L. White & Co. v. Culpeper Memorial Hospital, Inc.

81 Va. Cir. 27, 2010 Va. Cir. LEXIS 97
CourtCulpeper County Circuit Court
DecidedApril 28, 2010
DocketCase No. 2008-L-50
StatusPublished
Cited by1 cases

This text of 81 Va. Cir. 27 (L. White & Co. v. Culpeper Memorial Hospital, Inc.) is published on Counsel Stack Legal Research, covering Culpeper County Circuit Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
L. White & Co. v. Culpeper Memorial Hospital, Inc., 81 Va. Cir. 27, 2010 Va. Cir. LEXIS 97 (Va. Super. Ct. 2010).

Opinion

By Judge John G. Berry

On January 27, 2010, the court conducted a hearing on the Plea in Bar (Conditions Precedent), Plea of Contractual Limitations, and Plea in Bar (Judicial Estoppel) filed by the Defendant, Culpeper Memorial Hospital, Inc. Shortly before that hearing, on January 4, 2010, the court entered a Consent Order (Oyer) making the seven enumerated exhibits a part of the pleadings in the case as if they were incorporated into the Plaintiffs First Amended Complaint. In the hearing on January 27, the court received three additional exhibits but no other evidence concerning the pleas in bar.

To summarize the posture of the case as of the time of the hearing, in response to the Complaint filed in this case, the Defendant responded with, among other pleadings, its Motion to Dismiss. In that motion, it contended that the contract required all claims to be submitted to the architect for the project before any contract action could be filed in court. Because the court found that Article 4 of the General Conditions required submission of a claim or claims to the architect as a condition precedent to commencing litigation and because the Complaint was silent as to the Plaintiff’s compliance with this requirement, the court granted the Motion to Dismiss but allowed the Plaintiff to file amended pleadings. It did so in a timely fashion.

The First Amended Complaint contains allegations in paragraphs 28 and 29 that L. White and Company submitted the claim or claims to the architect. The Plaintiff’s contention is, and has been, that its claims are detailed in the document entitled “Claim Presented By: L. White and Company, Inc., General Contractor...” dated May 31,2002, sent to William [28]*28Hall Esquire, by Paul A. Simpson on June 14, 2002. In his cover letter sending the document, Mr. Simpson describes his client’s submission as a “draft of the test of the impact claim of L. White & Co____” The letter goes on to say that the “enclosed” is offered for settlement purposes only and to facilitate discussion in that regard.

Plea in Bar Regarding Submission of Claim to Architect

In its Plea in Bar, the Defendant contends, among other things, that the Plaintiff failed to submit its claim (or claims) in accordance with the provisions of the parties’ contract; therefore, it is barred from recovery because this condition precedent to filing the action has not been met. “A plea in bar is a defensive pleading that reduces the litigation to a single issue, which, if proven, creates a bar to the plaintiff’s right of recovery.” Baker v. Poolservice Co., 272 Va. 677, 688, 636 S.E.2d 360 (2006). “The party asserting the plea in bar bears the burden of proof.” Id. Where no evidence is taken in support of the plea, the trial court is required to rely solely upon the pleadings in resolving the issue presented, and the facts alleged in the complaint are deemed to be true. Hawthorne v. VanMarter, 279 Va. 566, 692 S.E.2d 226 (2010); Tomlin v. McKenzie, 251 Va. 478, 480, 468 S.E.2d 882 (1996). With these standards in mind, in this case, the court heard no testimony on the plea and received only three exhibits into evidence. Those additional documents received on January 27 are the United States Bankruptcy Court Summary of Schedules (5 pages); the facsimile cover sheet, letter of June 14, 2002, from Mr. Simpson to Mr. Hall, and the Construction Claim, all attached together as one exhibit (12 pages); and the facsimile cover sheet from Mr. Hall to Mr. Hobbs dated June 20, 2002, letter of June 20, 2002, from Mr. Daniel to Mr. Hobbs, and copy of the find page of the Construction Claim, all attached together as one exhibit (3 pages). The previously-entered Consent Order (Oyer) had the legal effect of incorporating the exhibits described therein into the Plaintiff’s First Amended Complaint. Wood v. Commonwealth, 25 Va. (4 Rand.) 329 (1826).

Part of the Defendant’s contention is that the pleadings and the evidence before the court in the form of additional documents do not provide any substantiation of an independent wrongful termination claim. During argument on this issue, Plaintiff’s counsel conceded as much. The court grants the Defendant’s plea in bar concerning any claim of wrongful termination of the contract.

The Defendant’s Plea of Contractual Limitations is also directed, at least partly, at a wrongful termination claim. In view of the court’s rulings on the question of whether a separate wrongful termination claim is being made and on the Plea in Bar (Conditions Precedent), the court concludes it is unnecessary to decide the Plea of Contractual Limitations except to say [29]*29that it does not find that this action was filed too late, that is beyond the five-year of limitation for a written contract.

As to the balance of the Plaintiff’s claim or claims, the court concludes that the documents attached to the Consent Order (Oyer), particularly Exhibits A, E, and G thereto, and the other documents considered by the court, in the context of the First Amended Complaint and the legal standards applying to consideration of the plea, indicate that the parties were treating the Plaintiff’s claim as having been submitted for decision under the contract pursuant to the provisions of Article 4 of the General Conditions. The architectural firm was attempting to reach a decision as to the merits of those claims, and, while it is disputed as to whether the Plaintiff supplied the additional information being sought by the architect, the court concludes that the Defendant has not proved that it is more probable than not that the Plaintiff failed to submit its claim for consideration by the architect. Contrary to the Defendant’s argument, in granting the Motion to Dismiss the Plaintiff’s Complaint earlier in the case, the court did not make any ruling concerning the submission of a claim to the architect, only that the pleadings made no allegation of such a submission and were, therefore, deficient. The court, accordingly, denies the Plea in Bar as to the issue of whether a claim was ever submitted as required by the parties’ contract.

Plea in Bar Regarding Alternative Dispute Resolution Contract Provisions

As a part of its Plea in Bar (Conditions Precedent), the Defendant also contends that the parties’ contract required L. White and Company to submit the claim or claims it raises in this action to Informal Negotiation, then Mediation, as a condition precedent to filing suit. The parties’ contract says the following in the Supplementary Conditions:

4.5 Informal Negotiation and Mediation
Neither party may initiate litigation to pursue a claim arising out of or related to this Agreement, or the performance thereof, without first exhausting the two-stage dispute mechanism set forth in this provision. Exhaustion of such dispute resolution mechanism by agreement of the parties is a condition precedent to the filing of any litigation on such claim.

The contract goes on to describe stage one of the two-stage mechanism as Informal Negotiation and provides the manner of implementing this process. It further provides that stage two, that is Mediation, is initiated by either party giving written demand for mediation if informal negotiation fails to resolve the claim.

[30]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
81 Va. Cir. 27, 2010 Va. Cir. LEXIS 97, Counsel Stack Legal Research, https://law.counselstack.com/opinion/l-white-co-v-culpeper-memorial-hospital-inc-vaccculpeper-2010.