La Rose v. Backer

11 A.D.2d 314, 203 N.Y.S.2d 740, 1960 N.Y. App. Div. LEXIS 8397
Appellate Division of the Supreme Court of the State of New York·Decided July 27, 1960·Published·Cited by 23 cases

Opinion

Reynolds, J.

This is an appeal from a judgment of foreclosure and sale against certain property owned by the defendants-appellants, Kalman Backer and Henry Shapiro, from the order ratifying and confirming the Referee’s report, Supreme Court (Best, J.), and from the Referee’s report in favor of plaintiifs-respondents and defendants-respondents. The defendants-appellants (the “Owners”) had contracted with the general contractor Anthony Servidone for the construction of the King George Motel near Lake George Village, Warren County. Plaintiifs-respondents were materialmen and subcontractors who performed and furnished materials for the general contractor. Joined as parties defendant were other subcontractors, materialmen and the general contractor.

Backer had financed the building of the Country Squire Motel located on Route 20 near Guilderland. He decided he wanted another motel substantially similar to be built on a promontory overlooking Lake George. After having the land cleared and leveled, construction was started and the footings were actually poured in April, 1956. This was done by hourly labor. The supervisor of this work withdrew from the job, however, and, Backer looked around for a general contractor to continue the construction. Servidone was engaged under a contract. This contract provided that Servidone should undertake the construction of the motel “ as per plans and specifications therefor, hereto attached and made a part hereof ”. Thereafter follows a list of modifications from those plans and specifications. The contract price was $130,000, 4 4 subject to additions and deductions as provided under the general conditions of this Agreement ’ ’. In respect to this, item 4 4 Tenth ’ ’ provides: 14 Changes in the work, or in the performance of the contract, either by alterations, additions to, or deductions from work, may be made by mutual consent, the same to be in written form, which shall include compensation and allowances. to be made for such additions, corrections and deductions. The furnishing of extras shall be governed b.y this provision, and there shall be no charge therefor unless the same are furnished at the request of the Owners, in writing, with agreement as to prices therefor.”

The rest of the contract contains the usual provisions including a provision for arbitration in the plans and specifications. This was executed on May 7, 1956. Four modifications were [317] subsequently made in accord with item Tenth ”, all relating to changes in the original plans and specifications. These plans and specifications were, in fact, the same ones used for the construction of the Country Squire Motel and the evidence seems to substantiate the fact that they were an integral part of the negotiations leading up to the execution of the contract. The evidence also substantiates the fact that the major changes in the plans were incorporated into the contract and its modifications, although the footings, as already stated, were laid so as to add a bit to the width of the building over what the plans called for. Prior to the contract’s execution, however, Servidone had inspected the Country Squire Motel and the site for the new motel upon which these footings had already been poured.

The contract called for the work to be completed on August 1, 1956, with a penalty clause for late completion and a bonus clause for early completion. Servidone’s work was not completed ivntil November 15. There is evidence that the owners, Backer in particular, were in constant attendance at the job and actually did much of the supervising. There is also evidence that the plans and specifications were not usable and made more impossible to follow by Backer’s continual interference. It is claimed that he persisted in making changes of one sort or another some of which were embodied in the contract or its modifications and some of which were not.

By November 15 the owners had paid Servidone $84,142 of the -contract price, but withheld the rest claiming inferior workmanship', for which adjustments would have to be made. Servidone, on the other hand, claimed a substantial sum for extras and in the meantime this action was started by plaintiffs. On March 8, 1957 Servidone served a demand for arbitration and on April 25 the parties executed an agreement setting up the arbitration machinery, and it was provided that the award should be made on or before May 17, 1957 and filed with the Clerk of the Supreme Court of Warren County which would serve as an award upon which judgment could be entered. No agreement was reached by the two arbitrators by May 17, but in August all the parties agreed that they should continue the arbitration. On October 21 a document was signed by both arbitrators which listed extra work by the contractor as amounting to $18,792 and omissions and faulty construction on his part to total $42,554. This would mean that, with the $84,142 already paid, the owners, when balancing the extras against the omissions, owed another $22,096, or a total contract price of $106,238, because the omissions so far exceeded the extras. Be that as it may, this decision was never confirmed and conse[318] quently never filed so that judgment could be taken. Servidone’s arbitrator denied that he knew what he was signing, but this incredible testimony was pretty well shaken on cross-examination on the trial of the lien action before the Referee.

The trial of this lien action started (before the Referee) on February 10, 1958 and the hearings ended on June 15, 1959. Servidone, as party defendant, claimed over against the owners the sum of $188,505.20 ($84,142 of which lin'd already been paid leaving a balance of $104,363.20). The original contract was admitted and the additional sum represented extra costs incurred because of the changes incorporated at the special request of the owners. Subsequently another cause of action was added under the theory of quantum meruit. The owners counterclaimed for $87,000 because of faulty work and omissions.

During the hearing testimony was given by materialmen, subcontractors— practically everyone who had anything to do with this job. Among these witnesses were two experts, an engineer and an architect, who testified after inspecting the finished motel, that in their opinion the labor and materials performed and supplied by ¡Servidone were of the fair and reasonable value of $234,500. The two architects who served as arbitrators also testified and, as before noted, their appraisal is in the record.

At the conclusion, the Referee’s report awarded Servidone $234,500 as the total sum due on the contract. Obviously the Referee had used as the only measure of value the testimony of the two experts. This substantial sum made it necessary, of course* to grant Servidone’s motion to increase the sum demanded in his claim. Thus Servidone was awarded $45,994.80 more than he had asked for in his original pleadings.

Free access — add to your briefcase to read the full text and ask questions with AI

La Rose v. Backer, 11 A.D.2d 314, 203 N.Y.S.2d 740, 1960 N.Y. App. Div. LEXIS 8397 (N.Y. Ct. App. 1960).

11 A.D.2d 314 (La Rose v. Backer) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Spectrum Painting Contractors, Inc. v. Kreisler Borg Florman General Construction Co.
64 A.D.3d 565 (Appellate Division of the Supreme Court of New York, 2009)
Industrial Window Corp. v. Federal Insurance
609 F. Supp. 2d 329 (S.D. New York, 2009)
Command Cinema Corp. v. VCA Labs, Inc.
464 F. Supp. 2d 191 (S.D. New York, 2006)
Sergeants Benevolent Ass'n Annuity Fund v. Renck
19 A.D.3d 107 (Appellate Division of the Supreme Court of New York, 2005)
Katz v. American Mayflower Life Insurance
14 A.D.3d 195 (Appellate Division of the Supreme Court of New York, 2004)
Ellis v. Abbey & Ellis
294 A.D.2d 168 (Appellate Division of the Supreme Court of New York, 2002)
SAA-A, Inc. v. Morgan Stanley Dean Witter & Co.
281 A.D.2d 201 (Appellate Division of the Supreme Court of New York, 2001)
Reilly v. NatWest Markets Group Inc.
181 F.3d 253 (Second Circuit, 1999)
Wilmoth v. Sandor
259 A.D.2d 252 (Appellate Division of the Supreme Court of New York, 1999)
Unisys Corp. v. Hercules Inc.
224 A.D.2d 365 (Appellate Division of the Supreme Court of New York, 1996)
Armand Cerrone, Inc. v. Sicoli & Massaro, Inc.
214 A.D.2d 968 (Appellate Division of the Supreme Court of New York, 1995)
H.B.L.R., Inc. v. Command Broadcast Associates, Inc.
156 A.D.2d 151 (Appellate Division of the Supreme Court of New York, 1989)
Care Systems, Inc. v. Laramee
155 A.D.2d 770 (Appellate Division of the Supreme Court of New York, 1989)
Recon Car Corp. v. Chrysler Corp.
130 A.D.2d 725 (Appellate Division of the Supreme Court of New York, 1987)
Syracuse Supply Co. v. State
110 A.D.2d 1053 (Appellate Division of the Supreme Court of New York, 1985)
S. Leo Harmonay, Inc. v. Binks Manufacturing Co.
597 F. Supp. 1014 (S.D. New York, 1984)
Contelmo's Sand & Gravel, Inc. v. J & J Milano, Inc.
96 A.D.2d 1090 (Appellate Division of the Supreme Court of New York, 1983)
Beaumont Birch Co. v. Najjar Industries, Inc.
477 F. Supp. 970 (S.D. New York, 1979)