Kuch & Watson, Inc. v. Woodman

331 N.E.2d 350, 29 Ill. App. 3d 638, 1975 Ill. App. LEXIS 2491
CourtAppellate Court of Illinois
DecidedJune 26, 1975
Docket72-351
StatusPublished
Cited by14 cases

This text of 331 N.E.2d 350 (Kuch & Watson, Inc. v. Woodman) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kuch & Watson, Inc. v. Woodman, 331 N.E.2d 350, 29 Ill. App. 3d 638, 1975 Ill. App. LEXIS 2491 (Ill. Ct. App. 1975).

Opinion

Mr. JUSTICE GUILD

delivered the opinion of the court:

Plaintiff appeals from the dismissal of its amended complaint against defendants Lorrin E. Woodman, doing business as Baxter & Woodman (hereinafter Woodman) and the Village of Gurnee (hereinafter the Village) for failure to state a cause of action.

Plaintiff’s amended complaint is in four counts; the first two counts are directed against defendant Woodman and Counts III and IV are directed against defendant Village. In substance, the amended complaint alleges that in 1961 the Village and Woodman entered into a contract whereby Woodman would plan a sewerage system for the Village. In 1966 the prior agreement was supplemented by Woodman, agreeing to furnish certain supervision over the construction of the sewer system. This contract provided that:

“The Engineers’ Super-vision is for the purpose of assuring the owner [the Village] that the plans and specifications are being properly executed * * *”
and
“The owner [the Village] will furnish engineering and inspection service to insure the work being carried out in accordance with the contract * *

In 1965 the Village entered into a contract with the Preston Woodall Company (hereinafter Woodall) whereby Woodall would act as the contractor for the installation of the sewerage system, with Maryland Casualty Co. (hereinafter Maryland) as surety.

The complaint further alleges that Woodall then “purported to satisfactorily install” approximately 60% of the sewerage system with the defendant Woodman and the defendant Village “supervising each stage of construction, and approving the same.” In 1967 Woodall was unable to complete the contract and was declared in default by the Village. Maryland, under its bond, then became liable for the completion of the project and in response to an invitation to bid to complete the contract the plaintiff submitted a $612,000 bid which was accepted by Maryland.

The complaint further alleges that in submitting its bid, plaintiff relied upon the contract between the defendants, specifically relying upon the supervision and approval of the work previously performed by Woodall. Plaintiff also alleges that it relied upon “assurances” of the defendant Woodman that die portion previously completed had been completed in a satisfactory manner. Plaintiff further contends that the defendant Woodman is charged with knowledge that the undertaking of work by the plaintiff would require that plaintiff assume complete responsibility for completing the entire sewerage system and that any failure on Woodman’s part to have properly supervised the previous work would cause plaintiff financial damage.

Plaintiff then alleges that Woodman failed to perform its duties under its contract with the Village by approving certain detailed substandard work, thereby requiring plaintiff to expend sums to satisfactorily complete the project. In Count I of the complaint plaintiff prays for an award of $210,000 in damages against the defendant Woodman and in Count II plaintiff prays for an award of $100,000 against the defendant Woodman as recovery of lost profits.

Count III, which as noted above is directed against the defendant Village, in addition to realleging much of Count I, also alleges that plaintiff s contract with Maryland incorporated the contract which the Village had entered into with Woodall and that the duties of the Village under the Village-Woodall contract accrued to plaintiff. Plaintiff then alleges that the Village breached its duties under that contract in several detailed respects. Plaintiff then prays for an award of $210,000 damages against the defendant Village and in Count II prays for an award of $100,000 against the defendant Village as a recovery of lost profits.

Plaintiff also filed three contracts, which it entered into with Maryland, which covered various portions of the work to be performed by plaintiff. Each of the contracts contained the following language:

“Whereas, the Contractor has examined the site of the work and has also inspected that portion of the work under said Contract heretofore performed by Woodall * * * and has offered to assume complete responsibility thereunder * * * including, without limiting, responsibility and liability of all maintenance, guarantee, and corrections or replacement of any defective work heretofore performed under said Contract and to assume such responsibility and complete performance of said Contract *

The contracts also each provided that the specified consideration for each contract was to be:

“* * * full compensation * * for all costs and expenses incurred and for any loss or damage sustained by reason of the action of the elements, or growing out of the nature of the work, or for any and all unforeseen difficulties or obstructions encountered, and for risks of every description * *

On July 21, 1972, the trial court filed its memorandum decision dismissing the complaint against both defendants. In substance, the trial court found that neither defendant could be said to have owed a legal duty to the plaintiff. The trial court further found that amended complaint against the Village sounded in tort and as such was barred by the statute of limitations. Ill. Rev. Stat. 1971, ch. 85, par. 8—101.

The question presented is whether the amended complaint states a cause of action against either defendant. In determining the legal sufficiency of a complaint on a motion to dismiss, all well-pleaded facts are to be taken as time for purposes of the motion, but mere conclusions of the pleader may be disregarded. (See Chicago Teachers Union v. Board of Education (1973), 14 Ill.App.3d 154, 301 N.E.2d 833.) In his memorandum opinion, the trial judge noted that plaintiffs’ reference in its amended complaint to “assurances” that the prior work had been satisfactorily completed, which assurances were allegedly made to plaintiff by the defendant Woodman, were mere conclusions of the pleader and were, theretofore, to be ignored in ruling on the motion to dismiss. This was correct. Section 31 of the Civil Practice Act (Ill. Rev. Stat. 1971, ch. 110, par. 31) requires that in stating a cause of action, substantial averments of fact must be alleged. Merely alleging that “assurances” were made without alleging, for example, when they were made, by whom and to whom they were made, whether they were oral or written or the substance of the alleged assurances, renders the allegation merely conclusory and not well pled and thus may be disregarded in ruling on a motion to dismiss.

A further difficulty is presented in determining what portions of the amended complaint have been well pled. This difficulty is based upon the obvious conflict between the provisions of the contract between plaintiff and Maryland on the one hand, and certain allegations of the complaint on the other.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Maurice L. Quinn v. The McGraw Companies, Inc.
168 F.3d 331 (Seventh Circuit, 1999)
Katz v. Belmont National Bank
491 N.E.2d 1157 (Illinois Supreme Court, 1986)
Bank of Lincolnwood v. Comdisco, Inc.
444 N.E.2d 657 (Appellate Court of Illinois, 1982)
Pinsof v. Pinsof
438 N.E.2d 525 (Appellate Court of Illinois, 1982)
Illinois Housing Development Authority v. Sjostrom & Sons, Inc.
433 N.E.2d 1350 (Appellate Court of Illinois, 1982)
Konicki v. Village of Hinsdale
427 N.E.2d 325 (Appellate Court of Illinois, 1981)
W. H. Lyman Construction Co. v. Village of Gurnee
403 N.E.2d 1325 (Appellate Court of Illinois, 1980)
Cipolla v. Bloom Township High School District No. 206
388 N.E.2d 31 (Appellate Court of Illinois, 1979)
McCauley v. Chicago Board of Education
384 N.E.2d 100 (Appellate Court of Illinois, 1978)
Ford v. University of Illinois Board of Trustees
371 N.E.2d 173 (Appellate Court of Illinois, 1977)
Brooks v. Midas-International Corp.
361 N.E.2d 815 (Appellate Court of Illinois, 1977)
Pollack v. Marathon Oil Co.
341 N.E.2d 101 (Appellate Court of Illinois, 1976)
Cook v. Askew
341 N.E.2d 13 (Appellate Court of Illinois, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
331 N.E.2d 350, 29 Ill. App. 3d 638, 1975 Ill. App. LEXIS 2491, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kuch-watson-inc-v-woodman-illappct-1975.