L. Romano Co. v. Skagit County

268 P. 898, 148 Wash. 367, 1928 Wash. LEXIS 873
CourtWashington Supreme Court
DecidedJuly 10, 1928
DocketNo. 21005. En Banc.
StatusPublished
Cited by1 cases

This text of 268 P. 898 (L. Romano Co. v. Skagit County) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
L. Romano Co. v. Skagit County, 268 P. 898, 148 Wash. 367, 1928 Wash. LEXIS 873 (Wash. 1928).

Opinion

Mitchell, J.

This is an appeal from a judgment in an action brought for the recovery of money alleged to be due for the construction of a county road in Skagit county, spoken of as the Wickersham Road. The action involved a number of kinds of work done and materials furnished. The contract under which the work was performed was a unit price contract, with the exception of the clearing and grubbing, which was a lump sum contract. The issues were made up including counterclaims interposed by the defendant county, and trial was had to the court without a jury. The plaintiff has appealed because it was not allowed to recover certain specified items set up in its complaint and covered by the evidence, and because of one item allowed the defendant county on its counterclaim. These items will be considered in their order. ■ The county will be spoken of as the respondent.

The first item or assignment is that the trial court erred in refusing to render judgment compensating ^appellant for 12,320 pounds of reinforcing steel bars- used in gutters on the project. An argument on behalf.'of the appellant, that the contract was ambig-’ uous.in.this particular and should be construed most strongly against the respondent, is made on the claim that, when the controversy over the item arose, the county engineer, representing the county, admitted that the steel should be paid for separately. A representative of the appellant corporation so testified, but *369 that testimony was flatly contradicted by the county engineer and others ..who were present. Upon this issue of fact, the preponderance, we think, is against the appellant. Such was the conclusion of the trial judge as expressed in his written opinion, which has been furnished to us by the appellant, and which was carried into the judgment.

Further, a reasonable construction of the contract by its terms with respect to this item leads to a conclusion against the appellant in our opinion. The gutters, in which the steel was used, are standard concrete gutters. The specifications for them, which are made a part of the contract, appear on a detailed drawing or blue print, affording information in detail consisting, among other things, of steel bars imbedded at intervals transversely through the gutter and into the pavement proper of the roadway, and two steel bars running with, or lengthwise of, the gutter. Certain items on the bid sheet or proposal of the appellant, which are a part of the contract and which áre important in the present consideration, are as follows:

“7 in. plain paving at $2.17 per square .yard; Class A. concrete at $40.00 per cubic yard; Class B. concrete at $25.00 per cubic yard; rein, bars pay. at 15c per lb.; and rein, bars strs. at 8c per lb.”

That is, for steel in the seven-inch paving fifteen cents per pound, and for steel used in cubical concrete in structures such as bridges, abutments, and probably culverts, eight cents per pound, while as to the gutters it simply.says “stan. cone, gutter 9,674 lin. ft. at 40c per lin. ft.” There being a separate statement or proposal fixing price for steel used in the plain paving and that used in cubical concrete in structures, and none for that used in the gutter, we think it must be held to mean that there was to be no separate charge for the steel used in the gutter and that the judgment *370 in the trial court in this respect was correct, there being no contention that any excess quantity of steel was used in the gutters.

The next assignment is that the court erred in refusing an allowance for clearing outside of the right of way. The contract, in this respect, provides:

“The right of way will in general be cleared to the width of 25 feet on each side of the center line, but will be cleared to greater widths where ordered by the county engineer. Clearing outside of the right of way shall be done under the same specifications and be paid for at the same price as clearing within the right of way. The clearing will in all cases conform to the stakes set by the county engineer. . . . Clearing will be paid for by the acre for the area actually cleared by the contractor in accordance with the stakes set by the county engineer.”

The working profile plan relied on by the appellant indicates a clearing fifty feet in width, and therefrom it is argued, as we understand, that all clearing outside of the fifty-foot strip must be paid for over and above appellant’s lump sum bid of $15,000. But the assumption is too narrow. The contract, either with or without the working profile, does not say that the right of way on which the lump sum bid for clearing and grubbing was made and accepted is only fifty feet in width, but it says that the right.of way will in general be cleared twenty-five feet on each side of the center line, and continuing, and in the same sentence, the contract says “but will be cleared to greater widths where ordered by the county engineer. ’ ’ That is, the right of way will be cleared more than fifty feet in width when ordered, thus negativing the idea of a right of way only fifty feet wide, within the lump sum contract price. The other provision quoted, viz: “Clearing outside the right of way shall be done under the same specifications, and be paid for at the same *371 price as clearing within the right of way,” would obviate the necessity for the new contract upon this feature, if finally there was some change in. the exact location of the road as shown on the working profile of the plan.

The roadway was to be leveled and graded to a width of thirty-five feet and, of course, where the surface of the road as graded was level with the natural contour, clearing a width of fifty feet would be sufficient, but the fact was and the profile shows cuts and fills of considerable magnitude, the slopes of the cuts to be three-fourths to one and one to one, and of the fills or embankments one and one-half to one. It was apparent, therefore, that where considerable cuts were made the hillside slopes and slopes of the embankments would extend the width of the clearing more than twenty-five feet on each side of the center line of the roadway.

Appellant makes no contention that these slopes were greater or wider than necessary. Bearing upon this question, there is a disputed question of fact. Appellant’s testimony tended to show that stakes were not set for clearing outside the fifty-foot strip until after that strip had been cleared, arguing therefrom that that strip was thus marked as the right of way, and that afterwards stakes were set to cover the slopes of the cuts and fills,, the clearing of which entitles the appellant to extra compensation. On the other hand, the respondent’s testimony showed that, in advance of the clearing, stakes were set at locations which marked the width of clearing necessary to take care of the proposed slopes; that where no greater width was required, the stakes were set twenty-five feet on each side of the center line; and when greater width was required, they were set at such greater distances. Upon this question of fact, the trial court was of the *372 opinion that the evidence convincingly preponderated in favor of the respondent, and upon our study of the record we are not disposed to disturb that view..

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Davis v. Michigan Trust Co.
2 F.2d 194 (Sixth Circuit, 1924)

Cite This Page — Counsel Stack

Bluebook (online)
268 P. 898, 148 Wash. 367, 1928 Wash. LEXIS 873, Counsel Stack Legal Research, https://law.counselstack.com/opinion/l-romano-co-v-skagit-county-wash-1928.