L. Romano Engineering Corp. v. State

113 P.2d 549, 8 Wash. 2d 670, 1941 Wash. LEXIS 618
CourtWashington Supreme Court
DecidedMay 19, 1941
DocketNo. 28113.
StatusPublished
Cited by11 cases

This text of 113 P.2d 549 (L. Romano Engineering Corp. v. State) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
L. Romano Engineering Corp. v. State, 113 P.2d 549, 8 Wash. 2d 670, 1941 Wash. LEXIS 618 (Wash. 1941).

Opinions

Jeffers, J.

This action was brought by L. Romano Engineering Corporation, against the state of Washington, in the early part of May, 1938, to recover for materials and services claimed to have been furnished by plaintiff in the performance of contract No. 2215, between plaintiff and defendant, and for which it has not been paid. Under the terms of the contract, plaintiff constructed about twelve miles of highway in Adams county, from Ritzville north.

Subsequent to the institution of this action, L. Romano, liquidating trustee of L. Romano Engineering Corporation, was substituted for L. Romano Engineering Corporation, as party plaintiff. We will hereinafter refer to the corporation as plaintiff and respondent.

The contract in question was entered into on or about September 19, 1936, and the work thereunder was completed on or before July 21, 1937. Plans and specifications upon which plaintiff bid for this job were made a part of the contract. These plans and specifications included the measurements to which the road was to be constructed, and detailed estimates of quantities of materials to be handled or supplied by plaintiff, with the provision that plaintiff should be paid for the actual services and quantities of materials fur *673 nished, at the contract unit prices, whether they overran or underran the original estimates.

In its complaint, plaintiff alleges that defendant, acting through its engineers, staked the roadway, and wrongfully, arbitrarily, and capriciously required the roadway to be constructed by plaintiff to an average width of 34.66 feet, instead of thirty feet, as specified in the plans and specifications, and required plaintiff to place materials on this highway to a greater depth than called for by the contract; that, because of this increase in width and depth, plaintiff had to provide for, and place, additional quantities of materials, for which, under the basic contract schedule of prices, defendant is indebted to plaintiff in the sum of $39,564. Plaintiff also alleges that defendant, acting through its highway engineer, wrongfully, arbitrarily, and capriciously classified improperly materials excavated, thereby depriving plaintiff of $26,141, additional compensation due. A further allegation is to the effect that defendant is wrongfully withholding from plaintiff a retained percentage of fifteen per cent, aggregating $20,145.21.

Other allegations appear in the complaint, but they are not material to this appeal, the trial court having found against plaintiff on these other matters, and plaintiff not having appealed from the judgment entered.

Defendant answered the complaint, denying specifically every material allegation of the complaint, and by way of an affirmative defense, pleaded the statute of limitations as a bar to plaintiff’s action.

The trial court found: (1) That the action was commenced within the time limited by law; (2) that the defendant staked the roadway for an actual width of thirty-four feet, and, acting wrongfully, capriciously, and arbitrarily, required plaintiff to construct the *674 roadway to an average width of 33.9 feet, rather than to the maximum of thirty feet specified in the plans; (3) that defendant’s records were not kept in accordance with the highway as actually constructed, but solely with reference to the original quantities called for in the construction of a highway thirty feet wide; (4) that, because of the increase in the roadway width and thickness, plaintiff was required to and did lay 11,158 additional cubic yards of top surfacing, 12,326 additional cubic yards of base surfacing, 1,915 additional cubic yards of filler, and 11,916 additional cubic yards of selected roadway borrow, for all of which defendant is indebted to plaintiff, under the basic contract schedule, in the sum of $35,229.40; (5) that plaintiff is entitled to an additional $3,041.50 for solid rock excavation, which defendant capriciously and wrongfully misclassified as class A excavation; (6) that there is due and owing from defendant to plaintiff the further sum of $2,500, being a portion of the retained percentage under the contract.

Judgment was entered for plaintiff in the sum of $40,770.90. Defendant has appealed from the judgment entered, and makes ten assignments of error.

Appellant claims the court erred in making each and every one of these findings of fact and the conclusions of law and judgment, for the reason that neither the findings nor the judgment is supported by the evidence. Appellant also assigns error in the admission of certain testimony, over appellant’s objection, relative to the number of road approaches actually constructed.

Appellant contends this action is barred by Rem. Rev. Stat., Vol. 7A, § 6400-40 [P. C. § 2696-513], which provides:

“Any contracting person . . . who claims a cause of action against the State of Washington arising out of any such contract must bring such suit in the proper court in Thurston county before the expiration *675 of one hundred and eighty days from and after the final acceptance and the approval of the final estimate of such work by the director of highways; otherwise such action shall be forever barred.”

Whether this section does or does not bar the recovery sought in this action is a question which turns upon the time the final estimate for contract No. 2215 was accepted and approved by the director of highways.

This action was commenced May 21, 1938. Appellant contends that the final estimate (defendant’s exhibit 18) was duly accepted and approved August 31, 1937, and that this was more than one hundred eighty days before this action was commenced. Respondent, on’ the other hand, contends that the final estimate was not accepted and approved until August 4, 1938, after this suit was commenced, and that the estimate which appellant treats as the final estimate was only monthly estimate No. 8.

There was a great deal of testimony introduced by the respective parties relative to this matter. The trial court adopted the contention of respondent, and, from the record, there was ample evidence to sustain this ruling. The problem is entirely a factual one, and resolves itself down to the question of whether or not estimate No. 8 is the final estimate on the contract. If estimate No. 8 was the final estimate, more than one hundred eighty days had run after the acceptance and approval by the director of highways before this action was commenced, and the action is barred; if not, the action was timely commenced.

Respondent completed work under this contract on or before July 21, 1937. Prior to this date, seven monthly estimates had been prepared, accepted, approved, and paid. Each of these monthly estimates showed the work completed by respondent during the *676 preceding month, and the amount to which it was entitled, under the contract price. Eighty-five per cent of this amount was paid respondent, fifteen per cent being retained by the state, as provided by Rem. Rev. Stat., § 10320 [P. C. §9727-1],

. On August 17,1937, nearly one month after the work on the contract was completed, estimate No. 8 was submitted to, and executed by, respondent. It was approved by the director of highways on August 31, 1937.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vale v. City of Seattle
W.D. Washington, 2024
Atkinson v. Aaron's LLC
W.D. Washington, 2024
State v. Jennings
502 P.3d 1255 (Washington Supreme Court, 2022)
State v. Weatherwax
Washington Supreme Court, 2017
State v. Walker
Washington Supreme Court, 2015
Eagle Insurance v. Albright
474 P.2d 920 (Court of Appeals of Washington, 1970)
Saddler v. State
401 P.2d 848 (Washington Supreme Court, 1965)
Berliner v. Greenberg
223 P.2d 598 (Washington Supreme Court, 1950)
Rushlight v. MacLain
182 P.2d 62 (Washington Supreme Court, 1947)
L. Romano Engineering Corp. v. State
12 Wash. 2d 736 (Washington Supreme Court, 1942)
L. Romano Engineering Corporation v. State
120 P.2d 1008 (Washington Supreme Court, 1942)

Cite This Page — Counsel Stack

Bluebook (online)
113 P.2d 549, 8 Wash. 2d 670, 1941 Wash. LEXIS 618, Counsel Stack Legal Research, https://law.counselstack.com/opinion/l-romano-engineering-corp-v-state-wash-1941.