L. G. De Felice & Son, Inc. v. State

63 Misc. 2d 357, 313 N.Y.S.2d 21, 1970 N.Y. Misc. LEXIS 1956
CourtNew York Court of Claims
DecidedJanuary 22, 1970
DocketClaim No. 48021
StatusPublished

This text of 63 Misc. 2d 357 (L. G. De Felice & Son, Inc. v. State) is published on Counsel Stack Legal Research, covering New York Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
L. G. De Felice & Son, Inc. v. State, 63 Misc. 2d 357, 313 N.Y.S.2d 21, 1970 N.Y. Misc. LEXIS 1956 (N.Y. Super. Ct. 1970).

Opinion

Miltom" Alpebt, J.

Claimant contracted with the State, through the Department of Transportation, to construct a portion of the Interstate Highway System known as the Northway. The portion of the highway to be so constructed by the claimant was located in Warren County and was that portion that ran between the Lake George interchange and Diamond Point Road. The project was identified as F.A. Project No. 1-87-3(59) and claimant’s contract was No. F.I.S.H. 64-15. In addition, claimant contracted for the reconstruction of a portion of the Lake George-Warrensburg Highway No. 5227, identified as F.A. Project No. F-490(8) and claimant’s contract was No. F.A.R.C. 64-14.

The contracts were approved by the State Comptroller on March 23,1964 and were to be completed on or before December 1, 1965.

Among the contract requirements were topsoiling and seeding of designated areas — the contract, as awarded, called for 8,250 cubic yards of topsoil to be provided, spread and seeded.

Claimant entered into the performance of the contract in the spring of 1964. The work proceeded during 1964 and was continued in the spring of 1965, after the shutdown for the winter 196A-1965.

In May of 1965, representatives of the State discussed with representatives of the claimant the possibility that additional topsoil would be required for the project. In the latter part of June of 1965 the necessity for the same became clear and, by Change Order No. 14 dated August 4, 1965 and received by the claimant on August 16, 1965, 18,000' additional cubic yards of topsoil were ordered “ Furnished and Placed.”

In the late summer of 1965 and into the early fall of 1965 claimant was delayed by reason of a two-week strike against its subcontractor engaged in the paving portion of claimant’s contract and also by adverse weather conditions. (See claimant’s Exhibit No. 7 in evidence, wherein claimant’s requested extension of time for completion to July 1, 1966 was granted.)

In late August of 1965 the State began conducting its tests to determine the areas where the additional topsoil should be placed. [359]*359This testing of soil was to be for the purpose of determining whether the original soil at the particular site would support a growth of grass or whether topsoil would be required so that grass could be grown. Such testing was to be at various locations along the route of the work. According to the State’s records, the last soil testing took place on November 2, 1965. As the tests proceeded, claimant procured the topsoil and dumped it on site during October and early November. The total topsoil on November 20, 1965 was estimated by a representative of the State at 39,000 cubic yards and later revised to 37,302 cubic yards; this was an overrun of the original contract amount by 29,052 cubic yards — an increase of almost 400%. It is noted that the 37,302-cubic-yard figure was over 10,000 cubic yards above what had then been formally ordered by the State in the original contract (8,250) and by Change Order No. 14 (18,000).

As a matter of fact, it was not until July 25, 1966 that by Change Order No. 18 an additional 10,000 cubic yards of topsoil were ordered ‘1 Furnished and Placed ’ ’ and ‘1 Seeding ” of an additional 42 acres was ordered by the State. It was generally agreed that this Change Order was confirmatory in nature.

By letter dated September 15,1965 the State advised claimant that the sealing of the stabilized shoulders would not be allowed until all work, except seeding adjacent to the area to be sealed, was completed. Such sealing, therefore, could not be performed until the topsoil dumping and spreading and guardrail work was completed. This was a change in claimant’s plan for the work, as it changed the time sequence in which claimant, with the State’s approval, had projected its work schedules so as to complete all of the work by December 1, 1965. Claimant was, by this September 15, 1965 directive of the State, obligated to withhold doing a portion of its work until almost the very end of its contract. By its original plan, this work was to be done earlier in the job; i.e., before October 15, 1965. In fact in “Public Works Specifications of January 2, 1962”, page 424, it is provided that Item 59W — Bituminous Stabilized Course (Including Shoulders) — may not be “ placed from October 15 to May 15, nor when the air temperature in the shade is below 50°F.”

Faced with such revision of scheduling, delays by the State, extra work required by the State, with the impossibility of completing the sealing work before October 15, as required by the State’s specifications, and with the approach of winter during which spreading and seeding of topsoil could not be done (note that this is in the Lake George-Adirondack Mountains area), claimant on November 15,1965 sought an extension of time under [360]*360the contract until July 1, 1966 and was granted such extension, with engineering and inspection charges assessed after June 15,1966. On May 25,1966, an additional extension to September 1, 1966 was sought and granted, extending the contract, however, only to August 1, 1966, with the same engineering and inspection assessment date as the first extension. On July 19, 1966 a third extension to September 1, 1966 was requested and granted with the original June 15, 1966 assessment date being continued.

The additional topsoil requirements commencing with order on contract No. 14 dated August 4, 1965 for 18,000 more cubic yards, and further directions in the fall of 1965 which were confirmed by order on contract No. 18 dated July 25, 1966 for a further 10,000 cubic yards, required claimant to go over the winter, as the topsoil could not be spread and seeded so late in the year even though the topsoil had been dumped on site in late fall of 1965.

In accordance with claimant’s Exhibit No. 6 in evidence, claimant was to do the topsoil, seeding and clean-up work between August 15, 1965 and December 1, 1965, which latter date was to be the end of the contract work. Yet, how could this be accomplished (a) if the State on September 15,1965 changed the order of the work concerning the sealing of the stabilized shoulders and, in effect, prevented the work to be done before October 15, 1965 as required by the State’s specifications, (b) if the State at that time did not know where and how much topsoil it required and was still testing for topsoil locations as late as November 2, 1965, and (c) where the State increased its topsoil requirements as it did, formally and informally, during the late summer and fall of 1965 from 8,250 cubic yards to a total of about 37,000 cubic yards during the time claimant had planned to complete its topsoil and all other work?

The State’s soil testing, the court finds occurred too late in the year, because the claimant was obligated by its progress schedule to complete all of the topsoil, seeding and cleanup work by the end of November, 1965. By delaying its tests and as the result thereof delaying the determination of where and in what amounts topsoil would he required, the State in effect forced claimant into a situation where there was no choice hut to postpone finishing of the work to the spring and summer of 1966.

Clearly, the claimant could not finish in 1965, as it planned to do, because of the above-described interfering and delaying actions of the State. Then, in 1966, work that was carried over had to be done. As contemplated by the revised schedule for the progress of the work in 1966 the' topsoil work, according to [361]

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
63 Misc. 2d 357, 313 N.Y.S.2d 21, 1970 N.Y. Misc. LEXIS 1956, Counsel Stack Legal Research, https://law.counselstack.com/opinion/l-g-de-felice-son-inc-v-state-nyclaimsct-1970.