KVAERNER E & C (METALS) v. Yellow Freight Systems, Inc.

266 F. Supp. 2d 1065, 2003 U.S. Dist. LEXIS 14711, 2003 WL 21339930
CourtDistrict Court, N.D. California
DecidedMay 12, 2003
DocketC02-1202 BZ
StatusPublished
Cited by1 cases

This text of 266 F. Supp. 2d 1065 (KVAERNER E & C (METALS) v. Yellow Freight Systems, Inc.) is published on Counsel Stack Legal Research, covering District Court, N.D. California primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
KVAERNER E & C (METALS) v. Yellow Freight Systems, Inc., 266 F. Supp. 2d 1065, 2003 U.S. Dist. LEXIS 14711, 2003 WL 21339930 (N.D. Cal. 2003).

Opinion

FINDINGS OF FACT AND CONCLUSIONS OF LAW

ZIMMERMAN, United States Magistrate Judge.

Plaintiff Kvaerner E & C (Metals) filed this action against defendant Yellow Freight System, Inc. under the Carmack Amendment to the Interstate Commerce Act, 49 U.S.C. § 14706. 1 Plaintiff’s claim arises out of a shipment of pumps by defendant to plaintiff in December 1999 and January 2000. Several pumps sustained damage ip. transit. In an April 4, 2003 Order, I granted plaintiffs motion for *1066 summary judgment on the issues of liability and the amount of damages, except for interest. Remaining for trial was the issue whether plaintiff gave defendant timely and adequate written notice of claim.

Trial commenced on May 5, 2003. Having considered and weighed the parties’ undisputed facts and the evidence adduced at trial, and having assessed the credibility of the witnesses, I now make these findings of fact and conclusions of law as required by Federal Rule of Civil Procedure 52(a).

FINDINGS OF FACT

1. On December 80, 1999 and January 4, 5, 11 and 12, 2000, defendant delivered pumps to plaintiffs job site in Calipatria, California. Several pumps had sustained damage in transit. On or about January 6, 2000, defendant inspected some of the pumps and completed an inspection report.

2. On February 8, 2000, plaintiffs project manager, Norm Williams, submitted a letter entitled, “Notice of Freight Claim,” to Denver Price, the manager of defendant’s Calexico, California terminal. The letter stated that plaintiff was undertaking to repair and test the damaged pumps, but that “some of the damage is substantial and will be costly to repair,” and that plaintiff “faces time-related liquidated damages which will far exceed” the repair costs. The letter also stated that it “shall serve as notice that Kvaerner intends to submit a damage claim to Yellow Freight to recover all costs.... Kvaerner will quantify and price the claim as soon as the damage is fully estimated (emphasis added).” Attached to the letter was a list of twenty-two damaged pumps, describing the damage to each pump.

3. On February 8, 2000 Mr. Williams did not have any estimates of the cost of repair or the other possible elements of damage. Mr. Williams was aware of the nine-month limitations period for submitting a claim and the need to quantify the claim, and intended to do so when he had the amounts.

4. After receiving the damaged pumps, plaintiff shipped them to Ingersoll Dresser Pump Company for repair or replacement. On or about March 21, 2000, plaintiff received an invoice from Ingersoll for $65,129.16 for the work. In total, plaintiff incurred $75,981.00 in damages to repair or obtain pumps in good condition, including additional freight charges and time lost.

5. In March 2000, after Mr. Williams received Ingersoll’s invoice, he prepared a spreadsheet identifying plaintiffs damages. Mr. Williams called Mr. Price, told him the damage amount and asked him where to send the information. Mr. Price told Mr. Williams to call the toll free number for defendant’s claims department. Mr. Williams called the claims department and inquired as to the procedure for submitting his cost information. He was told that he had to submit the information on defendant’s claim forms, which were sent to him. Mr. Williams testified that completing defendant’s forms was difficult and tedious because he had to link each damaged pump to one of defendant’s freight bills, . information not captured on his spreadsheet.

6. When defendant is notified of damage to a shipment and inspects the damage, an inspection report is completed. Less then 5% of defendant’s inspection reports ripen into a claim. Defendant receives approximately 75,000 claims per year, of which approximately 50% are paid. Of the claims that are denied, fewer than 1% are declined on the basis that they were not timely filed. A claim need not be submitted on defendant’s claim forms, but any written claim must contain basic information to be processed. If a written claim contains the required basic information but *1067 only a preliminary cost estimate, the claims department will issue a claim number and the claim will be processed once the final amount is received.

7. On or about December 13, 2000, a few days before Mr. Williams left plaintiffs employ, he completed the claim forms and sent them to defendant via Federal Express. Neither party has a copy of those forms and defendant denied receiving them.

8. Having received no communication from defendant, on October 30, 2001, plaintiff submitted a follow-up on defendant’s claim form. On November 2, 2001, defendant requested further information, which plaintiff submitted on November 13 and 14, 2001.

9. Defendant denied the claim on November 21, 2001 as not having been filed within nine months of delivery.

CONCLUSIONS OF LAW

1. A notice of claim must be in writing and contain (1) “facts sufficient to identify the ... shipment ... of property, (2) [an assertion] of liability for alleged loss, damage, injury or delay, and (3) a claim for the payment of a specified or determinable amount of money.” 49 C.F.R. § 1005.2(b).

2. The parties agree that plaintiffs claim should have been filed within nine months of delivery of the pumps, or by no later than mid September, 2000. See 49 C.F.R. § 1005.2 (a claim must be filed “within the time limits specified in the bill of lading.”).

3. The federal circuits are split as to whether a claim must specify a dollar amount to be legally sufficient under 49 C.F.R. § 1005.2(b). Compare Nedlloyd Lines v. Harris Transport, 922 F.2d 905, 907 (1st Cir.1991) and Pathway Bellows, Inc. v. Blanchette, 630 F.2d 900, 904 (2nd Cir.1980) (letters that did not specify an amount of money failed to meet the regulatory requirements) with Insurance Co. of No. Am. v. G.I. Trucking Co., 1 F.3d 903, 906 (9th Cir.1993) (rejecting Nedlloyd and Pathway Bellows). The Ninth Circuit has held that “written claims are to be construed liberally and that the standard for determining sufficiency is one of substantial performance.” The purpose of the claim requirement is “not to permit the carrier to escape liability, but to insure that the carrier may make a prompt and thorough investigation of the claim.” Insurance Co., 1 F.3d at 906, 907.

4.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
266 F. Supp. 2d 1065, 2003 U.S. Dist. LEXIS 14711, 2003 WL 21339930, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kvaerner-e-c-metals-v-yellow-freight-systems-inc-cand-2003.