Kuhn Construction Co. v. Ocean & Coastal Consultants, Inc.

723 F. Supp. 2d 676, 2010 U.S. Dist. LEXIS 71057, 2010 WL 2787456
CourtDistrict Court, D. Delaware
DecidedJuly 15, 2010
DocketCiv. 09-622-SLR
StatusPublished
Cited by15 cases

This text of 723 F. Supp. 2d 676 (Kuhn Construction Co. v. Ocean & Coastal Consultants, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Delaware primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kuhn Construction Co. v. Ocean & Coastal Consultants, Inc., 723 F. Supp. 2d 676, 2010 U.S. Dist. LEXIS 71057, 2010 WL 2787456 (D. Del. 2010).

Opinion

MEMORANDUM OPINION

SUE L. ROBINSON, District Judge.

I. INTRODUCTION

In November 2009, plaintiff Kuhn Construction Company (“plaintiff’), a Delaware business entity, brought this action against Ocean and Coastal Consultants, Inc. (“OCC”), a Connecticut corporation, and Robert F. Waite (‘Waite”), a New York entity (collectively, “defendants”). Plaintiff brought negligence and negligent misrepresentation claims against Waite and OCC, and fraud and misrepresentation, interference with existing contracts, and common law conspiracy claims against OCC. (D.I. 1 at ¶¶ 107, 115, 122-23, 127, 131) In December 2008, plaintiff brought a separate action against Diamond State Port Corporation (“DSPC”), a Delaware corporation, and its executive director, Eugene Bailey, in the Court of Chancery of the State of Delaware. (D.I. 6, ex. A) In the state action, plaintiff sought an injunction on DSPC’s attempts to force it into arbitration. (D.I. 6, ex. A at ¶ 66) The Supreme Court of Delaware, in an opinion dated March 8, 2010, reversed a grant of DSPC’s motion to compel arbitration and dismiss the complaint. Kuhn Const, Inc. v. Diamond State Port Corp., 990 A.2d 393, 398 (2010). Plaintiff has taken no further action in that ease.

On October 5, 2009, OCC moved to dismiss this case pursuant to Federal Rules of Civil Procedure 12(b)(7) and 12(b)(1), claiming that plaintiff failed to join a required party (DSPC), and that such joinder would destroy the court’s subject matter jurisdiction over this case. 1 (D.I. 6) On *681 October 20, 2009, Waite joined OCC’s motion to dismiss. (D.I. 9)

The court has jurisdiction over this case pursuant to 28 U.S.C. § 1332. For the reasons that follow, this court denies defendants’ motions to dismiss without prejudice to renew.

II. BACKGROUND

Prior to February 2007, DSPC engaged OCC to analyze the rehabilitation and reconstruction of Wharf Unit 2, Berth 4 at the Port of Wilmington in Delaware and prepare engineered drawings, plans, and specifications accordingly (“the Project”). (D.I. 1 at ¶¶ 6-7; D.I. 1, ex. A at 2; D.I. 6, ex. A at ¶ 2) Plaintiff asserts that OCC knew and intended that DSPC would supply the datum, survey, and elevation data within the documents to bidders and that bidders would rely on this data for bid-calculation purposes. (D.I. 1 at ¶ 106) In soliciting bids, DSPC utilized plans and specifications designed and prepared by OCC (“the Bid Documents”), including a set of plans and specifications dated February 2, 2007, labeled “For Bid Purposes Only” (“the Bid Drawings”), upon which plaintiff relied to prepare its bid. (Id. at ¶¶ 8,13,16)

As the lowest bidder, plaintiff entered into a contract with DSPC for the Project on approximately March 29, 2009 for the agreed-upon price of $10,750,000 (hereinafter, “the Contract”). (Id. at ¶ 10) Despite not being listed as the architect in the Bid Documents and not holding a license to practice architecture, the Contract listed OCC as the architect (a term which, according to plaintiff, refers to entities licensed to practice architecture). (Id. at ¶11)

Plaintiff references three activities which it claims resulted in the current dispute: (1) changes to the Bid Documents after the contract award; (2) undisclosed subsurface conditions and obstructions; and (3) welding issues. (Id. at ¶¶ 12, 57-58, 77-104)

A. Changes to the Bid Documents After Contract Award

In preparing its bid, plaintiff relied on note 4 of the Bid Documents, stating in part:

Do not use more than one splice per pile. Splice of taper section to pipe section shall not count as a splice as defined here. Do not splice pile in lower 40 feet. Both upper and lower sections of pipe piles ends shall be smooth, square and flat prior to splicing. Splice with associated pile and fitting corp. Advanced splicer S-18000 or equivalent accepted by the engineer of record.

(Id. at ¶ 14) In creating its bid, plaintiff relied on information in the Bid Documents stating that only the connection between the lowermost section of the steel pipe pile section and the adjoining section of steel pipe pile required welding, and all other splicing would be done using the S-18000 or equivalent and would require no welding. (Id. at ¶¶ 15-16)

Following the award of the contract to plaintiff, OCC, through DSPC, changed the contract requirements through alterations in the drawings. 2 (Id. at ¶ 12) On approximately May 24, 2007, plaintiff received from OCC a new set of drawings, dated May 23, 2007 and labeled “Issued for Construction,” which did not identify the changes from the Bid Drawings (hereinafter, the “IFC Drawings”). (Id. at ¶¶ 17- *682 18) Shortly after receipt of the IFC Drawings, on approximately May 29, 2007, plaintiff issued a Request for Information (“RFP) to DSPC to have OCC mark changes between the two sets of drawings. (Id. at ¶ 19) OCC replied on or about June 6, 2007 that most of the changes within the [IFC] Drawings “address the elevations field verified by [plaintiffs] surveyor and the shifting of the deadman wall 10 [feet] waterward due to interferences.” (Id. at ¶ 20 (alterations in original)) This reply included a new set of drawings (“the Highlighter Drawings”) highlighting changes between the Bid Drawings and the IFC Drawings. (Id. at ¶ 21) Plaintiff alleges that OCC did not note all changes on these drawings and, instead, purposefully obscured material changes and revisions it had made between the Bid Drawings and the IFC Drawings. (Id. at ¶ 22)

At a later meeting, OCC informed plaintiff that splices in the upper section of the steel pipe piles were considered “tension splices” requiring welding, referencing note 4 on the IFC drawings for this requirement. (Id. at ¶ 23) This note is substantially similar to note 4 on the Bid Documents, except that it states “[advanced splicer S-18000 welded-in place or equivalent accepted by the engineer of record.” (Id. at ¶ 24) (emphasis in original) OCC made no note in the Highlighter Drawings of this change. (Id. at ¶ 26) Plaintiff alleges that OCC knowingly and intentionally misrepresented that this change was in the Bid Documents when it had not been added until the IFC Documents and that OCC intentionally and purposefully failed to note the change in the Highlighter Drawings and in its response to plaintiffs RFI. (Id. at ¶¶ 25-26)

On July 7, 2007, OCC issued another set of construction documents with “clouds” and “call outs” marking changes made, including the change in wording of note 4 (“the July 7 Drawings”). (Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
723 F. Supp. 2d 676, 2010 U.S. Dist. LEXIS 71057, 2010 WL 2787456, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kuhn-construction-co-v-ocean-coastal-consultants-inc-ded-2010.