Kyongnam Kim and Isis a to Z Bridal Formal, Inc. v. Antonio Sanchez, D/B/A as D&C Construction

CourtCourt of Appeals of Texas
DecidedSeptember 4, 2014
Docket02-12-00465-CV
StatusPublished

This text of Kyongnam Kim and Isis a to Z Bridal Formal, Inc. v. Antonio Sanchez, D/B/A as D&C Construction (Kyongnam Kim and Isis a to Z Bridal Formal, Inc. v. Antonio Sanchez, D/B/A as D&C Construction) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kyongnam Kim and Isis a to Z Bridal Formal, Inc. v. Antonio Sanchez, D/B/A as D&C Construction, (Tex. Ct. App. 2014).

Opinion

COURT OF APPEALS SECOND DISTRICT OF TEXAS FORT WORTH

NO. 02-12-00465-CV

KYONGNAM KIM AND ISIS A TO Z APPELLANTS BRIDAL FORMAL, INC.

V.

ANTONIO SANCHEZ, D/B/A AS APPELLEE D&C CONSTRUCTION

----------

FROM COUNTY COURT AT LAW NO. 3 OF TARRANT COUNTY TRIAL COURT NO. 2011-002162-3

MEMORANDUM OPINION 1

Kyongnam Kim and Isis A to Z Bridal Formal, Inc. appeal from the trial

court’s judgment awarding breach of contract damages and attorney’s fees to

contractor Antonio Sanchez, doing business as D&C Construction. We affirm.

1 See Tex. R. App. P. 47.4. This case was originally submitted on May 21, 2013. On June 10, 2014, the court, on its own motion, ordered the appeal to be resubmitted on July 1, 2014; assigned this case to a new panel; and assigned the undersigned to author the opinion. Background

Kim initially hired Sanchez to pour a concrete pad and to resurface the

parking lot on property she owned in Bedford, Texas. He completed the work,

but she only paid him $5,000 of the $6,000 she had agreed to pay him. While he

was still doing the work, Kim and Sanchez agreed that he would perform

additional work: framing and finishing a building on the concrete pad. According

to Sanchez, Kim was to pay him periodically so that he could get the supplies he

needed. During the construction, Kim also asked Sanchez to frame a bathroom

area––which he did at no additional charge, to move a door, and to add electrical

to the building. Sanchez hired an electrician to do the electrical; Kim paid the

electrician half of the agreed amount, $1,000, but she did not pay the additional

$1,000. Sanchez had to pay the electrician out of his own pocket.

Sanchez completed all of the framing. But because Kim had not paid him

as she had promised, he did not have the supplies to complete the work. When

he asked Kim for the money needed to complete the project, she told him that

she was waiting for money and would pay him when she received it. Before

Sanchez stopped working on the project, he added temporary roofing material to

protect the inside structure at the City of Bedford’s urging. The only things he left

unfinished were the insulation, sheetrock, paint, texture, and taping; the

permanent roof shingles; and about $100 of electrical work that could not be

finished until the remainder of the inside of the structure was completed.

2 Sanchez eventually sued Kim for breach of contract. A jury found that

although both parties had breached the contracts, Kim did so first. Thus, it

awarded damages of $13,635 and attorney’s fees of $14,280. After the trial, Kim

moved to disregard the damages and attorney’s fees awards because of the

jury’s finding that Sanchez as well as Kim had breached the framing and

electrical contracts; Sanchez responded by moving the trial court to disregard the

finding that he had breached those agreements. The trial court agreed with

Sanchez, finding in its judgment that he was entitled to damages because

(1) Kim breached the contracts first and (2) Sanchez had substantially completed

the contract and, thus, the jury’s findings that he also breached were not

supported by the evidence. The trial court awarded Sanchez the full amount of

the jury’s findings on damages and attorney’s fees, plus pre and postjudgment

interest.

Jury Charge and Damage Issues

In her first issue, Kim argues that the trial court erred by refusing to

disregard the jury’s damages finding because it was rendered immaterial by the

jury’s additional findings that Sanchez also breached the framing and electrical

agreements or, alternatively, because there is no evidence to support the amount

of damages awarded. A trial court may disregard a jury finding if the finding is

immaterial or if there is no evidence to support the finding. GuideOne Lloyds Ins.

Co. v. First Baptist Church of Bedford, 268 S.W.3d 822, 831 (Tex. App.––Fort

Worth 2008, no pet.) (op. on reh’g).

3 The crux of Kim’s argument is that Sanchez could not recover contract

damages if he had also been in breach. But it is “[a] fundamental principle of

contract law . . . that when one party to a contract commits a material breach of

that contract, the other party is discharged or excused from any obligation to

perform.” E.g., Hernandez v. Gulf Grp. Lloyds, 875 S.W.2d 691, 692 (Tex.

1994). The jury found that Kim committed the first breach of the framing and

electrical contracts, a finding which is supported by the evidence that she failed

to pay him on the schedule as the parties had agreed.

Sanchez testified that he and Kim had agreed that she would pay him

some of the money for the framing before it was finished and that he told her he

needed money for materials before starting the roof. He also said several times

that he stopped working only because he had not been paid as agreed and could

not afford to buy shingles for the roof. Thus, there was evidence that Kim’s

failure to pay as agreed prevented Sanchez from completing the work and was

therefore a material breach excusing his further performance. See id. at 693 n.2.

Accordingly, the trial court did not err by denying Kim’s motion to disregard the

jury’s damages and attorney’s fees findings.

Kim further contends that Sanchez could not recover the amount of

damages awarded––even if she had committed a prior material breach excusing

his performance––because he was entitled to recover only under a quantum

meruit theory. See, e.g., Dobbins v. Redden, 785 S.W.2d 377, 378 (Tex. 1990)

(op. on reh’g); Vance v. My Apt. Steak House of San Antonio, 677 S.W.2d 480,

4 482–83 (Tex. 1984). According to Kim, because Sanchez sought the full amount

that he would have earned for completion of the contracts––even though he did

not complete all of the work––and did not seek any alternative damages, he is

entitled to recover only the $1,000 remaining on the first contract for the

concrete, which he did complete. Because her argument challenges the

appropriate measure of damages, it is essentially a challenge to the legal

sufficiency of the evidence supporting the amount of damages awarded.

Kim did not object to the omission of an instruction on the proper measure

of damages, nor did she tender her own instruction. Thus, we must measure the

sufficiency of the evidence to support the damages awarded by the charge as

given. See Equistar Chem., L.P. v. Dresser-Rand Co., 240 S.W.3d 864, 867–68

(Tex. 2007); Osterberg v. Peca, 12 S.W.3d 31, 55 (Tex.), cert. denied, 530 U.S.

1244 (2000); TeleResource Corp. v. Accor N. Am., Inc., 427 S.W.3d 511, 523

(Tex. App.––Fort Worth 2014, pet. denied); see also Arkoma Basin Exploration

Co. v. FMF Assocs.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Equistar Chemicals, L.P. v. Dresser-Rand Co.
240 S.W.3d 864 (Texas Supreme Court, 2007)
Arkoma Basin Exploration Co. v. FMF Associates 1990-A, Ltd.
249 S.W.3d 380 (Texas Supreme Court, 2008)
Bayer Corp. v. DX Terminals, Ltd.
214 S.W.3d 586 (Court of Appeals of Texas, 2007)
Guideone Lloyds Insurance Co. v. First Baptist Church of Bedford
268 S.W.3d 822 (Court of Appeals of Texas, 2008)
Osterberg v. Peca
12 S.W.3d 31 (Texas Supreme Court, 2000)
Dobbins v. Redden
785 S.W.2d 377 (Texas Supreme Court, 1990)
Reynolds v. Nagely
262 S.W.3d 521 (Court of Appeals of Texas, 2008)
Patel v. Ambassador Drycleaning & Laundry Co.
86 S.W.3d 304 (Court of Appeals of Texas, 2002)
Hernandez v. Gulf Group Lloyds
875 S.W.2d 691 (Texas Supreme Court, 1994)
Vance v. My Apartment Steak House of San Antonio, Inc.
677 S.W.2d 480 (Texas Supreme Court, 1984)
TeleResource Corporation v. Accor North America, Inc.
427 S.W.3d 511 (Court of Appeals of Texas, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
Kyongnam Kim and Isis a to Z Bridal Formal, Inc. v. Antonio Sanchez, D/B/A as D&C Construction, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kyongnam-kim-and-isis-a-to-z-bridal-formal-inc-v-a-texapp-2014.