LaFarge Building Materials, Inc. v. Federal Insurance Company

510 F. App'x 884
CourtCourt of Appeals for the Eleventh Circuit
DecidedFebruary 27, 2013
Docket12-14396
StatusUnpublished

This text of 510 F. App'x 884 (LaFarge Building Materials, Inc. v. Federal Insurance Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
LaFarge Building Materials, Inc. v. Federal Insurance Company, 510 F. App'x 884 (11th Cir. 2013).

Opinion

*885 PER CURIAM:

Defendants Cleveland Construction, Inc. (“CCI”), a general contractor, and Federal Insurance Company (“Federal Insurance”), its surety, appeal the district court’s final judgment of $87,855.64 in favor of Plaintiff Lafarge Building Materials, Inc. (“Lafarge”), a supplier of rock and concrete. After review, we affirm.

Defendant CCI was the general contractor on two construction projects, a Wal-Mart store and the Chamblee Village Retail Shops (“the property”). Plaintiff La-farge furnished materials, such as rock and concrete mix, to Michael B. Cline d/b/a/ Clinecrete (“Clinecrete”), a concrete subcontractor. When Clinecrete failed and refused to pay, Plaintiff Lafarge filed two materialman’s liens against the property. Defendant Federal Insurance, as surety, issued two bonds which released and bonded off Lafarge’s liens. Specifically, Defendant Federal Insurance’s bonds provided that (1) Defendants CCI and Federal Insurance “are held firmly bound unto Lafarge Building Materials, Inc., herein after known as Claimant in the sum” of $134,999.02 and $51,439.02; (2) that CCI entered into a contract with Cli-necrete and Clinecrete entered into a contract with Claimant Lafarge; (3) that “Claimant has filed a mechanics’ lien in the amount of $67,499.51” and another mechanic’s lien for $25,719.51 against certain property; (4) that the correctness of these claims is disputed; (5) the hens are released in accordance with Georgia law; and (6) that if CCI pays or causes to be paid the sums which the Claimant may recover on these claims, together with the cost of suit in a timely filed action, then this obligation to pay “shall be voided; otherwise it shall remain in full force and effect.” In other words, Claimant La-farge’s liens were released on the express condition that CCI and Federal Insurance would pay the sums Lafarge recovered in a timely filed lawsuit on these claims against Clinecrete if those sums were not paid by Clinecrete.

I. STATE COURT LAWSUIT

In March 2007, before the present federal lawsuit commenced, Plaintiff Lafarge, as the materialman, timely filed a lawsuit against Clinecrete, the subcontractor, in state court to recover the unpaid amounts and perfect its claims of lien. After Cline-crete failed to respond to Plaintiffs La-farge’s motion for summary judgment, the state court entered final judgment against Clinecrete on March 23, 2009. Among other things, the state court’s judgment awarded Plaintiff Lafarge the principal sums of $67,189.51 and $25,719.51 (totaling $92,909.20) “for building materials purchased on open account by Defendant [Cli-necrete] from Plaintiff [Lafarge] and incorporated into improvements constructed on the property commonly known as Cham-blee Village Shops/Chamblee Tucker Road, Dekalb County, Georgia.”

After the final judgment against Cline-crete (which included the sums totaling $92,909.02), Plaintiff Lafarge made claims for payment of those sums under the bonds, but Defendants refused payment.

II. FEDERAL COURT LAWSUIT

Plaintiff Lafarge then filed this federal civil action against Defendants CCI and Federal Insurance. 1 Plaintiff Lafarge seeks to recover under the bonds for the unpaid sums totaling $92,909.02 awarded *886 by the state court’s final judgment, plus attorney’s fees and costs.

On June 29, 2012, the district court entered an order ruling on Plaintiff Lafarge’s motion for partial summary judgment. The district court first concluded, as a matter of law, that the state court’s final judgment of $92,909.02 against subcontractor Clinecrete “conclusively establishes the value of materials that Plaintiff [Lafarge] delivered to the Property and that the materials were incorporated into the improvements thereon.”

The district court, however, found there was a genuine issue of material fact as to whether the full amount of $92,909.02 should be offset by two waivers of the rights to lien executed by Plaintiff La-farge. After mediation, the parties reached an agreement as to the offset amount, and Plaintiff Lafarge dismissed its remaining claim (for bad faith). The district court then entered an order incorporating its June 29, 2012 summary judgment order and entering final judgment for Plaintiff Lafarge in the amount of $87,855.64 after the offset. This appeal challenging the district court’s June 29, 2012 summary judgment order followed. 2

III. DISCUSSION

A. Materialman’s Liens

Under Georgia law, materialmen who furnish material to a subcontractor have a “special lien” on the property “for which they furnish labor, services, or materials.” O.C.G.A. § 44—14—361(a)(2). When a property owner obtains a release bond for a materialman’s hen, “the bond stands in the place of the real property as security for the lien claimant.” Few v. Capitol Materials, Inc., 274 Ga. 784, 786, 559 S.E.2d 429, 430 (2002). In these circumstances, the materialman “must still comply with the statutory requirements for perfecting the lien,” except for the notice of suit requirement, and “the principal and the surety on the bond are entitled to raise any defense that would have been available as a defense to the lien foreclosure.” Id., 559 S.E.2d at 430-31. 3

Additionally, the materialman “must first seek to recover monies owed from the contractor, the party with whom it has a contract, before seeking to recover from the property owner, with whom the supplier has no contractual relationship.” Id. “It is in [this] antecedent suit against the contractor that the adjudication is made as to items furnished and the amount due with respect to a particular contract.” TriState Culvert Mfg., Inc. v. Crum, 139 Ga. App. 448, 449, 228 S.E.2d 403, 405-06 (1976) (quotation marks omitted). More importantly, the judgment the material-man obtains against the contractor “is not conclusive against the (property owner), but it does establish prima facie that the (materialman) has a valid claim against the (contractor) for the amount of the judgment.” Id. at 450, 228 S.E.2d at 406. Thus, if there is proof of a judgment against the contractor, “[t]he burden is upon the (owner) to introduce evidence sufficient to rebut the correctness of the judgment.” Id. Moreover, “[t]his rule ap *887 plies to litigated cases against the (contractor) and ... to judgments rendered against him by default.” Id. (quotation marks omitted).

B. Analysis of this Case

Here, Plaintiff Lafarge first obtained a state court judgment for $92,909.02 against the party with whom it had a contract— subcontractor, Clinecrete. Plaintiff La-farge then submitted that state court judgment to the district court.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Craig v. Floyd County, Ga.
643 F.3d 1306 (Eleventh Circuit, 2011)
Cooper v. Corporate Property Investors
470 S.E.2d 689 (Court of Appeals of Georgia, 1996)
Kelly v. PIERCE ROOFING CO., INC.
469 S.E.2d 469 (Court of Appeals of Georgia, 1996)
Few v. Capitol Materials, Inc.
559 S.E.2d 429 (Supreme Court of Georgia, 2002)
Tri-State Culvert Manufacturing, Inc. v. Crum
228 S.E.2d 403 (Court of Appeals of Georgia, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
510 F. App'x 884, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lafarge-building-materials-inc-v-federal-insurance-company-ca11-2013.