L. E. Thompson, and Ruby Thompson v. Commissioner of Internal Revenue

489 F.2d 288, 33 A.F.T.R.2d (RIA) 517, 1974 U.S. App. LEXIS 10659
CourtCourt of Appeals for the Fourth Circuit
DecidedJanuary 9, 1974
Docket72-2498
StatusPublished

This text of 489 F.2d 288 (L. E. Thompson, and Ruby Thompson v. Commissioner of Internal Revenue) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
L. E. Thompson, and Ruby Thompson v. Commissioner of Internal Revenue, 489 F.2d 288, 33 A.F.T.R.2d (RIA) 517, 1974 U.S. App. LEXIS 10659 (4th Cir. 1974).

Opinion

WINTER, Circuit Judge:

The Tax Court decided that the amounts of $67,774.13 and $181,735.63, paid to L. E. Thompson in 1956 in settlement of his claims under his subcontract with Curtis Builders, Inc. (Curtis), which in turn had contracted to build two rocket launchers for the Department of the Navy, accrued and should have been included in the income reported jointly by him and Mrs. Thompson for the years 1953 and 1954. L. E. Thompson, 30 T.C.M. 1383, ¶ 71,321 P-H Memo TC (1971). We disagree, reverse, and remand for further proceedings.

I.

The facts are fully stated in the Tax Court’s memorandum decision and need be only summarized here:

On June 30, 1952, Curtis entered into a contract with the Department of the Navy to construct two rocket launchers for use at the Naval Proving Ground, Dahlgren, Virginia. The work was to be completed by March 29, 1954. Under *289 the contract, Curtis was entitled to receive partial payments as the work progressed. These progress payments could cover delivered materials, work done at the Contractor’s assembly plant, and preparatory work.

Under Article 25 of the prime contract, the government had the right to terminate the agreement, in whole or in part, for default. 1 In the event of such a “default termination,” Curtis was entitled to the reasonable value of “work performed which [was] in place at the site on the effective date of termination.” 2 While the government had the right to require Curtis to deliver work in progress to another contractor and to require that steps be taken to preserve and protect other property, all at the expense of the government, there was no provision for compensation for non-delivered or preparatory work.

The prime contract also made provi-' sion for termination at the' option of the government. 3 In the event of such an “option termination,” Curtis was entitled to whatever amount it and the government contracting officer agreed upon 4 or, failing agreement, to an amount determined under a complex “cost plus” formula. 5 Under an “option *290 termination” therefore, undelivered products and preparatory work were compensable.

On December 30, 1952, Curtis subcontracted with taxpayer L. E. Thompson, d/b/a Parkersburg Die and Tool Company, to fabricate and furnish three rocket launcher track assemblies, each 3,000 feet in length. The subcontract provided that the prime contractor was “bound to the Subcontractor by all the obligations that the Owner assume [d] to the Contractor under the Agreement, General Conditions, Drawings and Specifications, and by all the provisions thereof affording remedies and redress to the Contractor from the Owner.” However, with respect to payment, Curtis and taxpayer did not rely on incorporation of the payment provisions of the original contract. Instead, they agreed that taxpayer would be paid the sum of $249,509.75 for the entire job, with progress payments to be made under the following terms:

90% of value of material on job site by 25th day of each month to be paid by the 15th day of each month following delivery provided that the Subcontractor submits requisition in duplicate to Contractor’s office no later than 25th day of the month. Balance will be paid within thirty days after completion and acceptance by the owner. (emphasis added).

Thus, unlike the prime contractor who was entitled to progress payments for preparatory work and undelivered items, taxpayer’s right to payment under the subcontract was limited to work delivered to the job site.

From June, 1953 to December, 1953, Curtis made loans to the taxpayer and beginning in January, 1954 and continuing until October, 1954, it made a series of weekly advances. The characterization of these payments is not in question here.

The value of certain cast steel yokes shipped to the job site at Dahlgren, Virginia, by directive of the government, and invoiced by taxpayer to Curtis, were shown on taxpayer’s books as reductions in the amount taxpayer owed Curtis on the loans and advances. In this appeal, it is not disputed that the amounts invoiced in 1953 and 1954 were includible in taxpayer’s income for those years. Other than these certain east steel yokes, taxpayer made no other deliveries to the job site.

By letter dated November 30, 1954, Curtis (but not taxpayer) was advised that its contract with the government was terminated “effective immediately due to your default in performance.” While the Curtis contract was thus terminated, the government instructed taxpayer to continue to perform his subcontract, although it does not appear that the government elected to have Curtis formally assign its rights under the subcontract to the government as was the government’s right. 6 Taxpayer protested this directive but was not permitted to discontinue his performance until approximately 70 days after November 30, 1954. It does not appear that Curtis ever took any formal or explicit action to terminate taxpayer’s subcontract.

During the next two years, negotiations were carried on by and between Curtis, taxpayer, and the government. The government finally agreed to rescind the termination of Curtis’ contract for “default in performance” and “ter *291 mination at the option of the government” was substituted. 7 Under the latter, Curtis was entitled to substantial payment and on November 30, 1956, payment by the government was made to Curtis. Of the total payment, $256,135.-85 was paid to Curtis on account of taxpayer’s work. From this sum Curtis deducted $117,000.00 due it for loans and advances to taxpayer and paid $65,744.-94 to the Small Business Administration for the principal and interest on a loan made to the taxpayer. Curtis then paid the taxpayer the remainder of $73,390.-91. Taxpayer and his wife reported as income in their joint income tax return for 1956, the $256,135.85 paid in settlement in that year.

Prior to February, 1954, taxpayer and Curtis’ president discussed what action they would take in the event the government terminated the contract. They agreed that if the contract was terminated, Curtis’ president would request its bonding company to pay taxpayer in full and then either the bonding company or Curtis would employ taxpayer to redesign and construct the rocket launchers. There is no evidence, however, that the bonding company acceded to this agreement, or that the agreement was subsequently carried out.

II.

The Commissioner’s determination that taxpayer followed an accrual method of accounting is unchallenged in this appeal. For accrual method taxpayers, the tax year in which income is includible is determined under Treasury Regulation § 1.451-1 (a), 26 C.F.R. § 1

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Thompson v. Commissioner
1971 T.C. Memo. 321 (U.S. Tax Court, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
489 F.2d 288, 33 A.F.T.R.2d (RIA) 517, 1974 U.S. App. LEXIS 10659, Counsel Stack Legal Research, https://law.counselstack.com/opinion/l-e-thompson-and-ruby-thompson-v-commissioner-of-internal-revenue-ca4-1974.