Kunofsky v. Davie Shoring, Inc.

828 So. 2d 1203, 2002 La.App. 4 Cir. 0882, 2002 La. App. LEXIS 3066, 2002 WL 31256446
CourtLouisiana Court of Appeal
DecidedSeptember 25, 2002
DocketNo. 2002-CA-0882
StatusPublished

This text of 828 So. 2d 1203 (Kunofsky v. Davie Shoring, Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kunofsky v. Davie Shoring, Inc., 828 So. 2d 1203, 2002 La.App. 4 Cir. 0882, 2002 La. App. LEXIS 3066, 2002 WL 31256446 (La. Ct. App. 2002).

Opinion

I Judge MICHAEL E. KIRBY.

In this eoncursus proceeding1 brought in First City Court, defendants Mr. Wilfred Bolds, d/b/a B & W General Contractors (“B & W”), and Davie Shoring, Inc. each claimed entitlement to $2,600.00 placed in the registry of the court for shoring work performed on property owned by Mr. Edward Kunofsky. Following trial, the court awarded $1,950.00 to Davie Shoring, Inc. and $650.00 to B & W. B & W now appeals the First City Court judgment, arguing that the court erred in awarding any amount of the $2,600.00 to Davie Shoring, Inc.

Edward Kunofsky filed a petition in eoncursus, naming as defendants Davie Shoring, Inc. and B & W. In this petition, Kunofsky stated that defendants performed services in connection with renovation of his property under a contract between Kunofsky and B & W. Da-vie Shoring, a subcontractor of B & W, made formal amicable demand upon Ku-nofsky for payment of its invoice in the sum of $2,600.00 for services rendered on Kunofsky’s property. Kunofsky acknowledged in the petition that he remains indebted to B & W for the sum of $2,600.00, but claimed that such sum is not and will not be due and owing to B & W unless and |2until B & W can provide assurance that Kunofsky is not exposed to the claim alleged by Davie Shoring or any other subcontractors that assisted in the renovation. The First City Court issued an order granting Ku-nofsky’s request to deposit the sum of $2,600.00 into the registry of the court.

In its answer to the petition in concur-sus, B & W claimed that Davie Shoring [1205]*1205never completed the work it agreed to do, and was already paid for the work it actually did. B & W further claimed that it completed the work left undone by Davie Shoring and is due the full amount on deposit with the registry of the First City Court.

Following trial, the court found that Da-vie Shoring performed approximately 75% of the work it was contracted to perform, and that B & W completed the remaining 25% of the project. Based on that finding, the court awarded Davie Shoring $1,950.00 and awarded B & W $650.00.

At trial, Edward Kunofsky testified that he hired Mr. Bolds as general contractor to perform renovation work at his house on Burgundy Street. Mr. Bolds then subcontracted with Davie Shoring to level and shore the house. He said a worker sent by Davie Shoring arrived intoxicated every day and at one point, pulled down his pants and exposed his buttocks to Mr. Kunofsky’s neighbor. Mr. Kunofsky complained to Mr. Bolds about the worker’s behavior and told him to replace the worker immediately. He said the work was only partially completed, so Mr. Bolds sent his own workers to finish the job. Mr. Kunofsky stated that the work was ultimately completed to his satisfaction, but not by Davie Shoring.

Kunofsky testified that he only told Mr. Bolds to replace the particular worker whose behavior he found offensive. He did not tell Mr. Bolds to replace |sDavie Shoring. He admitted he would not have objected if Davie Shoring had just replaced that worker with a different worker.

On cross-examination, Mr. Kunofsky said he could not remember if the intoxicated worker was the only worker on the job at his house from Davie Shoring. He said Davie Shoring was on this job for a couple of weeks.

The next witness was Wilfred Bolds. Mr. Bolds testified that he was the contractor on the renovation job at Mr. Ku-nofsky’s house. He hired Davie Shoring as the subcontractor to perform the level and shoring portion of the job. He terminated Davie Shoring as the subcontractor because of the unprofessional conduct of its workers. He said Davie Shoring had two workers on the job, and one of them was usually intoxicated. He said he informed Mr. Warren Davie of Davie Shoring about the intoxicated worker, but Mr. Davie never replaced the worker. Mr. Bolds and two of his employees finished the leveling and shoring work on the house. Mr. Bolds said that when he and his workers took over, less than fifty percent of the leveling and shoring work had been completed.

Mr. Bolds testified that he paid Davie Shoring $1,500.00 for work it had completed. He said Davie Shoring worked on this job for at least five days before being terminated. He said the job should have taken Davie Shoring two to three weeks to complete. He said he and his workers had to redo most of the work that Davie Shoring had done. In the time that Davie Shoring was on the job, it leveled the house off and installed sills on one side of the house. He explained a sill is the bottom beam on a house that sits on piers.

The next witness was Warren Pat Davie of Davie Shoring. He testified that Mr. Bolds hired his company to replace a rotten sill in the right wall of Mr. Kunofsky’s house and to reconstruct seven piers. He said that he and Mr. Bolds ^entered into a verbal contract whereby Mr. Bolds agreed that Davie Shoring would be paid $5,200.00 to complete the job. He said he was paid $1,500.00 when he agreed to perform the job, and was supposed to be paid $2,600.00 when the sills were changed and the build[1206]*1206ing was ready to be raised. He said a large part of the job is preparation for the changing of the sills because the structure needs to be temporarily supported while the sills are being changed out.

He said that the first time Mr. Bolds complained to him about the intoxicated worker was when Mr. Davie called Mr. Bolds to collect the second payment. He said the job he was hired to perform usually takes two workers about two weeks to complete. He said his workers had completed the portion of the job that Mr. Bolds agreed needed to be completed in order for Davie Shoring to be entitled to receive the second payment. Mr. Davie sent Mr. Bolds an invoice for $2,600.00 when all of the sills were changed and the building was ready to be raised. He said this figure represented the amount owed for work that was already completed. He stated that he left the job when he did not receive the second payment from Mr. Bolds. He said that is his normal procedure if he does not get his second payment; he waits until he receives payment before completing a job. Mr. Davie said he did not leave because Mr. Bolds asked him to leave; he left because Mr. Bolds did not pay him. He said the third and final payment was supposed to be $1,100.00 and that would have been due upon completion of the job.

On cross-examination, Mr. Davie stated that part of his verbal agreement with Mr. Bolds was that the work would be performed in a workmanlike manner. He stated that his work was performed in a workmanlike manner.

On rebuttal, Mr. Bolds testified that the work performed by Davie Shoring was not done properly and was redone by Mr. Bolds’ workers. He said the |B$1,500.00 initial payment to Davie Shoring was just to get work started; it was not for a percentage of the job.

The trial court found that although one of the employees of Davie Shoring conducted himself in an unprofessional manner, the evidence showed that Davie Shoring completed approximately 75% of the work it was hired to perform. The court also ruled that B & W was entitled to be compensated for the work performed to complete the project. On appeal, B & W argues that the trial court erred in finding that Davie Shoring performed work under the contract for which it was owed any funds. B & W claims that there was no evidence to support that finding and only evidence to the contrary.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mistich v. Volkswagen of Germany, Inc.
666 So. 2d 1073 (Supreme Court of Louisiana, 1996)
Stobart v. State Through DOTD
617 So. 2d 880 (Supreme Court of Louisiana, 1993)
Watson v. State Farm Fire and Cas. Ins. Co.
469 So. 2d 967 (Supreme Court of Louisiana, 1985)
Arceneaux v. Domingue
365 So. 2d 1330 (Supreme Court of Louisiana, 1978)
Rosell v. Esco
549 So. 2d 840 (Supreme Court of Louisiana, 1989)
Sistler v. Liberty Mut. Ins. Co.
558 So. 2d 1106 (Supreme Court of Louisiana, 1990)
Housley v. Cerise
579 So. 2d 973 (Supreme Court of Louisiana, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
828 So. 2d 1203, 2002 La.App. 4 Cir. 0882, 2002 La. App. LEXIS 3066, 2002 WL 31256446, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kunofsky-v-davie-shoring-inc-lactapp-2002.