L. G. Defelice, Inc. v. Division of Highways

18 Ct. Cl. 102
CourtWest Virginia Court of Claims
DecidedJanuary 4, 1991
DocketCC-85-388
StatusPublished

This text of 18 Ct. Cl. 102 (L. G. Defelice, Inc. v. Division of Highways) is published on Counsel Stack Legal Research, covering West Virginia Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
L. G. Defelice, Inc. v. Division of Highways, 18 Ct. Cl. 102 (W. Va. Super. Ct. 1991).

Opinion

STEPTOE, JUDGE:

L. G. DeFelice, Inc., claimant contractor, entered into a contract with respondent for the construction of a section of the West Virginia Turnpike also known as Kanawha County Project No.ID-77-2 (37) 71. The contract was awarded to claimant L. G. DeFelice, Inc. (hereinafter to be referred to as DeFelice) on August 13, 1979, for upgrading a section of the West Virginia Turnpike from the existing two lanes to a four-lane highway. The project involved heavy excavation, the construction of two bridges, and concrete payment. The construction area was mountainous on the north end, involving blasting operations for excavation, while the south end of the project consisted of fill areas. The project had a considerable amount of excess excavation which had to be wasted.

The claim has seven causes of action. The first four causes of action are on behalf of the prime contractor, DeFelice. The fifth cause is on behalf of the subcontractor Atlas Machine and Iron Works, Inc. The sixth cause of action is on behalf of the subcontractor Norther Systems, Inc. The seventh cause of action is on behalf of the subcontractor the Vaughn Building Co., which cause of action was withdrawn and dismissed by the Court at the beginning of the hearing of this claim. The total amount of the claim as brought by DeFelice is in the amount of [103]*103$539,238.89. The Court has determined that each cause of action shall be considered and decided separately.

FIRST CAUSE OF ACTION

This claim is for interest on the final payment by respondent. Both parties have agreed that the amount of $976.14 is due and owing to DeFelice pursuant to West Virginia Code Chapter 14, Article 3, Section 1. The Court accordingly makes an award to DeFelice in the amount of $976.14.

SECOND CAUSE OF ACTION

This claim is for delay expense incurred by DeFelice due to the alleged interference with and obstruction of its normal construction operations, by respondent’s having ordered a change in claimant’s blasting schedules.

Site preparation involved the blasting and removal of large quantities of rock and surface and sub-surface material in the northern part of the project area, and transporting it to the southern part of the project area, where it was to be used as fill material.

It appears from the evidence that DeFelice devised a blasting sequence involving three shots per working day, with intervals of about three hours between shots. Such an interval was required for removing random rock falling on the existing turnpike, setting up and taking down temporary barricades, loading and removal of the blasted material, and, principally, for moving blasting equipment from one site, after use, to the next site, and setting it up for the next blast, all in difficult terrain. The system was efficient, and no criticism of it appears to have been made by the respondent.

It further appears from the evidence that, on or about the 22nd day of April, 1980, the respondent, apparently at the insistence of the West Virginia Turnpike Commission which felt that traffic on the existing two-lane turnpike was not moving as briskly as it should, ordered DeFelice to conduct blasting only on even hours of the working day; that DeFelice could not prepare for a succeeding blast in a two-hour period, and was forced to blast at four-hour intervals, and consequently lost production; that by October of 1980 the contractor was some 13% behind in its projected blasting and site preparation schedule; consequently it elected, in order to get back on schedule, to continue blasting and hauling operations during the winter months of December, 1980, and January, February and March of 1981, a period during which all construction operations were usually suspended.

DeFelice contends that respondent's unilateral change of its blasting procedures on or about April 22, 1980, caused it, DeFelice, to be delayed in its performance, and that the delay resulted in extra expense to DeFelice in the amount of $86,356.05. The respondent, the Division of Highways, correctly points out that the respondent had a contractual right to take measures to [104]*104protect traffic on the existing Turnpike and that the order revising the timing of explosions was a lawful exercise of such right for the protection of the Turnpike, and its revenues, and for the convenience of its customers. Be that as it may, the respondent, in exercising its right, made it more expensive for the contractor to perform its duties under the contract.

It is a necessary implication of every contract with promises binding each party that neither will interfere to prevent performance by the other.

17 Am,Jur.2d 899, Contracts §442.

A building contractor may recover damages sustained by him resulting from unreasonable delay on the part of the owner in permitting him to perform his contract.

See Atlantic Coast Line R. Co. v. A. M. Walkup Co., 132 Va. 386, 112 S.E. 663 (1922)

In a contract action where one party has been wronged and has a number of remedies, he may select the most efficient one.'

Cochran v. Ollis Creek Coal Company, 157 W.Va. 931, 206 S.E.2d 410 (1974).

The DeFelice claim consists of:

$51,044.20 for labor,
$ 8,750.48 for equipment expenses,
$10,394.73 for materials used, and,
$7,166.64 for a total of $86,356.05.

The Court finds from a preponderance of the evidence that respondent unreasonably delayed DeFelice in the performance of its duties specified in their contract, and that DeFelice is entitled to recover, in the second cause of action, the sum of $51,044.20, for labor delay, and $8,750.48 for equipment expense delay.

The Court further finds that DeFelice has not proved by a preponderance of the evidence a loss of materials due to the delay caused by the respondent.

The Court disallows that portion of the claim designated as an overhead item, upon the ground that the claim is conjectural and speculative.

See State ex rel. Shatzer v. Freeport Coal Co. et. al., 144 W.Va. 178, 107 S.E.2d 503 (1959).

[105]*105Accordingly, the Court makes an award to DeFelice, on the second cause of action, in the amount of $59,794.68.

THIRD CAUSE OF ACTION

This claim, by DeFelice against the respondent, the Division of Highways, is for delay expense incurred early in the construction period, due to the alleged failure of the respondent to provide a right-of-way for the use of the contractor in hauling, by truck, blasted rock and other surface and subsurface material, from the northern part of the construction area to the southern portion, for use as fill material.

In the contract between DeFelice and the respondent, the latter was required to provide for necessary access to construction areas and necessary rights-of-way for haulage.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cochran v. Ollis Creek Coal Company
206 S.E.2d 410 (West Virginia Supreme Court, 1974)
State Ex Rel. Shatzer v. Freeport Coal Co.
107 S.E.2d 503 (West Virginia Supreme Court, 1959)
Atlantic Coast Line Railroad Co. v. A. M. Walkup Co.
112 S.E. 663 (Supreme Court of Virginia, 1922)
McDonald v. Cole
32 S.E. 1033 (West Virginia Supreme Court, 1899)
L.D.A., Inc. v. Cross
279 S.E.2d 409 (West Virginia Supreme Court, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
18 Ct. Cl. 102, Counsel Stack Legal Research, https://law.counselstack.com/opinion/l-g-defelice-inc-v-division-of-highways-wvctcl-1991.