returned to the building after HLR discovered moisture coming through the exterior façade of the building. HLR explained that in addition to the leakage at the base of the building, there was also evidence of water intrusion from above.

Martin advised HLR to suspend the repair work it was performing so that he could evaluate the entire building. Based on his additional evaluation, Martin determined that there was also water coming through the roof and that moisture was collecting inside the building's siding. On October 29, 2021, Martin produced a report that summarized his evaluations and recommended additional repairs required to make the office building waterproof. The report also suggested that some of the repairs to the foundation of the building that had previously been recommended were not necessary.

In the agreed pretrial order entered by the district court prior to trial, Laha Holdings alleged that it suffered damages in the amount of $277,500 to repair the office building. In addition, Laha Holdings alleged $9,817.50 in lost income per month because of its inability to rent the building. Furthermore, Laha Holdings alleged that it suffered these losses for 57 months, resulting in a loss of rental income of $559,597.50. Consequently, Laha Holdings claimed that it sustained a total amount of $837,097.50 in damages.

On March 28, 2022, the district court commenced a three-day jury trial. At trial, Laha Holdings presented the testimony of five witnesses. In addition, Laha Holdings offered 25 exhibits that were admitted into evidence. Although its counsel cross- examined the witnesses called by Laha Holdings and presented closing arguments to the

4 jury, PSI did not call any witnesses to testify or offer any exhibits for admission into evidence.

At trial, Laha Holdings called Lennox Cary, a project manager for HLR, who testified regarding the work performed on the office building by his company in an attempt to resolve the water intrusion based on the repairs identified by PSI. According to Cary, the conditions at the building did not match the details reported by PSI and, as a result, HLR came up with an alternative remediation plan. He explained that after PSI approved the alternative plan, HLR went forward with the repairs and had completed most of the work by March 2017.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Steele v. J. I. Case Co.
419 P.2d 902 (Supreme Court of Kansas, 1966)
City of Mission Hills v. Sexton
160 P.3d 812 (Supreme Court of Kansas, 2007)
Puckett v. Mt. Carmel Regional Medical Center
228 P.3d 1048 (Supreme Court of Kansas, 2010)
Leavenworth Plaza Associates, L.P. v. L.A.G. Enterprises
16 P.3d 314 (Court of Appeals of Kansas, 2000)
Unruh v. PURINA MILLS, LLC
221 P.3d 1130 (Supreme Court of Kansas, 2009)
Wolfe Electric, Inc. v. Duckworth
266 P.3d 516 (Supreme Court of Kansas, 2011)
Marcus v. Swanson
539 P.3d 605 (Supreme Court of Kansas, 2023)

Cite This Page — Counsel Stack

Bluebook (online)
Laha Holdings v. Professional Service Industries, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/laha-holdings-v-professional-service-industries-inc-kanctapp-2024.