This text of 466 P.2d 413 (L. M. White Contracting Co. v. Tucson Rock & Sand Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
L. M. White Contracting Co. v. Tucson Rock & Sand Co., 466 P.2d 413, 11 Ariz. App. 540, 1970 Ariz. App. LEXIS 541 (Ark. Ct. App. 1970).

Opinion

HATHAWAY, Judge.

This litigation between Tucson Rock and Sand Company as plaintiff and L. M. White Contracting Company as defendant arose out of the latter’s refusal to permit the plaintiff to enter upon land owned by the defendant and to remove sand and gravel therefrom. The case was tried to the court sitting without a jury and extensive findings of fact and conclusions of law were rendered. The issues as to plaintiff’s right to enter and remove gravel were resolved in its favor, hence this appeal. The trial court, however, denied plaintiff’s claim for damages for the period in which its right was denied, which ruling is subject of the cross appeal.

The judgment entered below declared the defendant to be a constructive trustee of the subject property for the plaintiff’s benefit, that the plaintiff had a profit a prendre in the property consisting of the right to quarry, sever and remove rock, sand and gravel in such quantities and at such times as it desired and until exhaustion of the rock, sand and gravel deposits, and that it had an easement over the defendant’s property to the property which was subject of the profit a prendre. The judgment further ordered that for each cubic yard of material removed by the plaintiff it was to pay to the defendant five cents per cubic yard, that the defendant could make use of the subject property coextensive with that of the plaintiff, and that the constructive trust would terminate upon depletion and exhaustion of all rock, sand and gravel deposits on the subject property.

The trial court made the following factual findings which, in the absence of a “clearly erroneous” showing, we accept as true. Ashton Company, Inc., Contractors and Engineers v. State, 9 Ariz.App. 564, 454 P.2d 1004 (1969). At all material times, the defendant and its predecessor in interest (L. M. White Contracting Company, a sole proprietorship) had extremely close business relationships with the plaintiff. The defendant and plaintiff had interlocking boards of directors, containing common directors; had common officers, managerial employees and stockholders, and common, though not identical, business pursuits. At all times up to the year 1962, Mr. L. M. White was president of the plaintiff corporation and at all times up to and including May, 1955, he was also president of the defendant corporation. (L. M. White Contracting company was incorporated in 1950)

In 1947, the plaintiff purchased a parcel of real property located south of Speedway Boulevard (hereinafter referred to as south borrow pit). This property was purchased because both plaintiff and L. M. White Contracting Company (defendant’s predecessor in interest) were in need of new sources from which to quarry building materials and the property was purchased with the specific intent that it be used as a borrow pit for the mining or quarrying of such materials. At the time of purchase, an oral agreement was entered into between plaintiff and L. M. White Contracting Company, the substance of which was that they would jointly engage in quarry operations in the borrow pit, each having the right to use the pit to the same extent as the other, the only difference being that for each cubic yard of material removed by White Company, it would pay plaintiff at the rate of five cents per cubic yard. Each party had the right to remove as much material as it wanted, as and when needed and desired, and for so long as the source lasted.

*543 Pursuant to this agreement, both parties removed materials from the south borrow pit and between 1951 and 1959, the defendant removed large quantities of material to be used on a very large construction job at Davis Monthan AFB in which plaintiff had no interest. The effect of defendant’s quarrying activity, coupled with plaintiff’s, was to substantially exhaust the deposits in the south borrow pit. At that time, and at the time of trial, deposits suitable for use as building materials and available for quarrying were scarce. The availability of such deposits were extremely important to businesses such as plaintiff’s and defendant’s, and such availability afforded a substantial competitive advantage to them. The plaintiff was not engaged in selling raw materials and would not have allowed the defendant to remove materials from the south borrow pit were it not for the close relationship between the plaintiff and defendant and their oral agreement.

When the defendant’s quarrying operations in the borrow pit achieved such magnitude because of the Davis Monthan construction project, Mr. White, then president of both plaintiff and defendant, instructed employees of both corporations to find additional materials’ sources for their mutual use. Plaintiff, in consideration of a loan to one Martin, was successful in obtaining the privilege of quarrying from Martin’s land for both corporations. Also, the defendant’s general manager who was also a stockholder and director in the plaintiff corporation, located additional deposits of building materials on a realty parcel north of Speedway (hereinafter referred to as the north borrow pit). This parcel was in the general vicinity of the south borrow pit.

The plaintiff and defendant thereupon entered into an oral agreement, the substance of which was that the defendant would purchase this parcel and that both parties would jointly engage in quarrying operations in the new borrow pit, each having the right to use it to the same extent as the other, the only difference being that for each cubic yard of material removed by plaintiff it would pay defendant at the rate of five cents per cubic yard. In all other respects the use of the pit was. to be co-extensive, each party having a right to remove as much material as it wanted, as and when needed and desired, and for so long as the material lasted. (In substance, this agreement was the same as the agreement with reference to the south borrow pit, the only difference being that the defendant expended its funds for purchase of the property and the plaintiff paid for the quantities of material removed).

The latter agreement was entered into' by mutual assent and in good faith, each; party standing in a position of trust and confidence as to the other, and the defendant enjoyed a position of superiority by reason of the common officers, directors and stockholders. In other words, the transaction was not consummated at arms-length. In accordance with this agreement, the defendant purchased the north borrow pit property in 1953 and acquired rights of ingress and egress thereto. Plaintiff, because of the rights it believed it had acquired by virtue of this agreement, allowed the defendant to continue its. quarrying operations in the south borrow pit.

The defendant continued quarrying in the south borrow pit after 1953 and removed substantial amounts of material therefrom; the combination of defendant’s- and plaintiff’s respective quarrying operations resulted in exhaustion of the materials in the south borrow pit. It was not until these materials had been exhausted that the parties commenced quarrying in the north borrow pit. However, when they did begin use of the north pit, their operations were in all respects coextensive, each removing the material it desired, when and as needed, and in such quantities as needed, the plaintiff paying the defendant in the same fashion as defendant had paid plaintiff for materials removed from the south borrow pit.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cal X-Tra v. W.V.S v. Holdings, L.L.C.
276 P.3d 11 (Court of Appeals of Arizona, 2012)
In re United States Currency In Amount of $26,980.00
18 P.3d 85 (Court of Appeals of Arizona, 2000)
Estate of Hernandez v. Flavio
930 P.2d 1309 (Arizona Supreme Court, 1997)
Pioneer Annuity Life Insurance v. National Equity Life Insurance
765 P.2d 550 (Court of Appeals of Arizona, 1988)
Berger v. Mead
338 N.W.2d 919 (Michigan Court of Appeals, 1983)
Murry v. Western American Mortgage Co.
604 P.2d 651 (Court of Appeals of Arizona, 1979)
Rhine v. Miller
583 P.2d 458 (Nevada Supreme Court, 1978)
Fleitz v. Van Westrienen
560 P.2d 430 (Court of Appeals of Arizona, 1977)
Chirekos v. Chirekos
537 P.2d 608 (Court of Appeals of Arizona, 1975)
James Weller, Inc. v. Hansen
517 P.2d 1110 (Court of Appeals of Arizona, 1973)
Nitrini v. Feinbaum
501 P.2d 576 (Court of Appeals of Arizona, 1972)
Terry v. Simmons
496 P.2d 11 (Oregon Supreme Court, 1972)
Ramada Inns, Inc. v. Marriott Corporation
494 P.2d 64 (Court of Appeals of Arizona, 1972)
Norman v. Transamerica Title Insurance
493 P.2d 112 (Arizona Supreme Court, 1972)
Roche v. Golden Sky Lands, Inc.
487 P.2d 756 (Arizona Supreme Court, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
466 P.2d 413, 11 Ariz. App. 540, 1970 Ariz. App. LEXIS 541, Counsel Stack Legal Research, https://law.counselstack.com/opinion/l-m-white-contracting-co-v-tucson-rock-sand-co-arizctapp-1970.