Laclede Gas Co. v. Missouri Public Service Commission

526 S.W.3d 245, 2017 WL 2332756, 2017 Mo. App. LEXIS 528
CourtMissouri Court of Appeals
DecidedMay 30, 2017
DocketWD 79558
StatusPublished
Cited by1 cases

This text of 526 S.W.3d 245 (Laclede Gas Co. v. Missouri Public Service Commission) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Laclede Gas Co. v. Missouri Public Service Commission, 526 S.W.3d 245, 2017 WL 2332756, 2017 Mo. App. LEXIS 528 (Mo. Ct. App. 2017).

Opinion

Alok Ahuja, Judge

Laclede Gas Company applied to the Public Service Commission (the “PSC” or “Commission”) for authority to issue long-term financing. The Commission granted Laclede only part of the financing authority it requested. Laclede appeals. We affirm.

Factual Background

Laclede is a public utility which distributes, transports, and sells natural gas to approximately 640,000 retail customers in eastern Missouri, and approximately 500,-000 customers in western Missouri under the name Missouri Gas Energy. Laclede is subject to the Commission’s jurisdiction.

Pursuant to § 393.200,1 Laclede must seek PSC approval for the issuance of [248]*248long-term financing. On April 15, 2015, Laclede applied for authority to issue up to $550 million in long-term financing through September 30, 2018. Staff opposed the petition and recommended that the PSC approve financing authority of only $300 million.

The PSC held an evidentiary hearing, and issued its Report and Order on February 10, 2016. In its order the Commission concluded that “Laclede’s currently-known financing needs are less than the amount of the authority requested,” and that Lac-lede “only expects to issue $300 million in financing between [the date of the order] and 2018.” The Commission found that, although “Laclede anticipates approximately $550 million in capital expenditures” during the relevant time period, it “expects to cover $250 million of this amount through operating cash flow rather than through financing.” The Commission noted that, in presentations to rating agencies, Laclede had stated that it expected to issue $300 million in long-term financing through 2018. The Commission also noted that $370 million of the authority the Commission had approved in Laclede’s prior financing case remained unissued.

Based on its findings, the PSC authorized Laclede to issue $300 million in long-term financing for the specified purposes of “refinancing short-term debt, funding capital expenditures, and retiring long-term debt schedule to mature.” Because Laclede had no current plans to issue the remaining $250 million in financing for which it had requested authorization, the PSC declined to authorize that additional amount simply to give Laclede the “flexibility” to respond to unknown future developments in the industry or in financial markets. The PSC adopted the conclusion of its order in Laclede’s 2010 financing case, where it denied Laclede’s request for additional long-term financing authority to afford the company such financial “flexibility.” The PSC noted that Laclede was free to make future requests for additional financing authority in a “specified amount supported by a specified purpose as the law requires.”

Laclede appeals.

Standard of Review

Pursuant to section 386.510, the appellate standard of review of a PSC order is two-pronged: first, the reviewing court must determine whether the PSC’s order is lawful; and second, the court must determine whether the order is reasonable. The burden of proof is upon the appellant to show that the order or decision of the PSC is unlawful or unreasonable. The lawfulness of a PSC order is determined by whether statutory authority for its issuance exists, and all legal issues are reviewed de novo. An order’s reasonableness depends on whether it is supported by substantial and competent evidence on the whole record, and the appellate court considers the evidence together with all reasonable supporting inferences in the light most favorable to the Commission’s order. The Commission’s factual findings are presumptively correct, and if substantial evidence supports either of two conflicting factual conclusions, the Court, is bound by the findings of the administrative tribunal.

State ex rel. AG Processing, Inc. v. Pub. Serv. Comm’n, 120 S.W.3d 732, 734-35 (Mo. banc 2003)(footnotes omitted); see also State ex rel. Union Elec. Co. v. Pub. Serv. Comm’n, 399 S.W.3d 467, 476 (Mo. App. W.D. 2013).

Analysis

I.

Laclede argues that the PSC’s Report and Order was unlawful because § 393.200.1 requires the Commission to [249]*249approve any request for long-term financing authority so long as the utility demonstrates that the financing proceeds will be used for one of the purposes enumerated in the statute. We disagree.

Section 393.180 specifies that a public utility’s use of long-term financing mechanisms is a “special privilege” subject to State regulation and control:

The power of gas corporations, electrical corporations, water corporations, or sewer corporations to issue stocks, bonds, notes and other evidences of indebtedness and to create liens upon their property situated in this state is a special privilege, the right of supervision, regulation, restriction and control of which is and shall continue to be vested in the state, and such power shall be exercised as provided by law and under such rules and regulations as the commission may prescribe.

Section 393.200.1 details the circumstances in which the Commission may authorize a public utility to issue long-term financing. It provides:

A gas corporation, electrical corporation, water corporation or sewer corporation organized or existing or hereafter incorporated under or by virtue of the laws of this state may issue stocks, bonds, notes or other evidences of indebtedness payable at periods of more than twelve months after the date thereof, when necessary for the acquisition of property, the construction, completion, extension or improvement of its plant or system, or for the improvement or maintenance of its service or for the discharge or lawful refunding of its obligations or for the reimbursement of moneys actually expended from income, or from any other moneys in the treasury of the corporation not secured or obtained from the issue of stocks, bonds, notes or other evidence of indebtedness of such corporation, within five years next prior to the filing of an application with the commission for the required authorization, for any of the aforesaid purposes except maintenance of service and except replacements in cases where the applicant shall have kept its accounts and vouchers of such expenditure in such manner as to enable the commission to ascertain the amount of money so expended and the purposes for which such expenditure was made; provided, and not otherwise, that there shall have been secured from the commission an order authorizing such issue, and the amount thereof, and stating the purposes to which the issue or proceeds thereof are to be applied, and that, in the opinion of the commission, the money, property or labor to be procured or paid for by the issue of such stock, bonds, notes or other evidence of indebtedness is or has been reasonably required for the purposes speciñed in the order, and that except as otherwise permitted in the order in the case of bonds, notes and other evidence of indebtedness, such purposes are not in whole or in part reasonably chargeable to operating expenses or to income.

(Emphasis added.)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
526 S.W.3d 245, 2017 WL 2332756, 2017 Mo. App. LEXIS 528, Counsel Stack Legal Research, https://law.counselstack.com/opinion/laclede-gas-co-v-missouri-public-service-commission-moctapp-2017.