Kunc v. Harper-Turner Oil Company

1956 OK 118, 297 P.2d 371
CourtSupreme Court of Oklahoma
DecidedApril 3, 1956
Docket36739
StatusPublished
Cited by18 cases

This text of 1956 OK 118 (Kunc v. Harper-Turner Oil Company) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kunc v. Harper-Turner Oil Company, 1956 OK 118, 297 P.2d 371 (Okla. 1956).

Opinion

HALLEY, Justice.

Parties will be referred to 'as they appeared in the trial- court.

’ Plaintiffs" owned the West Half of Sec^ tion 33, 14N, 2W, in Oklahoma County covered by an. -oil .and. gas, .lease executed -by them February 10, 1941, for a, term of five years on; Producers -88 Form to Black Oak Oil Company, and later assigned, to the,defendant. The lease had .a special , provision that it would become,void unless the.lessee commenced the drilling of a well on either the East Half of Section 32 or the West Half of Section 33, within six mpnth's ‘from the date of the lease to a sufficient depth to test all Pennsylvanián Sand, unless oil or gas in payirig quantities was found at a

lesser depth.

In August, 1941, the lessee^ completed á producing oil and gas well in the center of the NW SW'NW of- Section "33, and’in February, 1943, a second well was drilled in the center of NÉ SW of' Section 33, but was a dry hole and abandoned.

On June 6, 1946, the lessee obtained an order of the Corporation Commission holding that the lease should be divided into well spacing units of 40 acres each, hut this order did not. include the SW}4 of Section 33. No further wells were drilled on this lease and on August’9, 1948, plaintiffs made a written demand that defendant commence the drilling of additional wells within 60 days or a suit to cancel the lease would bé fifed-

November 26, 1948, this action was filed by'-plaintiffs alleging that, defendant had -failed to diligently develop the dease and prayed- that' the .lease be deemed cancelled and forfeited-. Defendant, answered generally . denying the allegations of plaintiffs and alleged that a reasonably prudent operator, under -existing circumstances would not have drilled additional wells and that ^current.'exploration’ in the general area ■would -.give . additional geological information and .offered .to' drill additional wells •whenever conditions justified.

On January-,'5, .1950, ,a hearing was had -and a.demurrer by defendant was overruled, and the. demjurrer was,-renewed on .March *374 8, 1950, and the court found that no judgment should be entered at that time, but that the matter be continued indefinitely to be reset at any time after six months from that date.

No further action appears to have been taken for more than two years, when on July 16, 1952, the plaintiffs filed an application for further hearing and prayed that the matter be set for hearing and for a determination of the issues raised by the pleadings.

November 18, 1952, the plaintiffs sent a notice to the defendant stating that defendant had forfeited their lease and demanded that it release the lease of record and that any physical encroachment or entry upon the undeveloped portion of the land covered by the lease would be considered a trespass.

Plaintiffs filed a supplemental petition alleging that on November 17, 1952, defendant had illegally entered upon plaintiffs’ land and started preparation for the commencement of drilling, but that such entry was a trespass. They prayed that the lease be decreed abandoned and terminated, forfeited and cancelled by operation of law; that the defendant was estopped, that it was a trespasser and that it be enjoined from continuing to trespass upon plaintiffs’ land. They also prayed that defendant be enjoined and restrained from entering upon or occupying the undeveloped portion of the lease. Damages were asked for failure to develop diligently the leasehold estate. On demurrer the court held such damages not recoverable in addition to the other relief sought. Defendant pleaded the 10th paragraph of the lease providing that if lessee should be judicially determined obligated to drill a well or wells, they should have 90 days in which to commence such well or wells. Defendant also pleaded the Corporation Commission’s order creating a Bartles-ville Sand Unit containing the West Half of the NWJ4 of Section 33 and attached a copy of such order to its answer.

Plaintiffs replied that the unitization of part of the lease here involved was not to-their benefit but caused them loss of royalty and revenue and asserted that defendant cannot rely upon the express terms of the lease because the lease had expired and had been abandoned by the defendant.

March 2, 1954, a hearing was had and the case taken under advisement until April 28, 1954, on which date the court made findings of fact and conclusions of law in substance as follows:

That lessee drilled the first well at a cost of $22,133.43 in 1941, to the Bartlesville Sand horizon to a depth of about 5,817 feet which has continued to produce; that in October, 1950, the Corporation Commission entered an order creating the East Edmond South Field Bartlesville Sand Unit, including the West Half of the NW}4 of Section 33, but not the remainder of the West Half of Section 33; that the owners of the minerals have participated in the oil and gas production from such sand unit and have been receiving royalty therefrom since 1941.

That no delay rentals have been paid by defendant since completing the first producing well and that in March, 1943, defendant drilled a well on the NE14 of SW}4 of Section 33 to a depth of 6020 feet but it was plugged as a dry hole.', .

During 1952 and 1953, the defendant continued to explore for oil and gas in the area West and South of the lease in question and in November, 1952, drilled a well three-quarters of a mile South of plaintiffs’ lease and found the tight Bartlesville Sand productive of gas but not deemed commercial but were thereby led to believe that such sand might be , productive South of the first well drilled on plaintiffs’ lease and began operations there to commence a well in November, 1952.

That plaintiffs learned that such well was about to be drilled and notified defendant that they considered their lease abandoned and expired except as to the West Half of the NW}4. This new well was spudded in November 21, 1952, arid completed as a producer in the Bartlesville Sand December 24, 1952. The cost of this well was $38,-.138.48, and produced about 30 barrels of oil per day.

Two or possibly three locations in the West Half of Section 33 may be productive, one directly South and one a diagonal offset in the NE of the SE14 of Section 33.

*375 The Corporation Commission in June, 1946, at the instance of defendant established a 40 acre drilling- and spacing unit North and West of plaintiffs’ land as a Bartlesville common source of supply, fixed generally as North of the East West center line of Section 33.

The court found that no productive well had been drilled as a direct offset to plaintiffs’ land except the J. Kune No. 1 in the center of SE}4 of the NE}4 of Section 32 which was completed after the first well on plaintiffs’ land.

He found that there had been no drainage from plaintiffs’ land by wells on adjacent tracts; and that no physical abandonment of any portion of their leasehold had occurred and that defendant never intended to abandon any portion of the lease here involved.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

HALL v. GALMOR
2018 OK 59 (Supreme Court of Oklahoma, 2018)
Rook v. James E. Russell Petroleum, Inc.
658 P.2d 1059 (Court of Appeals of Kansas, 1983)
The Superior Oil Company v. Devon Corporation
604 F.2d 1063 (Eighth Circuit, 1979)
Superior Oil Co. v. Devon Corp.
604 F.2d 1063 (Eighth Circuit, 1979)
Somers v. Harris Trust & Savings Bank
566 P.2d 775 (Court of Appeals of Kansas, 1977)
Crocker v. Humble Oil & Refining Company
419 P.2d 265 (Supreme Court of Oklahoma, 1966)
Oklahoma Natural Gas Company v. Long
1965 OK 153 (Supreme Court of Oklahoma, 1965)
Rist v. Westhoma Oil Company
1963 OK 126 (Supreme Court of Oklahoma, 1963)
Montana Eastern Pipe Line Co. v. Shell Oil Co.
216 F. Supp. 214 (D. Montana, 1963)
Lyons v. Robson
1958 OK 232 (Supreme Court of Oklahoma, 1958)
Brown v. Shafer
325 P.2d 743 (Supreme Court of Oklahoma, 1958)
Panhandle Eastern Pipe Line Co. v. Isaacson
255 F.2d 669 (Tenth Circuit, 1958)

Cite This Page — Counsel Stack

Bluebook (online)
1956 OK 118, 297 P.2d 371, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kunc-v-harper-turner-oil-company-okla-1956.