L. Balkin Builder, Inc. v. State

11 Ill. Ct. Cl. 407, 1939 Ill. Ct. Cl. LEXIS 112
CourtCourt of Claims of Illinois
DecidedNovember 14, 1939
DocketNo. 2957
StatusPublished
Cited by1 cases

This text of 11 Ill. Ct. Cl. 407 (L. Balkin Builder, Inc. v. State) is published on Counsel Stack Legal Research, covering Court of Claims of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
L. Balkin Builder, Inc. v. State, 11 Ill. Ct. Cl. 407, 1939 Ill. Ct. Cl. LEXIS 112 (Ill. Super. Ct. 1939).

Opinion

Mr. Justice Linscott

delivered the opinion of the court:

The claimant filed its complaint with the Clerk of this court on August 26, 1936, and alleged that on or about the 8th day of October, 1935, the respondent, through its proper officers awarded to the claimant, a certain written contract for the construction of a public improvement known as State Bond Issue, Boute 50, Section 101 — SB—NBH 1, which contract was duly accepted by the claimant, a copy thereof being attached to the complaint; that in pursuance of said contract, the claimant performed and completed all of the work as was required to be done by said contract and the plans, specifications and amendments thereto; that the respondent, acting-through its proper officers, on or about the 15th day of April, 1936, requested and directed the claimant to perform and complete additional and extra work for the public improvement as aforesaid, which extra and additional work was not required to be performed according to the terms of the contract, plans, specifications and amendments; that said extra and additional work consisted of excavating and backfilling- a crib wall, and the furnishing of an asphalt plank together with the pumping and drainage of water from said public improvement; that thereafter, pursuant to the authorization, direction and in accordance with' the special instance and request of the respondent, through its proper officers, the claimant excavated and backfilled the said crib wall, furnished and completed the asphalt plank, and pumped and drained the water from said public improvement; that the fair, reasonable and customary charge for said additional and extra work was the sum of $6,022.57.

The common counts are attached under Paragraph 4.

Claimant further charges that there is due and owing to the claimant from the respondent the said sum of $6,022.57, which claim has been presented to the Department of Public Works and Buildings, Division of Highways of the State of Hlinois, but the State has failed and refused to pay that sum.

An affidavit is attached to the complaint, signed by L. Balkin, president of L. Balkin Builders, Inc. In this affidavit he says he has full and complete knowledge of all the facts and that the facts contained in the complaint are true to the best of his knowledge and that the State of Illinois is indebted to the claimant in the sum hereinabove mentioned.

A copy of the contract attached to the complaint is as follows::

“Contract
1. This Agreement, made and concluded this 8th day of October, 1934, between the State of Illinois, acting by and through the Department of Public Works and Buildings, known as the party of the first part, and L. Balkin, Bldr. Inc. his/their executors, administrators, successors or assigns, known as the party of the second part.
2. Witnesseth : That for and in consideration of the payments and agreements mentioned in the Proposal hereto attached, to be made and performed by the party of the first part, and according to the terms expressed in the Bond referring to these presents, the party of the second part agrees with said party of the first part at his/their own proper cost and expense to do all the work, furnish all materials and all labor necessary to complete the work in accordance with the plans and specifications hereinafter described, and in full compliance with all of the terms of this agreement and the requirements of the Engineer under it.
3. And it is also understood and agreed that the Notice to Contractors, Special Provisions, Proposal, and Contract Bond, hereto attached, and the Plans for State Bond Issue Route No. 50 Federal Aid Project No. 141D-NRH, Section 101SBNRH-1, in Cook County, dated March 22, 1934, and the "Standard Specifications for Road and Bridge Construction,” adopted by said Department January 2, 1932, are all essential documents of this contract and are a part hereof.
4. In Witness Whereof, The said parties have executed these presents on the date above mentioned.
The State of Illinois,
By the Department of Public Works and Buildings
By Robert Kxngery, ' Director.
Attest: Party of the First Part.
Ernest Lieberman, (If a corporation)
Acting Superintendent of Highways.
Corporate
Name L. Balkin Builder, Inc.
By L. Balkin, President.
Attest: Party of the Second Part.
H. B. Balkin, Secretary. (If a co-partnership)
(Seal) (Seal)
(Corporate Seal)
.............................(Seal)
Partners doing business under the firm name of
.............................( Seal) ”

The above, consisting of four pages and the signatures thereto, is all that is attached to the complaint, but it is obvious that there are other writings, consisting of plans, specifications and special provisions that are made a part of the contract by special reference, but not copied therein.

The respondent made a motion to dismiss and filed this motion on December 6, 1938. The evidence was filed in this case on November 3, 1938. As grounds for the motion to dismiss it is contended that the claimant has no claim against the State of Illinois arising under the contract referred to in the complaint for reasons not appearing upon the face of claimant’s complaint but appearing from an affidavit attached to the motion to dismiss in support of said motion; that it appears that on October 1, 1934, the claimant made and executed an assignment to the Duffin Iron Company of all its right, title and interest to the sum of $33,986.94, and in and to any and all monies owing, payable and thereafter becoming due or payable to the claimant from the State of Illinois under the contract referred to in the complaint. The affidavit attached to the motion to dismiss was made by M. K. Lingle, Engineer of Claims, Division of Highways, Department of' Public Works and Buildings, State of Illinois, and' he states that there is attached to his affidavit, a true and correct copy of an instrument executed by L. Balkin Builder, Inc., under-date of October 1, 1934, and that the contract mentioned and referred to therein is the same contract mentioned and referred to in the complaint filed in the Court of Claims in this case; that said instrument is in words and figures as follows,, to wit:

“Assignment
"For and in consideration of the sum of One Dollar ($1.00) and other good and valuable considerations to the undersigned in hand paid, receipt whereof is hereby acknowledged, the undersigned, L.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dearborn Associates v. State
35 Ill. Ct. Cl. 624 (Court of Claims of Illinois, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
11 Ill. Ct. Cl. 407, 1939 Ill. Ct. Cl. LEXIS 112, Counsel Stack Legal Research, https://law.counselstack.com/opinion/l-balkin-builder-inc-v-state-ilclaimsct-1939.