Laclede Construction Co. v. Tudor Iron Works

69 S.W. 384, 169 Mo. 137, 1902 Mo. LEXIS 260
CourtSupreme Court of Missouri
DecidedJune 18, 1902
StatusPublished
Cited by28 cases

This text of 69 S.W. 384 (Laclede Construction Co. v. Tudor Iron Works) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Laclede Construction Co. v. Tudor Iron Works, 69 S.W. 384, 169 Mo. 137, 1902 Mo. LEXIS 260 (Mo. 1902).

Opinion

MARSHALL, J.

— This is an action to recover $62,402, damages alleged to have been suffered by reason of an alleged breach of contract by the defendant.

[141]*141The contract pleaded in the petition is as follows:

“St. Louis, Dec. 9, 1898.

“Wm. E. Guy, Esq., Pres. Laclede Construction Co., St. Louis.

“Dear Sir: We propose to furnish your company sufficient track fastenings for 39,000 tons 75 lb. rails, as follows:

Track Spikes 5-§x-j\......$1.48 per 100 lbs.

Track bolts § and f with TJ. S. nuts.......... 1.69 per 100 lbs.

Angle Splices, sufficient for 100 miles of 75 lb. rail....... 1.05 per 100 lbs.

“All f. o. b. cars Madison, 111., less allowance of 5 cts. for freight to P.ekin or elsewhere on your line.

“Terms, cash on the 20th of the month following delivery. Deliveries as wanted during 1899, in car lots. All to be of first-class material and workmanship. Bolts to' be of especially good fibrous iron with high tensile strength. All subject to inspection.

“It is the intention of this contract to supply fastenings, for such rails as you may buy, or lay, up to this amount, and it is binding only to that extent. We will furnish you fastenings also for repairs and for new sidings at the above prices in car lots; less than car lots at 5 cts. advance; excepting splices on which special prices for less than car lots will be made according to the quantity.

“Your acceptance of the above on this sheet and duplicate will complete the contract between us.

“Yours truly,

“B. S. Adams, Sec.

“Accepted:

“Laclede Construction Co.,

“By Wm. E. Guy, Prest.”

The petition then contains the following further material averments:

[142]*142“Plaintiff further states that it required 1,980,000 pounds of track spikes and 412,000 pounds of track bolts f and f with U. S. square nuts to be sufficient track fastenings for 39,000 tons 75-pound rails and 1,689,600 pounds of angle splices to- be sufficient for 100 miles of 75-pound rails.

“Plaintiff further states that on demand of plaintiff the defendant furnished'the plaintiff during the year 1899, and prior to June 26th of said year 1899, under the terms,of said contract, the following, to-wit: 140,000 pounds of said track spikes 5-^x-jSg.j 60,000 pounds of said track bolts £ and f U. S. nuts, and 762,000 pounds of said angle splices.

“Plaintiff further states that it duly performed all the conditions of said agreement on its part, and did during the year 1899 buy, and did during the year 1899 lay, 39,000 tons seventy-five-pound rails, and was during the year 1899 ready and willing to receive at said Madison, Illinois, and did on (he twenty-seventh day of June, 1899, demand of defendant, and was ready to- pay for the remainder of the said material agreed to be delivered as aforesaid by defendant during the year 1899, and not thereto furnished by defendant as aforesaid, ■ to-wit, 1,840,000. pounds of * said track spikes, 5-Jx-jk-, 352,500 pounds of track bolts £ and § with U. S. square nuts and 927,600 pounds of said angle splices, but defendant refused to deliver the same to plaintiff to its damage in the sum of $62,402, for which with interest from December 31, 1899, it prays judgment.”

The answer is lengthy and need not be further analyzed than to say it sets up inler alia two defenses; first, that the contract pleaded is unilateral, and, second, that the plaintiff did not perform, all the conditions precedent required by the contract to be performed by it before it was entitled to demand of the defendant a performance of its part of the contract.

Upon the trial the plaintiff- introduced various corres[143]*143pondence between the parties hereto, and the Eepublic Iron and Steel Company, to whom the defendant company sold out its plant and business on May 15, 1899, and also produced certain oral testimony. In condensed form, the substance of the correspondence is this:

First. On January 18, 1899, the defendant wrote to the plaintiff as follows: “Concerning verbal instructions from you, we have accepted the order number 10 from the St. L., P. & N. Ry. for 10,000 pair of splices to be deducted from' the contract we have with your company for 100 miles. This will leave sixty-five miles still due on the contract, same prices and terms as the contract with your company.”

Second. On March 11, 1899, the defendant wrote to the plaintiff as follows: “Will you kindly advise me if you are likely to need any track fastenings on current contract during April, May and June, so that- we can reserve the total for you. Your answer to this will be considered an estimate and not binding upon you.” To which the plaintiff replied on March 15, 1899, saying it would not need any track fastenings of any consequence prior to June, 1899.

- Third. On May 15, 1899, the defendant wrote the plaintiff that it had sold out its plant and business to the Eepublic Iron and Steel Company, and asking if the plaintiff desired any track fastenings made in June or even July it should say so at once as the works were fast filling up with orders that would take the whole summer. The plaintiff is not shown to have replied to this letter at all.

Fourth. On June 27, 1899, the plaintiff wrote to the^ defendant (ignoring the sale to the Eepublic Iron and Steel Company) and demanded performance of the terms of the contract on its part, and delivery “at the very earliest possible moment” of “the balance of the angle bars due under said contract, also all the bolts, nuts and spikes.”

Fifth. On June 29, 1899, the defendant acknowledged receipt of the plaintiff’s letter of June 27th, and said it could [144]*144not deliver any of the track fastenings before sixty days, and made some reference to the character of the spikes to be furnished, and asked if the plaintiff had-ordered the splices.

Sixth. On July 8, 1899, the plaintiff replied saying' that the defendant might consider its letter of June 27th “to be an order for the angle bars, bolts, nuts and spikes to the entire amount due this company under the contract,” and asked that they be delivered “at the very earliest possible date.” ' ^

Seventh. On August 15, 1899, the Republic Iron and Steel Company wrote to the plaintiff as follows: “In regard to the telephone request from your office for immediate delivery of the track fastenings claimed'to be due you under contract with your company of December 9, 1898, we beg to advise you that we can not see our way to accede to your demands. The spirit and intent of this contract of December 9, 1898, was to furnish you such material up to the limit named, as should be necessary in the prosecution of the work of railway construction undertaken by you, arid" it in substance provided that it should be valid only to that extent. It was for such rails as you might buy or lay up to1 the amount of the limit. The contract of the year before, which bore date February 17, 1897, was for such rails ‘as you may buy up to this amount.’ That contract was construed by your company to mean, that you were under obligation to take, at the price in that contract named, only such fastenings as should be necessary to lay such rails as you should actually put in place, and did not require you to buy fastenings for rails that you might buy but not lay.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Robson v. United Pacific Insurance Company
391 S.W.2d 855 (Supreme Court of Missouri, 1965)
Middleton v. Holecroft
270 S.W.2d 90 (Missouri Court of Appeals, 1954)
Mutual Bank & Trust Co. v. Shaffner
248 S.W.2d 585 (Supreme Court of Missouri, 1952)
Williams v. Patterson, Anc. Adm.
218 S.W.2d 156 (Missouri Court of Appeals, 1949)
Great Eastern Oil Co. v. DeMert & Dougherty, Inc.
166 S.W.2d 490 (Supreme Court of Missouri, 1942)
Wright v. Fuel Oil Co.
114 S.W.2d 959 (Supreme Court of Missouri, 1938)
Snow v. Prince
13 S.W.2d 342 (Texas Commission of Appeals, 1929)
Royal Brewing Co. v. Uncle Sam Oil Co.
226 S.W. 656 (Missouri Court of Appeals, 1920)
Hefernan v. Neumond
201 S.W. 645 (Missouri Court of Appeals, 1918)
Tull v. Fletcher
196 S.W. 436 (Missouri Court of Appeals, 1917)
Royal Brewing Co. v. St. Louis Brewing Ass'n
176 S.W. 553 (Missouri Court of Appeals, 1915)
Merryman v. Buddecke
147 S.W. 1016 (Supreme Court of Missouri, 1912)
Taylor v. Sebastian
138 S.W. 549 (Missouri Court of Appeals, 1911)
Cal Hirsch & Sons Iron & Rail Co. v. Paragould & Memphis Railroad
127 S.W. 623 (Missouri Court of Appeals, 1910)
Jenkins v. Clopton
121 S.W. 759 (Missouri Court of Appeals, 1909)
City of New York v. Paoli
63 Misc. 411 (New York Supreme Court, 1909)
Barber v. Ozark Improvement Co.
111 S.W. 846 (Missouri Court of Appeals, 1908)
Bircher v. Boemler
103 S.W. 40 (Supreme Court of Missouri, 1907)
Eaton v. Wear Coal Co.
101 S.W. 1140 (Missouri Court of Appeals, 1907)
Bailey v. Leishman
89 P. 78 (Utah Supreme Court, 1907)

Cite This Page — Counsel Stack

Bluebook (online)
69 S.W. 384, 169 Mo. 137, 1902 Mo. LEXIS 260, Counsel Stack Legal Research, https://law.counselstack.com/opinion/laclede-construction-co-v-tudor-iron-works-mo-1902.