Kushner v. Dravo Corp.

158 N.E.2d 858, 339 Mass. 273, 1959 Mass. LEXIS 798
CourtMassachusetts Supreme Judicial Court
DecidedMay 26, 1959
StatusPublished
Cited by19 cases

This text of 158 N.E.2d 858 (Kushner v. Dravo Corp.) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kushner v. Dravo Corp., 158 N.E.2d 858, 339 Mass. 273, 1959 Mass. LEXIS 798 (Mass. 1959).

Opinion

Whittemore, J.

The plaintiff had a verdict in this action of tort to recover for damage to the plaintiff’s dwelling house at 375 Broadway, Somerville, allegedly caused by negligent blasting by the defendant under a contract with the metropolitan district commission (the commission). The defendant excepted to the denial of its motion for a directed verdict, to the admission of evidence of an alleged expert on blasting called by the plaintiff,'and to the judge’s charge.

The jury could have found facts as follows: The .defendant, under the contract, was excavating a shaft ("Shaft 9”) to connect with a tunnel to be used to provide water for the *275 Boston metropolitan area. This shaft was approximately 1,450 feet from the plaintiff’s house.

The plaintiff was in her home on March 16, 1953, at two o’clock in the afternoon when she heard “sort of a roar or rumble.” She was “jounced.” She heard falling objects downstairs. All of her canned goods in the pantry had fallen to the floor. Objects fell from a table and a vase toppled over. There were cracks in several ceilings and a. stairway was “slanted.” On March 17 before six o’clock in the morning she heard another “roar” which shook the house. There were similar occurrences on March 18 at about quarter of five in the afternoon but not thereafter. 1

The defendant’s daily blasting report showed that the defendant set off a blast of 180 pounds on March 16 at 2 p.m., no blast on March 17, a blast of 180 pounds on March 18 at 5:45 p.m., and a blast of 163 pounds on March 20. It showed also that beginning on March 23, all blasts were set off with the use of “delays,” that is, the total charge of powder was divided into several smaller charges, each of which was set off successively. Delays were not used in any of the blasts prior to March 23, but were used on April 3 when the pounds detonated were 172; on March 24 for 212 pounds; March 30, 200 pounds; April 4, 212 pounds; and April 11, 208 pounds. Other poundages after March 23 were larger.

The contract specifications required that “Blasting shall be done with explosives of such power and in such quantities and positions as will not . . . damage any existing structures. To this end, every blast in the shaft shall be exploded, by use of delays, in stages consistent with the location, type and character of the rock. . . . The contractor . . . will ... be held responsible for and shall make good any damage to other property whether or not owned by the commission.” The department of public safety rules and regulations form Y provides: “In blasting operations, no charge shall be used in any one blast which will result in *276 injury to persons or property. When it is necessary to blast in close proximity to a building or other structure, light face blasts only, with short lines of resistance and small charges, shall be used. . . .”

There was testimony that a single charge generates more earth movement than a series of delays. An expert for the defendant testified that “[T]t is usual and standard procedure to use delays in solid rock.”

The daily report shows progressive lower elevations from —12 feet on March 23 to —172 feet on May 9, 1953. The —12 figure means 12 feet below sea level which in the shaft was about 60 feet below the surface. The overburden was about 28 feet. The blasting was all in bedrock except to remove occasional large boulders in the overburden. Testimony that on March 23 the depth was 60 feet (or 63 feet as shown on the daily report) and the overburden was 28 feet, permitted the conclusion that the blasting had been in solid rock for some time. The daily record sheet shows that in rock the average increase in depth from blast to blast (with no blasting on some days) was about 6% feet. March 21 and 22, 1953, were respectively Saturday and Sunday. The jury could have concluded therefore that on March 16 and 18 (and on the 17th if there was a blast on that day) the defendant was blasting in solid rock. 1

The defendant admits that the testimony would warrant a finding of causation (see Coffey v. West Roxbury Trap Rock Co. 229 Mass. 211, 213; Dalton v. Demos Bros. Gen. Contractors, Inc. 334 Mass. 377) but not of negligence.

1. A majority of the court thinks there was evidence of negligence. The contract which in its requirement of delays made specific the provision of the rule for the use of small charges where necessary to avoid injury was of course not admissible to establish a duty to the plaintiff. In Hampson v. Larkin, 318 Mass. 716, we held that the charge was correct that the owner’s contractual obligation to the builder *277 did not vary or heighten the duty of the owner to an injured architect to have reasonably safe instrumentalities; the contract did not make the defendant an insurer. The principle exemplified in that case does not however bar the contract as evidence of negligence. The defendant owed a duty to all persons whose property might be injured to refrain from negligent operation. O’Regan v. Verrochi, 325 Mass. 391, 392-393, and cases cited. The contract requirement did not alter that duty but it did furnish some evidence of what was due care in the circumstances. The safety requirements of the contract were, in the first instance, imposed by a public agency, experienced in construction, for the protection of the public. The standard of care thus established was comparable to those which might be imposed by a municipal ordinance or a departmental regulation. The contract made specific for this work the safety regulation of the department of public safety. The contractor, by executing the contract, joined in imposing the safety requirements as a term of the contract, and hence in establishing the standard. The contractual standard is somewhat analogous to that imposed by company rules, the violation of which may be evidence of negligence. See Stevens v. Boston Elev. Ry. 184 Mass. 476, 479-480; McNeil v. New York, N.H. & H. R.R. 282 Mass. 575, 577. Our cases have long held that evidence of a general practice or of what is customarily done by others may, in the judge’s discretion, be received on the issue of negligence. Myers v. Hudson Iron Co. 150 Mass. 125, 138. Hendrick v. Boston & Albany R.R. 170 Mass. 44, 48. Dolan v. Boott Cotton Mills, 185 Mass. 576, 579. Moynihan v. Holyoke, 193 Mass. 26. Draper v. Cotting, 231 Mass. 51, 59. Edgarton v. H. P. Welch Co. 321 Mass. 603, 609. See Corthell v. Great Atl. & Pac. Tea Co. 291 Mass. 242, 243-244; Robitaille v. Netoco Community Theatre of No. Attleboro, Inc. 305 Mass. 265, 268. Wigmore on Evidence (3d ed.) § 461 (6).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bernier v. Smitty's Sports Pub, Inc.
59 N.E.3d 1192 (Massachusetts Appeals Court, 2016)
Cabreira v. Verizon New England, Inc.
22 Mass. L. Rptr. 649 (Massachusetts Superior Court, 2007)
Dalbo v. Chang
1995 Mass. App. Div. 107 (Mass. Dist. Ct., App. Div., 1995)
Demirgian v. Star Market Co.
1994 Mass. App. Div. 75 (Mass. Dist. Ct., App. Div., 1994)
Bacon v. Federal Kemper Life Assurance Co.
512 N.E.2d 941 (Massachusetts Supreme Judicial Court, 1987)
Corsetti v. Stone Co.
483 N.E.2d 793 (Massachusetts Supreme Judicial Court, 1985)
Zedros v. Kenneth Hudson, Inc.
418 N.E.2d 1279 (Massachusetts Appeals Court, 1981)
Upham v. Chateau De Ville Dinner Theatre, Inc.
403 N.E.2d 350 (Massachusetts Supreme Judicial Court, 1980)
Coalite, Inc. v. Aldridge
229 So. 2d 524 (Alabama Court of Appeals, 1968)
Killeen v. Sharpe & Wiley, Inc.
40 Mass. App. Dec. 26 (Mass. Dist. Ct., App. Div., 1968)
Carney v. Bereault
204 N.E.2d 448 (Massachusetts Supreme Judicial Court, 1965)
Bristol Wholesale Grocery Co. v. Municipal Lighting Plant Commission of Taunton
200 N.E.2d 260 (Massachusetts Supreme Judicial Court, 1964)
Baker v. Pagani Bros.
25 Mass. App. Dec. 117 (Mass. Dist. Ct., App. Div., 1962)
Ted's Master Service, Inc. v. FARINA BROS. CO. INC.
178 N.E.2d 268 (Massachusetts Supreme Judicial Court, 1961)
Piontek v. Joseph Perry, Inc.
173 N.E.2d 292 (Massachusetts Supreme Judicial Court, 1961)
Banaghan v. Dewey
162 N.E.2d 807 (Massachusetts Supreme Judicial Court, 1959)
Woodcock v. Trailways of New England, Inc.
162 N.E.2d 658 (Massachusetts Supreme Judicial Court, 1959)

Cite This Page — Counsel Stack

Bluebook (online)
158 N.E.2d 858, 339 Mass. 273, 1959 Mass. LEXIS 798, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kushner-v-dravo-corp-mass-1959.