L. R. & J. Smith Co. v. Cleveland (City)

25 Ohio C.C. Dec. 8, 16 Ohio C.C. (n.s.) 77, 1908 Ohio Misc. LEXIS 303
CourtCuyahoga Circuit Court
DecidedDecember 28, 1908
StatusPublished

This text of 25 Ohio C.C. Dec. 8 (L. R. & J. Smith Co. v. Cleveland (City)) is published on Counsel Stack Legal Research, covering Cuyahoga Circuit Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
L. R. & J. Smith Co. v. Cleveland (City), 25 Ohio C.C. Dec. 8, 16 Ohio C.C. (n.s.) 77, 1908 Ohio Misc. LEXIS 303 (Ohio Super. Ct. 1908).

Opinion

MARVIN, J.

The relation of the parties here is the reverse of the relation in which they stood in the court of common pleas. The terms plaintiff and defendant as used in this opinion will refer to the parties as they stood in the original action.

The plaintiff is .a municipal corporation, and the .defendant is a business corporation.

[9]*9The plaintiff sued to recover from the defendant the sum of $1,903.44, which was paid by the plaintiff to the defendant on July 16, 1898. The petition alleges that this payment was made in pursuance of a fraudulent conspiracy between the defendant and one Geoi’ge R. Warden, then director of publie works of the city of Cleveland, that a claim was presented by the defendant which was fraudulent and that Warden, as director of public works, fraudulently approved the claim, as a result of which the claim was paid.

This matter grew out of work done by the defendant under a written contract entered into between the plaintiff and the defendant on March 24, 1897. Under this contract the defendant undertook to lay a forty-eight inch riveted steel water main in Spruce street across Sycamore street slip in the city of Cleveland. This was to be done under plans and specifications set out in the contract, from which it appears that the work was to consist of removing a portion of the dock on the north side of Sycamore street slip, excavating a trench and laying a forty-eight inch riveted steel pipe across the slip and then restore the dock on said north side and the piling on the south side to their original condition. Certain excavation was provided for in this contract, and it was provided that the contractor must assume all risk as to the material to be excavated. Another of the provisions of the contract reads:

“A portion of the dock on the north side of the slip will have to be removed to make room for the excavating and laying of the pipe. A few piles on the north side of the slip may also have to be removed.”

A further provision of the contract is: ■

“That portion of the dock and all piles that are removed or that are in any way disturbed, must be rebuilt or redriven after the pipe is laid and trench refilled. Any timber piles, etc., damaged in any way must be replaced with new material. If the old piles that are removed should be found of less length than thirty-four feet below the city base of levels, four new piles will have to be furnished and driven two on each side of the pipe, of the length as shown in plan.”

[10]*10Another provision was:

“Any work or material incidental to and necessary for completion of the work must be furnished by the contractor without extra charge, although the same be not mentioned in these specifications or shown on the plans.”

A further provision was:

“No claim for extra work shall be made, unless the same be done in pursuance of a written order from the superintendent of the waterworks, and the price to be paid therefor agreed upon beforehand; said order to be given prior to the doing of said extra work.”

The entire amount to be paid for the work thus contracted for was $1,800.

As the work progressed it was found that by reason of quick sand, a great amount of work was necessary to prevent the docks in the immediate vicinity from giving way or being injured, and that a considerable number of piles had to be put in and certain bolts and spikes used, which the defendant claimed was not a part of the work to be done under the contract. The fact that this work must be done was reported to the superintendent of waterworks by the defendant, and the claim is made by the defendant that he directed the work to be done. However, no written order for any of this work, claimed by the defendant to be “extra,” was given, but, on November 30, 1897, the defendant presented a bill to the officers of the plaintiff for “extra” work, amounting to $1,903.44 in the aggregate. After a considerable time and after consultation between the superintendent of waterworks and the director of public works and the law department of the city, this bill was approved by the director of public works and thereafter paid.

The claim on the part of the plaintiff is that all of the items of this bill are for work and material provided for in the original contract, and that there was no authority for its payment, and that the plaintiff is therefore entitled to recover it back. The defendant denied all fraud; averred that the work and material included in this'bill for “extras” was out[11]*11side of the contract, and that it was ordered by the proper officer of the city, and as a further defense, alleged that the payment was voluntarily made by the city, and that by reason of this voluntary payment the plaintiff was not entitled to recover back the money paid.

The result of the trial in the court of common pleas was a verdict and judgment for the plaintiff for the entire amount.'

A motion for a new trial was made by the defendant, which was overruled, and by proper proceedings the case is here for review.

The court took from the jury the issue of fraud, saying there was no evidence tending to show any fraudulent conspiracy on the part of the defendant and the director of public works, and that the plaintiff, if it recovered at all, must recover without there being any element of fraud in the case.

And then the court said:

“If by reason of the slope at which the trench was dug, or if by reason of quicksand encountered in making the excavation, or if by reason of boats or other craft passing in the slip, before the trench was refurnished with dirt or if by reason of any other cause not attributable to the city, the surrounding soil sank or gave way and thus caused the disturbance of the dock and piles which were restored by the defendant, the defendant in making such restoration would be doing merely that which it was required to do by the contract between the parties, and the work and material furnished by it in so doing would not be extra work and material. ’ ’

We are not prepared to say that this was a misconstruction of the contract, but if the parties, to wit, the defendant and the proper officers of the city, construed it otherwise, their misconstruction was a mistake of law and not a mistake of fact.

The court said also to the jury that the burden of proving that no written order for the “extra” work was given to the defendant was upon the plaintiff. This last instruction is not and could not be complained of by the defendant, because it was admitted by it on the trial, that no written order for this extra work was made, and since the matters specified in that [12]*12part of the charge, hereinbefore quoted, substantially included all that was claimed by the defendant as extras, there was. practically nothing left for the jury to consider as to whether the defendant was entitled to recover anything on its bill against, the city.

On the matter of the voluntary payment the court said, this to the jury:

“However, there is another principle of law to be considered in this connection, which is that notwithstanding the* claim against the city was illegal and no action could have been maintained thereon against the city, yet if the city, through its.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vindicator Printing Co. v. State
67 N.E. 733 (Ohio Supreme Court, 1903)

Cite This Page — Counsel Stack

Bluebook (online)
25 Ohio C.C. Dec. 8, 16 Ohio C.C. (n.s.) 77, 1908 Ohio Misc. LEXIS 303, Counsel Stack Legal Research, https://law.counselstack.com/opinion/l-r-j-smith-co-v-cleveland-city-ohcirctcuyahoga-1908.