Kunze v. Jones

166 N.W. 904, 200 Mich. 453, 1918 Mich. LEXIS 852
CourtMichigan Supreme Court
DecidedMarch 27, 1918
DocketDocket No. 172
StatusPublished

This text of 166 N.W. 904 (Kunze v. Jones) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kunze v. Jones, 166 N.W. 904, 200 Mich. 453, 1918 Mich. LEXIS 852 (Mich. 1918).

Opinion

Stone, J.

Appeal from decree dismissing bill of complaint. The plaintiff filed his bill of complaint to foreclose a mechanic’s lien which he had filed against the lands and building of defendants. By the contract, which was made in writing on October 3, 1913, between plaintiff, as contractor, and F. P. Jones and Mary E. Jones, his wife, as owners, plaintiff was to do, to the satisfaction, of the defendants’ architect, acting as the agent of the defendants, all the labor and furnish the material for the concrete work, brick work, iron work, and furnish the material and construct tile drains and inside sewers, and perform the labor of setting all the stone, work for a certain build- • ing then and there about to be erected by the said F. P. Jones and Mary E. Jones on certain described land in the village of Highland Park, in consideration of the sum of $1,425 to be paid by the said defendants, who were the owners of said premises as tenants by the entireties. F. P. Jones died pending the case, and the title to the property has vested in Mary E. Jones as survivor.

By the terms of the contract, the plaintiff, as such [455]*455contractor, was to proceed in a prompt and diligent manner and wholly finish the said work, but the time limit in which the contract was to be'completed was left blank.

The 10th clause of said contract was as follows:

“Should the contractor at. any time refuse or neglect to supply a sufficiency of properly skilled workmen, or of materials of the proper quality, or fail in any respect to prosecute the work with promptness and diligence, or fail in the performance of any of the agreements on his part herein contained, such refusal, neglect or failure being certified by the architect, the owners shall be at liberty, after three days’' written notice to the contractor, to provide any such labor or materials, and to deduct the cost thereof from any money then due or thereafter to become due to the contractor under this contract; and if the architect shall certify that such refusal, neglect or failure is sufficient ground, for such action, the owners shall also be at liberty to terminate the employment of the contractor for the said work and to enter, upon the premises and take possession of all materials thereon, and to employ any other person or persons to finish the work, and to provide the materials therefor; and in case of such discontinuance of the employment of the contractor, he shall not be entitled to receive any further payment under this contract until the said work shall be wholly finished, at which time, if the unpaid balance of the amount to be paid under the contract shall exceed the expense incurred by the owners in finishing the work, such excess shall be paid by the owners to the contractor, but if such expense shall exceed such unpaid balance, the contractor shall pay the difference to the owners. The expense incurred by the owners as herein provided, either for furnishing materials or for finishing the work, and any damage incurred through ■ such default, shall be audited and certified by the architect whose certificate thereof shall be conclusive upon the parties.”

The 13th clause was as follows:

“And it is hereby mutually agreed between the parties hereto that the sum to be paid by the owners to [456]*456the contractor for said work and materials shall be Fourteen Hundred and Twenty-five ($1,425.00) subject to additions or deductions on account of alterations as hereinbefore provided, and that such sum shall be paid in current funds by the owners to the contractor in installments, as work progresses, on certification from the architects, reserving 15 per cent, until the •building is entirely completed. It being understood that the final payment shall be made within 60 days after this contract is completely finished.”

The plaintiff started the work on or about October 6, 1913, and had made such progress that on or about October 16th the architect gave him a certificate for $500, the work having been performed in a manner reasonably satisfactory to the architect up to that date.

This amount was paid to the plaintiff by the owners. Plaintiff started veneering above the foundation, and continued to have work done on the building intermittently until November 22d.

Plaintiff claimed that some of the delays were caused by the carpenters, over whom he had no control; that some delays occurred on account of his workmen not working steadily.

The plaintiff testified that he saw the architect on the job frequently, and that he never complained of the plaintiff’s work being unsatisfactory until plaintiff asked him for a second certificate.

Upon the hearing, there was a sharp conflict in the testimony as to the progress of the work at this time. The plaintiff testified:

“After the first payment of $500 was made to me I veneered the two sides of the building, and practically all the rear, and a good third of the front with pressed brick. I put in porches and studdings for all stone steps.”

It was the further claim of the plaintiff that just prior to November 28th he called at the architect’s [457]*457office several times to get a certificate for more money, but could not find the architect there, so he wrote him a letter requesting a certificate for payment.

Plaintiff finally had a conversation with the architect in which the latter stated to him that the work which he had done was unsatisfactory, and the architect refused to give the certificate requested by the plaintiff; that plaintiff then asked the architect to point out to him what part-of the work was unsatisfactory, and also told the architect that if there were any unsatisfactory things he would be glad to remedy them.

The plaintiff further testified that after going to the architect’s office several times more, and not finding him in, he left at the office the following paper to be signed by the architect:

“Detroit, Mich., Nov. 28,1913.
“A. E. Kunze:
“I hereby agree to accept brick work that is done on 2-family flat building located on Cortland Ave. being built for F. P. Jones to date. Except.”

But as claimed by the plaintiff, the architect never pointed out to him what part of the work was wrong or unsatisfactory and in- fact refused to do so; that at the time of the plaintiff’s request for this second certificate he had become liable for, and had expended for labor and materials the sum of $1,244.39; that plaintiff had actually paid out all of this amount, except $340.39; that he had received $500; so that there was at this time actually due plaintiff $744.38, less the amount which he owed for materials, which was $340.39, or a net amount due plaintiff of $403.99; that the building at this time was substantially completed, the work above described having been done.

The plaintiff further claims that to finish the work at that time the labor would not amount to more than $75; that there were enough of the common brick on [458]*458the ground to complete the building; but that a few more pressed brick would be needed.

At this time plaintiff mailed a letter requesting a payment of $650. The architect replied as follows:

“Detroit, Mich., Mon., Dec. 1st.
“A. E. Kunze,
“Dear Sir:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Schliess v. City of Grand Rapids
90 N.W. 700 (Michigan Supreme Court, 1902)
Gier v. Daiber
111 N.W. 773 (Michigan Supreme Court, 1907)
Halpin v. Garman
158 N.W. 29 (Michigan Supreme Court, 1916)

Cite This Page — Counsel Stack

Bluebook (online)
166 N.W. 904, 200 Mich. 453, 1918 Mich. LEXIS 852, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kunze-v-jones-mich-1918.