Lacchi Construction Co. v. United States

102 Ct. Cl. 324, 1944 U.S. Ct. Cl. LEXIS 31, 1944 WL 3732
CourtUnited States Court of Claims
DecidedOctober 2, 1944
DocketNo. 44844
StatusPublished
Cited by4 cases

This text of 102 Ct. Cl. 324 (Lacchi Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lacchi Construction Co. v. United States, 102 Ct. Cl. 324, 1944 U.S. Ct. Cl. LEXIS 31, 1944 WL 3732 (cc 1944).

Opinion

LittletoN, Judge,

delivered the opinion of the court:

Plaintiff seeks to recover $29,256.22 under nine separate items of a claim made under a contract with defendant entered into July 15, 1933, to furnish all labor and materials and perform all work required for the construction of a Booster Pumping Plant to serve as a dam across the Dale-carlia Eeservoir serving the District of Columbia. The several items of the claim now urged, and with respect to [353]*353which findings of fact established by the greater weight of the evidence of record have been made, are as follows:

Claim 1. Repair cofferdam_$6,068. 72
Profit_ 606.87
Claim 2. Rental cofferdam for extra work_ 7, 600. 00
Profit_ 760.00
Claim 3. Extra pumping- 809. 00
Profit_ 80.90
Claim 4. Additional forms- 402. 80
Profit_ 40.28
Claim 5. Additional brickwork_ 440. 00
Profit_ 44. 00
Claim 6. Balance dredging costs on extra work_ 563. 03
Claim 7. Bulkheads or concrete forms_ 205.00
Profit_ 20. 50
Claim 8. Liquidated damages deducted_ 3, 925. 00
Claim 9. Field and office overhead___ 7,690.12
Total_$29, 256.22

The general facts having a bearing upon the claims in connection with the preparation and contents of the drawings and specifications, the making of the bid, the execution of the contract, and the construction and collapse of the cofferdam are set forth in findings 1 to 13, inclusive.

The facts as to Claim 1 are set forth in findings 15 to 29, inclusive.

On this claim plaintiff contends that it was misled as to subsurface conditions by defendant’s probe chart or drawing, and the contract drawings. Specifically, plaintiff insists that defendant made a positive misrepresentation as to the subsurface conditions on the basis of the facts and information in its possession by leading plaintiff to believe that the subsurface conditions at the “rock” elevations shown consisted of bedrock or solid rock over the entire area of the site of the work and over the area covered by the hand and jet probings made by defendant, whereas the subsurface conditions later found to exist consisted of large boulders. Plaintiff contends that this alleged misrepresentation was the cause of the collapse of the cofferdam and the resulting cost of reconstructing and repairing it, and that if the area underneath the silt and mud had consisted of solid rock the steel sheet cofferdam [354]*354piling would have notched into the rock, no water would have come ip. underneath the piling, and the dam would not have given way and collapsed as it did.

From the Commissioner’s report of the facts and a careful study of the evidence of record, these contentions, in our opinion, are not supported by the facts. First, we think there was no misrepresentation by defendant, and, secondly, we are convinced from a study of all the evidence that subsurface conditions were not the cause of the collapse of the cofferdam, but that it collapsed because it was not properly and adequately braced on the inside to withstand the water pressure from the outside.

As to the alleged misrepresentation on the probe drawing, defendant had no information other than that disclosed on this probe chart which fairly and accurately indicated the result of the probings theretofore made. Various elevations were shown at the points of probings over the area, and, in each instance, the chart showed whether the hand and jet probings, both made at the same points, encountered “mud” or “rock” and the elevation in each instance. Another section of the probe chart showed the water elevation; by an irregular line it indicated the approximate average elevation of mud and by another very irregular line indicated the approximate average elevation at which “rock” had been encountered by the probings. The chart also explained in a “note” that the various probings were indicated by a dot when encountering “rock” and by a circle when encountering “mud”. A hand probe is made by driving a small rod to point of resistance, and a jet probe is made by using a %-inch or a one-inch pipe and forcing the water through it under pressure and extending the pipe to the point of resistance. The chart showed that the jet probings went below the hand probings and that, in practically every instance, the jet probes encountered “rock.” Defendant’s probe chart indicated as fairly and accurately as possible the information which defendant had as a result of probings — nothing more and nothing less. It is generally understood by engineers, and plaintiff should have known, that a probe chart can be only approximate; it cannot show definite solid rock. It can only indicate what the probe rod or pipe strikes at the point of probe. If it [355]*355strikes rock, suck rock may be a boulder or it may be solid rock. The boulders may be numerous or so close together, as was the case here, as to cause rock to be encountered by the probings over a large area. In the area in question boulders up to six feet in diameter were found after the earth had been excavated, and it was necessary to excavate as much as 13 feet lower to find solid bedrock suitable for foundation footings. In the case of probings, there is always an element of doubt as to whether the probe has encountered solid rock or bedrock, or has encountered a boulder.

With reference to the cause of the collapse of the cofferdam near the northeast corner at wooden guide pile 7B, the proof shows that the sheet piling was not sufficiently nor adequately braced; that before the collapse certain sheet piling at that point was bending inwardly six inches near the lower portion thereof, due to insufficient bracing and excess excavation at that point; that the water pressure caused the existing bracing to give way near the top of the piling which moved the sheet piling upward, and that section of the cofferdam moved inward about 12 feet, causing the entire dam to be flooded. The proof shows that, at this point the toe of the steel piling held firm until the bracing and supports collapsed. At the point of collapse the bracing and struts supporting the upper section of the cofferdam steel piling and wales had been placed at an incline or acute angle to the outside water pressure, and guide pile 7B had been sheared for seven feet at its bottom end or cut in two by the driving of the steel piling. As a result this guide pile, to which the struts and bracings were attached, gave way and there was nothing left to hold the interior bracing and struts in place.

Plaintiff is not entitled to recover on this claim.

In Claim 2, findings 30 to 35, inclusive, plaintiff seeks to recover $7,600 as rental for its cofferdam at $50 a day for 152 days, the period of extra work under Extra Work Order No. 1, plus a profit of 10 percent, of $760.

No recovery can be had under this claim for several reasons. This matter was of necessity included in and covered by the extra work order which was based upon plaintiff’s proposal, and was accepted and signed by plaintiff without protest. [356]*356Cf. Enos L.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Acme Process Equipment Co. v. United States
171 Ct. Cl. 324 (Court of Claims, 1965)
Acme Process Equipment Co. v. United States
347 F.2d 509 (First Circuit, 1965)
National Trailer Convoy, Inc. v. The United States
345 F.2d 573 (Court of Claims, 1965)
Remington Rand Inc. v. United States
120 F. Supp. 912 (Court of Claims, 1954)

Cite This Page — Counsel Stack

Bluebook (online)
102 Ct. Cl. 324, 1944 U.S. Ct. Cl. LEXIS 31, 1944 WL 3732, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lacchi-construction-co-v-united-states-cc-1944.