L A S A Per L' Industria Del Marmo Societa Per Azioni v. Southern Builders, Inc.

45 F.R.D. 435, 12 Fed. R. Serv. 2d 136, 1967 U.S. Dist. LEXIS 11729
CourtDistrict Court, W.D. Tennessee
DecidedDecember 15, 1967
DocketCiv. No. C-66-261
StatusPublished
Cited by3 cases

This text of 45 F.R.D. 435 (L A S A Per L' Industria Del Marmo Societa Per Azioni v. Southern Builders, Inc.) is published on Counsel Stack Legal Research, covering District Court, W.D. Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
L A S A Per L' Industria Del Marmo Societa Per Azioni v. Southern Builders, Inc., 45 F.R.D. 435, 12 Fed. R. Serv. 2d 136, 1967 U.S. Dist. LEXIS 11729 (W.D. Tenn. 1967).

Opinion

MEMORANDUM DECISION AND ORDER

BAILEY BROWN, Chief Judge.

Southern Builders, Inc. of Tennessee, City of Memphis and Continental Casualty Co. have moved to dismiss a cross-claim filed against them by Alexander Marble and Tile Co., a partnership. A. L. Aydelott and A. L. Aydelott and Associates, Inc. have filed a motion to dismiss a third party complaint filed against them by this same partnership. The contentions are that the cross-claim and third party complaint are not authorized by the Federal Rules of Civil Procedure. Briefs have been filed and arguments heard, after which these motions were taken under advisement.

It will be necessary, properly to present the questions to be decided, to outline the pertinent allegations of the pleadings.

The original complaint was filed by an Italian corporation, referred to herein, for brevity, as “LASA.” This complaint, as twice amended and supplemented, alleges in substance as follows. Southern Builders, a Tennessee corporation, as principal contractor, entered into a contract in 1962 with the City to build a city hall and under the contract obligated itself to the City to pay for all labor and materials. Southern Builders procured and furnished to the City a statutory performance and payment bond, with Continental Casualty as surety, under which Southern Builders obligated itself to the City to perform the contract and to pay for all labor and materials. Alexander Marble and Tile Co., a partnership, whose partners are Tennessee residents, together with Marble International, Inc., a Texas corporation, as joint venturers, entered into a subcontract with Southern Builders under which they were to supply all marble and anchoring devices and install the marble. Alexander then contracted with LASA to supply to it all of the marble for a contract price of $468,641.26, that the [437]*437marble has been supplied as agreed, and that there is a balance due of $127,240.80. The Alexander partnership has since been incorporated and its liabilities assumed by Alexander Marble & Tile Co., Inc., a Tennessee corporation. The City improperly released retainages to the principal contractor, Southern Builders. LASA therefore sues Alexander (partnership and corporation), Marble International, Southern Builders, Continental Casualty and the City for the alleged balance due.1

To this original complaint Alexander (partnership and corporation) filed an answer and counterclaim. (Marble International has not made an appearance, apparently on the theory that effective service of process has not been had as to it. In the cross-claim and third party complaint, which are now before the Court on motions to dismiss, the Alexander partnership sues as such and as a “joint venturer.”) In this answer and counterclaim they contend that the actual net contract price for the marble was only $265,050.00; that, after LASA had failed to ship marble as agreed and had threatened to cease shipments, the price was then under duress increased, first to $336,030.00 and then to $370,686.90; that a total of $406,967.74 has actually been paid to LASA; that much of the marble that was shipped arrived late, was broken, or was of the wrong type; and that LASA had failed to ship all the marble it was obligated to ship. Alexander by this counterclaim sues LASA for overpayment of the contract price and for unliquidated damages for failure to ship marble as agreed.

To this original complaint, Continental Casualty and Southern Builders have filed answers and Southern Builders has filed a counterclaim. They aver that Southern Builders is obligated to pay only “just and valid” claims for labor and materials and that LASA has no such claim; aver that nothing is owed LASA for marble delivered and installed on this job; deny that the City improperly released any retainages; and aver that LASA failed to ship marble as agreed. Southern Builders by its counterclaim sues LASA for all damages to it because of LASA’s failure to ship marble as agreed to Alexander.

Alexander (partnership) has filed a cross-claim against Southern Builders, Continental Casualty and the City. This is the cross-claim that is the subject of one of the motions to dismiss we are here considering.

In this cross-claim, Alexander sues all cross-defendants for a balance alleged to be due under its subcontract with Southern Builders.

In the same cross-claim, it is further averred that Southern Builders, under the insistence of the architect, A. L. Aydelott, hindered Alexander in the performance of the subcontract by failing to properly prepare the concrete base and install metal support angles; by insisting that Alexander work in inclement weather; by insisting that Alexander install the marble in accordance with Aydelott’s improper specifications; and by refusing to pay over funds due Alexander for work done. It is further averred that Southern Builders, under the insistence of Aydelott, wrongfully terminated the subcontract, forced Alexander off the job, and brought in another subcontractor which was allowed to finish the job not in accordance with the original specifications (as Alexander had sought) and at an inflated price. It is further averred that Southern Builders and Aydelott injured the business [438]*438reputation of Alexander by publicly blaming Alexander for many ills not its fault and which were the fault of Southern Builders and Aydelott. Alexander, in this cross-claim, accordingly also sues only Southern Builders for unliquidated damages, actual and punitive.

Southern Builders and Continental Casualty have filed answers to Alexander’s cross-claim against them, and Southern Builders has filed a “counterclaim” (which is probably actually a cross-claim, See 3 Moore, Federal Practice § 13.02) against Alexander. They deny that Southern Builders owes Alexander any balance on the subcontract; deny that it so obstructed Alexander in the performance of the subcontract as alleged; admit that it terminated the subcontract but deny that it acted improperly in doing so; deny that the subcontract was completed at an inflated price and pursuant to different specifications; and deny that it wrongfully injured Alexander’s business reputation as alleged and allege that this claim is barred by limitations. Southern Builders cross-claims against Alexander for any amount it is held to be liable to LASA in the original action. Southern Builders further cross-claims against Alexander for unliquidated damages for not maintaining progress schedules, for faulty materials and workmanship, for overdrawing money pursuant to false project information, and failing generally to follow the specifications, the subcontract, and the general contract.

Alexander has also filed a third party complaint, which has been once amended, against A. L. Aydelott and Associates, Inc. and against Aydelott, individually, who is its principal officer (hereinafter collectively referred to as “Aydelott”) alleging that they had the architectural contract with the City. They are, respectively, a Tennessee corporation and a citizen of Tennessee. This is the third party complaint that is the subject of the other motion to dismiss we are here considering.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
45 F.R.D. 435, 12 Fed. R. Serv. 2d 136, 1967 U.S. Dist. LEXIS 11729, Counsel Stack Legal Research, https://law.counselstack.com/opinion/l-a-s-a-per-l-industria-del-marmo-societa-per-azioni-v-southern-builders-tnwd-1967.