COURT OF APPEALS SECOND DISTRICT OF TEXAS FORT WORTH
NO. 02-12-00465-CV
KYONGNAM KIM AND ISIS A TO Z APPELLANTS BRIDAL FORMAL, INC.
V.
ANTONIO SANCHEZ, D/B/A AS APPELLEE D&C CONSTRUCTION
----------
FROM COUNTY COURT AT LAW NO. 3 OF TARRANT COUNTY TRIAL COURT NO. 2011-002162-3
MEMORANDUM OPINION 1
Kyongnam Kim and Isis A to Z Bridal Formal, Inc. appeal from the trial
court’s judgment awarding breach of contract damages and attorney’s fees to
contractor Antonio Sanchez, doing business as D&C Construction. We affirm.
1 See Tex. R. App. P. 47.4. This case was originally submitted on May 21, 2013. On June 10, 2014, the court, on its own motion, ordered the appeal to be resubmitted on July 1, 2014; assigned this case to a new panel; and assigned the undersigned to author the opinion. Background
Kim initially hired Sanchez to pour a concrete pad and to resurface the
parking lot on property she owned in Bedford, Texas. He completed the work,
but she only paid him $5,000 of the $6,000 she had agreed to pay him. While he
was still doing the work, Kim and Sanchez agreed that he would perform
additional work: framing and finishing a building on the concrete pad. According
to Sanchez, Kim was to pay him periodically so that he could get the supplies he
needed. During the construction, Kim also asked Sanchez to frame a bathroom
area––which he did at no additional charge, to move a door, and to add electrical
to the building. Sanchez hired an electrician to do the electrical; Kim paid the
electrician half of the agreed amount, $1,000, but she did not pay the additional
$1,000. Sanchez had to pay the electrician out of his own pocket.
Sanchez completed all of the framing. But because Kim had not paid him
as she had promised, he did not have the supplies to complete the work. When
he asked Kim for the money needed to complete the project, she told him that
she was waiting for money and would pay him when she received it. Before
Sanchez stopped working on the project, he added temporary roofing material to
protect the inside structure at the City of Bedford’s urging. The only things he left
unfinished were the insulation, sheetrock, paint, texture, and taping; the
permanent roof shingles; and about $100 of electrical work that could not be
finished until the remainder of the inside of the structure was completed.
2 Sanchez eventually sued Kim for breach of contract. A jury found that
although both parties had breached the contracts, Kim did so first. Thus, it
awarded damages of $13,635 and attorney’s fees of $14,280. After the trial, Kim
moved to disregard the damages and attorney’s fees awards because of the
jury’s finding that Sanchez as well as Kim had breached the framing and
electrical contracts; Sanchez responded by moving the trial court to disregard the
finding that he had breached those agreements. The trial court agreed with
Sanchez, finding in its judgment that he was entitled to damages because
(1) Kim breached the contracts first and (2) Sanchez had substantially completed
the contract and, thus, the jury’s findings that he also breached were not
supported by the evidence. The trial court awarded Sanchez the full amount of
the jury’s findings on damages and attorney’s fees, plus pre and postjudgment
interest.
Jury Charge and Damage Issues
In her first issue, Kim argues that the trial court erred by refusing to
disregard the jury’s damages finding because it was rendered immaterial by the
jury’s additional findings that Sanchez also breached the framing and electrical
agreements or, alternatively, because there is no evidence to support the amount
of damages awarded. A trial court may disregard a jury finding if the finding is
immaterial or if there is no evidence to support the finding. GuideOne Lloyds Ins.
Co. v. First Baptist Church of Bedford, 268 S.W.3d 822, 831 (Tex. App.––Fort
Worth 2008, no pet.) (op. on reh’g).
3 The crux of Kim’s argument is that Sanchez could not recover contract
damages if he had also been in breach. But it is “[a] fundamental principle of
contract law . . . that when one party to a contract commits a material breach of
that contract, the other party is discharged or excused from any obligation to
perform.” E.g., Hernandez v. Gulf Grp. Lloyds, 875 S.W.2d 691, 692 (Tex.
1994). The jury found that Kim committed the first breach of the framing and
electrical contracts, a finding which is supported by the evidence that she failed
to pay him on the schedule as the parties had agreed.
Sanchez testified that he and Kim had agreed that she would pay him
some of the money for the framing before it was finished and that he told her he
needed money for materials before starting the roof. He also said several times
that he stopped working only because he had not been paid as agreed and could
not afford to buy shingles for the roof. Thus, there was evidence that Kim’s
failure to pay as agreed prevented Sanchez from completing the work and was
therefore a material breach excusing his further performance. See id. at 693 n.2.
Accordingly, the trial court did not err by denying Kim’s motion to disregard the
jury’s damages and attorney’s fees findings.
Kim further contends that Sanchez could not recover the amount of
damages awarded––even if she had committed a prior material breach excusing
his performance––because he was entitled to recover only under a quantum
meruit theory. See, e.g., Dobbins v. Redden, 785 S.W.2d 377, 378 (Tex. 1990)
(op. on reh’g); Vance v. My Apt. Steak House of San Antonio, 677 S.W.2d 480,
4 482–83 (Tex. 1984). According to Kim, because Sanchez sought the full amount
that he would have earned for completion of the contracts––even though he did
not complete all of the work––and did not seek any alternative damages, he is
entitled to recover only the $1,000 remaining on the first contract for the
concrete, which he did complete. Because her argument challenges the
appropriate measure of damages, it is essentially a challenge to the legal
sufficiency of the evidence supporting the amount of damages awarded.
Kim did not object to the omission of an instruction on the proper measure
of damages, nor did she tender her own instruction. Thus, we must measure the
sufficiency of the evidence to support the damages awarded by the charge as
given. See Equistar Chem., L.P. v. Dresser-Rand Co., 240 S.W.3d 864, 867–68
(Tex. 2007); Osterberg v. Peca, 12 S.W.3d 31, 55 (Tex.), cert. denied, 530 U.S.
1244 (2000); TeleResource Corp. v. Accor N. Am., Inc., 427 S.W.3d 511, 523
(Tex. App.––Fort Worth 2014, pet. denied); see also Arkoma Basin Exploration
Co. v. FMF Assocs.
Free access — add to your briefcase to read the full text and ask questions with AI
COURT OF APPEALS SECOND DISTRICT OF TEXAS FORT WORTH
NO. 02-12-00465-CV
KYONGNAM KIM AND ISIS A TO Z APPELLANTS BRIDAL FORMAL, INC.
V.
ANTONIO SANCHEZ, D/B/A AS APPELLEE D&C CONSTRUCTION
----------
FROM COUNTY COURT AT LAW NO. 3 OF TARRANT COUNTY TRIAL COURT NO. 2011-002162-3
MEMORANDUM OPINION 1
Kyongnam Kim and Isis A to Z Bridal Formal, Inc. appeal from the trial
court’s judgment awarding breach of contract damages and attorney’s fees to
contractor Antonio Sanchez, doing business as D&C Construction. We affirm.
1 See Tex. R. App. P. 47.4. This case was originally submitted on May 21, 2013. On June 10, 2014, the court, on its own motion, ordered the appeal to be resubmitted on July 1, 2014; assigned this case to a new panel; and assigned the undersigned to author the opinion. Background
Kim initially hired Sanchez to pour a concrete pad and to resurface the
parking lot on property she owned in Bedford, Texas. He completed the work,
but she only paid him $5,000 of the $6,000 she had agreed to pay him. While he
was still doing the work, Kim and Sanchez agreed that he would perform
additional work: framing and finishing a building on the concrete pad. According
to Sanchez, Kim was to pay him periodically so that he could get the supplies he
needed. During the construction, Kim also asked Sanchez to frame a bathroom
area––which he did at no additional charge, to move a door, and to add electrical
to the building. Sanchez hired an electrician to do the electrical; Kim paid the
electrician half of the agreed amount, $1,000, but she did not pay the additional
$1,000. Sanchez had to pay the electrician out of his own pocket.
Sanchez completed all of the framing. But because Kim had not paid him
as she had promised, he did not have the supplies to complete the work. When
he asked Kim for the money needed to complete the project, she told him that
she was waiting for money and would pay him when she received it. Before
Sanchez stopped working on the project, he added temporary roofing material to
protect the inside structure at the City of Bedford’s urging. The only things he left
unfinished were the insulation, sheetrock, paint, texture, and taping; the
permanent roof shingles; and about $100 of electrical work that could not be
finished until the remainder of the inside of the structure was completed.
2 Sanchez eventually sued Kim for breach of contract. A jury found that
although both parties had breached the contracts, Kim did so first. Thus, it
awarded damages of $13,635 and attorney’s fees of $14,280. After the trial, Kim
moved to disregard the damages and attorney’s fees awards because of the
jury’s finding that Sanchez as well as Kim had breached the framing and
electrical contracts; Sanchez responded by moving the trial court to disregard the
finding that he had breached those agreements. The trial court agreed with
Sanchez, finding in its judgment that he was entitled to damages because
(1) Kim breached the contracts first and (2) Sanchez had substantially completed
the contract and, thus, the jury’s findings that he also breached were not
supported by the evidence. The trial court awarded Sanchez the full amount of
the jury’s findings on damages and attorney’s fees, plus pre and postjudgment
interest.
Jury Charge and Damage Issues
In her first issue, Kim argues that the trial court erred by refusing to
disregard the jury’s damages finding because it was rendered immaterial by the
jury’s additional findings that Sanchez also breached the framing and electrical
agreements or, alternatively, because there is no evidence to support the amount
of damages awarded. A trial court may disregard a jury finding if the finding is
immaterial or if there is no evidence to support the finding. GuideOne Lloyds Ins.
Co. v. First Baptist Church of Bedford, 268 S.W.3d 822, 831 (Tex. App.––Fort
Worth 2008, no pet.) (op. on reh’g).
3 The crux of Kim’s argument is that Sanchez could not recover contract
damages if he had also been in breach. But it is “[a] fundamental principle of
contract law . . . that when one party to a contract commits a material breach of
that contract, the other party is discharged or excused from any obligation to
perform.” E.g., Hernandez v. Gulf Grp. Lloyds, 875 S.W.2d 691, 692 (Tex.
1994). The jury found that Kim committed the first breach of the framing and
electrical contracts, a finding which is supported by the evidence that she failed
to pay him on the schedule as the parties had agreed.
Sanchez testified that he and Kim had agreed that she would pay him
some of the money for the framing before it was finished and that he told her he
needed money for materials before starting the roof. He also said several times
that he stopped working only because he had not been paid as agreed and could
not afford to buy shingles for the roof. Thus, there was evidence that Kim’s
failure to pay as agreed prevented Sanchez from completing the work and was
therefore a material breach excusing his further performance. See id. at 693 n.2.
Accordingly, the trial court did not err by denying Kim’s motion to disregard the
jury’s damages and attorney’s fees findings.
Kim further contends that Sanchez could not recover the amount of
damages awarded––even if she had committed a prior material breach excusing
his performance––because he was entitled to recover only under a quantum
meruit theory. See, e.g., Dobbins v. Redden, 785 S.W.2d 377, 378 (Tex. 1990)
(op. on reh’g); Vance v. My Apt. Steak House of San Antonio, 677 S.W.2d 480,
4 482–83 (Tex. 1984). According to Kim, because Sanchez sought the full amount
that he would have earned for completion of the contracts––even though he did
not complete all of the work––and did not seek any alternative damages, he is
entitled to recover only the $1,000 remaining on the first contract for the
concrete, which he did complete. Because her argument challenges the
appropriate measure of damages, it is essentially a challenge to the legal
sufficiency of the evidence supporting the amount of damages awarded.
Kim did not object to the omission of an instruction on the proper measure
of damages, nor did she tender her own instruction. Thus, we must measure the
sufficiency of the evidence to support the damages awarded by the charge as
given. See Equistar Chem., L.P. v. Dresser-Rand Co., 240 S.W.3d 864, 867–68
(Tex. 2007); Osterberg v. Peca, 12 S.W.3d 31, 55 (Tex.), cert. denied, 530 U.S.
1244 (2000); TeleResource Corp. v. Accor N. Am., Inc., 427 S.W.3d 511, 523
(Tex. App.––Fort Worth 2014, pet. denied); see also Arkoma Basin Exploration
Co. v. FMF Assocs. 1990-A, Ltd., 249 S.W.3d 380, 387 (Tex. 2008) (providing
that legal sufficiency complaint may be raised by post-trial motion challenging a
single jury question).
The damage instruction read as follows:
What sum of money, if any, if paid in cash, would fairly and reasonably compensate Antonio Sanchez for his damages, if any, that resulted from Kim Kyongnam’s failure to comply with the agreement between Antonio Sanchez and Kim Kyongnam?
Consider the following elements of damages, if any, and none other.
5 Do not increase or reduce the amount in one answer because of your answer to any other question about damages. Do not speculate about [what] any party’s ultimate recovery may or may not be. Any recovery will be determined by the Court when it applies the law to your answers at the time of judgment. Do not add any amount for interest on damages, if any.
Kim concedes that she owes $1,000 remaining unpaid on the first contract
for the concrete pad and parking. Sanchez testified that Kim owed him $1,000
for the first contract, $1,000 for the electrical contract that he paid out of his own
pocket, and $11,635 for the framing contract (including $1,000 for moving the
door). 2 He further testified that the cost to complete the remaining framing and
electrical work was roughly equivalent to what he had spent out of pocket on that
part of the job, including purchasing materials for the temporary roof. He sought
these out-of-pocket expenses as additional damages, arguing during closing that
he should recover that amount. Accordingly, we conclude and hold that there is
sufficient evidence to support the total damages award of $13,635. We overrule
Kim’s first issue.
In her second issue, Kim contends that the trial court erred by disregarding
the jury’s findings that Sanchez failed to comply with the framing and electrical
2 Sanchez presented evidence that the initial contract amount for the framing was $15,635, increased by agreement of the parties to $16,635 with the inclusion of the movement of the door. Sanchez presented further evidence that Kim had paid a total of $3,000 toward the framing contract. Thus, the jury awarded him $2,000 less than the full price of the framing contract ($1,000 for the concrete pad, $1,000 for the electrical, and $11,635 for the framing). Accordingly, contrary to Kim’s argument on appeal, Sanchez did not recover damages for full performance rather than substantial completion.
6 agreements. She points out that even Sanchez admits that he did not fully
complete the work under those contracts.
The legal doctrine of substantial performance generally permits a party to a
contract who breaches nonmaterial terms (but has otherwise substantially
performed) to sue the other party to the contract for breach. Bayer Corp. v. DX
Terminals, Ltd., 214 S.W.3d 586, 598 n.11 (Tex. App.––Houston [14th Dist.]
2006, pet. denied); Patel v. Ambassador Drycleaning Co., 86 S.W.3d 304, 306
(Tex. App.––Eastland 2002, no pet.). Thus, it was not necessary for the trial
court to render an order disregarding the jury’s finding that Sanchez breached
the framing and electrical agreements. However, even if the trial court erred by
disregarding these findings, the error is not reversible because the evidence
supports the judgment for damages based on Kim’s prior material breach. See
Tex. R. App. P. 44.1(a). We overrule Kim’s second issue.
In her third issue, Kim contends that the trial court erred by including in the
judgment $1,000 in damages for Sanchez’s moving the location of a door when
there was no separate jury question asking whether Kim had breached an
agreement to move the door. The jury could have reasonably inferred from
Sanchez’s testimony that he and Kim agreed that he would move the door for
$1,000 as an addition to the scope of work on the framing agreement: according
to Sanchez, after he began the framing work, the city required the door to be
moved, and Kim asked him to move it. He told her he would move it for an
additional $1,250, and they agreed on $1,000. Thus, the evidence supports a
7 reasonable inference that the agreement to move the door was an addition to the
scope of work of the framing agreement. Because the evidence also showed
that Kim still owed substantially more than $1,000 on the framing agreement
work, the trial court did not err by incorporating the jury’s damage finding into the
judgment. We overrule Kim’s third issue.
Attorney’s Fees
In her fourth issue, Kim contends that Sanchez is precluded from
recovering attorney’s fees because his supplemental response to her request for
disclosures regarding experts was deficient. See Tex. R. Civ. P. 194.2(f).
According to Kim, “No information was provided concerning the amount of
attorney’s fees sought; the method of calculation of fees by hourly rate or
contingency; or the number of anticipated hours expended in preparation for trial.
Additionally, no documents were produced such as billing records or fee
agreement as also required.”
Rule of civil procedure 194.2(f) allows a party to request disclosure of the
general substance of an expert’s mental impressions and opinions and a brief
summary of the basis for them. Id.; Goldman v. Olmstead, 414 S.W.3d 346, 365
(Tex. App.—Dallas 2013, pet. denied). In response to Kim’s request for
disclosure of any expert witness, Sanchez stated the following: “Mr. Moore is
expected to testify regarding the reasonable and necessary attorney fees that
were necessary in prosecuting this case and in rebuttal to any attorney fee
testimony offered by an expert on behalf of Defendant.”
8 A disclosure identifying an attorney’s fees expert that states that the expert
will be testifying about the reasonableness and necessity of attorney’s fees
sought is sufficient to give the “general substance” of that expert’s anticipated
testimony, especially when, as here, the responding party is seeking fees for
representation during the entire litigation, which are not determinable at the time
of disclosure. See Goldman, 414 S.W.3d at 365; Reynolds v. Nagely, 262
S.W.3d 521, 531 (Tex. App.––Dallas 2008, pet. denied). Accordingly, we
conclude and hold that the trial court did not abuse its discretion by allowing
Sanchez’s counsel to testify regarding his attorney’s fees. We overrule Kim’s
fourth issue.
Conclusion
Having overruled Kim’s four issues, we affirm the trial court’s judgment.
/s/ Terrie Livingston
TERRIE LIVINGSTON CHIEF JUSTICE
PANEL: LIVINGSTON, C.J.; WALKER, J.; and CHARLES BLEIL (Senior Justice, Retired, Sitting by Assignment).
DELIVERED: September 4, 2014