L. R. Foy Construction Co. v. Board of Education of School District No. 1

325 P.2d 53, 183 Kan. 25, 1958 Kan. LEXIS 309
CourtSupreme Court of Kansas
DecidedMay 10, 1958
Docket40,863
StatusPublished
Cited by2 cases

This text of 325 P.2d 53 (L. R. Foy Construction Co. v. Board of Education of School District No. 1) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
L. R. Foy Construction Co. v. Board of Education of School District No. 1, 325 P.2d 53, 183 Kan. 25, 1958 Kan. LEXIS 309 (kan 1958).

Opinion

The opinion of the court was delivered by

Price, J.:

Plaintiff construction company, of Hutchinson, submitted a bid for the construction of a school building in Leavenworth. Accompanying the bid was a surety bid bond in the amount of $75,000.00. The bid as submitted was the low bid by a considerable amount and was accepted by the school board. Plaintiff later claimed that due to a mistake its bid was $100,000.00 lower than was intended. Negotiations for settlement of the dispute fell through and the board accepted the next lowest bid, submitted by another contractor.

Plaintiff then brought this action against the school board and school officials to have the bid bond declared null and void and to enjoin defendants from bringing suit on the bond.

From an adverse judgment, plaintiff has appealed.

The record in the case is voluminous, but, briefly stated, the over-all picture is this:

The school board was authorized to issue its bonds in the amount of $1,680,600.00 for a school building, including $125,000.00 for furnishings. Plans and specifications were prepared by the board’s architect, and on February 13, 1957, the board issued invitations for bids. On March 8th a copy of the plans and specifications was mailed to plaintiff construction company, and on April 8th plaintiff submitted its initial bid of $1,750,000.00, intending to amend the bid by wire prior to the formal opening of bids which was set for April 11th at 2:30 P. M. Accompanying this bid was a surety bid bond in the amount of $75,000.00, executed by the American Bonding Company of Baltimore.

*27 At 1:10 P. M. on April 11th, plaintiff, through its employee and estimator, McGaffin, telephoned an amended bid message to the Western Union office in Hutchinson for transmittal to Leavenworth. The message received by the telegraph office in Hutchinson from McGaffin read:

“BASE BID DEDUCT $569,611.00”

This message was immediately transmitted by wire to the telegraph office in Leavenworth and was telephoned by that office to the school board at approximately 1:55 P. M. It will be seen that the “deduct” figure of $569,611.00 contained in the telegram, subtracted from the initial bid of $1,750,000.00 previously submitted, made the revised bid received by the board in the sum of $1,180,-389.00. Other contractors also submitted bids. The next lowest was that by Hunter in the amount of $1,289,831.00. Doolittle’s bid was $1,290,000.00, and that of Bass was $1,307,373.00. Plaintiff’s bid therefore was approximately $109,000.00 less than Hunter’s, the next lowest.

At 2:30 P. M. the board opened the bids at a public meeting and shortly thereafter adjourned to another room to proceed with the letting. After a short discussion, plaintiff’s bid, being the lowest submitted, was accepted and the president of the board started signing the contract forms. In the meantime plaintiff had received a telephone call from a material supplier to the effect that its bid was low by approximately $109,000.00. Plaintiff then called Loebsack the board’s architect, who was present at the letting. This telephone call was made at 3:54 P. M. In this conversation the architect told McGaffin the basic amount of plaintiff’s bid but did not quote plaintiff’s telegram. McGaffin told Loebsack that there “must have been a mistake” and that “it looks like we left our window walls out.” He requested that the board withhold any action but was advised by Loebsack the board had already acted. In this connection, it should be stated that in plaintiff’s general estimate the window walls were listed at $104,950.00, but, contrary to McGaffin’s statement to Loeb-sack, the window walls had not been omitted in making up the bid.

That evening McGaffin again called Loebsack about the matter and contended that plaintiff’s bid should have been for $1,280,389.00 —that is, exactly $100,000.00 higher than its bid which was submitted to and accepted by the board. Plaintiff’s position was that something was “wrong” but it was not sure of just what the trouble was until it discovered that the window walls had not in fact been *28 omitted. The next day plaintiff sent a telegram to the board pointing out the “error” in its former telegram and stating that the correct deduction was in fact $469,611.00, which figure would make plaintiff’s bid in the amount of $1,280,389.00. This figure would make its corrected bid approximately $9,000.00 lower than Hunter’s bid, the next lowest. This telegram also requested that if plaintiff’s corrected bid was not accepted by the board the bid and bond should be returned.

On April 22nd a conference was had with the board, at which Mr. Foy, owner of plaintiff company, Loebsack, McGaffm, and their respective counsel, were present. The matter was gone over in detail. Plaintiff refused to perform under its bid as submitted and accepted by the board, but offered to go ahead and perform under its corrected bid. The board refused, and subsequently let the contract to Hunter for the sum of $1,289,831.00.

Plaintiff then brought this suit to have the bid bond declared null and void and to enjoin the board from bringing suit on it.

The case was tried on May 8th and 9th, and after having the matter under advisement the court made the following findings of fact:

“1. That the organization and respective officers of the parties hereto are as alleged and admitted herein;
“2. That on or about the 13th day of February, 1957, the defendant, the Board of Education of the City of Leavenworth, of the State of Kansas, caused to be issued its certain ‘invitation for bids’ for the construction of said High School buildings at Leavenworth, Kansas, according to plans and specifications prepared for it by its Architects, Thos. W. Williamson, Victor H. Loebsack and Associates;
“3. That the said plans and specifications provided for and included forms for bid, bid bond, agreement and performance bond and provided for bids for the general construction of said High School buildings with certain alternates therein described and that the plaintiff requested and received a copy of the aforesaid plans and specifications;
“4. That on or about the 8th day of April, 1957, the plaintiff caused to be mailed to the defendant Board of Education, its bid for said general contract and alternates and that the bid of the plaintiff for said general contract was $1,750,000.00 and that said bid of the plaintiff with bid bond attached thereto is in proper form and was received by the defendant Board of Education prior to the time provided for the opening of the bids for said construction;
“5. That addenda Number 1 and Number 2 were made to said plans and specifications in proper time and that the plaintiff had adequate notice thereof prior to the time fixed for opening of bids, April 11, 1957;
“6. That on the 11th day of April, 1957, at or about 1:10 P. M. of said day, *29

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Atkinson v. Herington Cattle Co., Inc.
436 P.2d 816 (Supreme Court of Kansas, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
325 P.2d 53, 183 Kan. 25, 1958 Kan. LEXIS 309, Counsel Stack Legal Research, https://law.counselstack.com/opinion/l-r-foy-construction-co-v-board-of-education-of-school-district-no-1-kan-1958.