Krusi v. S.J. Amoroso Construction Co.

97 Cal. Rptr. 2d 294, 81 Cal. App. 4th 995
CourtCalifornia Court of Appeal
DecidedJuly 18, 2000
DocketA086602
StatusPublished
Cited by20 cases

This text of 97 Cal. Rptr. 2d 294 (Krusi v. S.J. Amoroso Construction Co.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Krusi v. S.J. Amoroso Construction Co., 97 Cal. Rptr. 2d 294, 81 Cal. App. 4th 995 (Cal. Ct. App. 2000).

Opinion

Opinion

HAERLE, Acting P. J.

I. Introduction

In 1995, two testamentary trusts (hereinafter appellants), purchased a two-story commercial building. The following year, they filed suit against respondents, the architects and contractors who designed and constructed the building in 1985-1987, alleging improper design and/or construction. The trial court granted respondents summary judgment on the basis that appellants, the fourth owners of the building, lacked standing to sue. We affirm.

*997 n. Factual and Procedural Background

The building at issue in this case is located at 3351 El Camino Real in Atherton, San Mateo County. Construction on it started in September 1985 and a notice of completion was filed in March 1987. Respondents, defendants below, are the building’s architects and general contractor and some of the latter’s subcontractors.

The owner of the building when it was completed was a corporation named Atherton Square II Associates, Inc. That entity was, apparently, the successor in interest to a partnership known as Atherton Square Partnership, which was the entity that originally contracted with the architects for the design of the building. 1 In September 1990, another partnership, 3351 El Camino Associates, acquired the building. That group sold it to appellants in February 1995, and appellants thus became its fourth (counting the first partnership) owners.

During the course of the original construction, a dispute arose between the first owner of the property, Atherton Square Partnership, and the architect, one of the respondents here. The dispute, which went to arbitration, ultimately included a claim by the owner that the architect’s work was defective. More specifically, the owner claimed that there were leaks in the garage headwall. Prior to the completion of the arbitration, one of the architect’s officers inspected the building and found evidence of such leaks. In a deposition taken in the course of the arbitration, that officer testified he was uncertain as to whether there had been any specific efforts undertaken by the general contractor, S. J. Amoroso Construction Co., Inc. (Amoroso), to remedy the water infiltration problem. The arbitration was heard by an American Arbitration Association arbitrator who, on April 30, 1988, ruled in favor of the architect on the owner’s defective work claims.

Prior to the sale to appellants in 1995, their seller became aware of several leaks, which occurred during the rainy season, from the building’s decks into various tenant offices. At least one of these leaks was characterized by the building manager as “persistent.” The same manager testified that another tenant reported “numerous [leaks] over a period of years.” These leaks were “to the best of [seller’s] knowledge . . . repaired prior to the sale” to appellants. Indeed, the seller reported to its limited partners that the sale price would probably have to be reduced, albeit by only a small amount (probably around $15,000), because of the costs to repair those leaks.

*998 The seller to appellants also found a “failure of the gypcrete underlayment on the second floor (i.e. crumbling) apparently due to the weight of a movable surgical table,” but averred that it, too, was repaired.

Appellants represented to the trial court that, aside from the leaks that they believed to be repaired, they were unaware of any problems in the design and construction of the building. However, after their purchase of the building, the same building manager alleged that “the frequency and magnitude of the reported leaks at the subject building . . . increased.” Thus, appellants contended that since their acquisition of the building, it “has sustained damages such as new leaks in the decks and deteriorating interior underlayment on the second floor.”

All of this led appellants to hire consultants. These consultants advised appellants, at least according to the latter, that the persistent leaks and “deteriorating underlayment” were the result of “building wide deficiencies in the original design and construction of the subject building.” One of these consultants, a contractor, stated that the “nature and cause for the defects and resultant damages . . . were not and are not exposed, open or evident without an invasive inspection” and would not be apparent to a layperson. The same contractor stated that much of the building’s structure and components had been damaged “as a result of water infiltration.” He went on to note that the inadequate construction and installation of a “waterproofing membrane,” was “the cause for leaks at the subterranean garage walls.”

Another of the consultants, an engineer, stated that damage had been sustained to a variety of flooring materials in the building “as a result of deteriorating gypsum flooring on the second story of the subject building.”

In April 1996, appellants sued respondents for damages to the building, alleging causes of action for negligence, breach of implied warranty, and declaratory relief. After extensive discovery, in August 1998 respondent Amoroso moved for summary judgment. After briefing and argument, the trial court granted its motion on the basis that (1) there was no evidence of property damage as a result of the alleged defects, and (2) as a subsequent purchaser, appellants lacked standing to sue for the defects. It also ruled against appellants on their breach of implied warranty cause of action. 2

Appellants filed a motion for reconsideration arguing, inter alia, that (1) a case the trial court may have relied upon in connection with the first part of *999 its ruling had been accepted for review by our Supreme Court and (2) there were additional facts negating the applicability of the principal authority the court relied upon regarding the standing issue. Additionally, other respondents filed “piggyback” motions for summary judgment. After additional briefing requested by the court, on January 14, 1999, it denied the motion for reconsideration and granted the additional motions for summary judgment filed by the other respondents. Judgments in favor of the respondents were entered at various dates in February and March 1999.

Appellants filed a timely notice of appeal.

III. Discussion

The controlling issue on this appeal is clearly that labeled “standing” by the trial court. 3 However, and as we shall develop more below, it is probably more properly phrased as when a cause of action for design or construction defects accrues and who then owns it—or, as applied here, who doesn’t own it. In considering this seldom-litigated issue, we must necessarily decide which is the most applicable precedent, our own decision in Huang v. Gamer (1984) 157 Cal.App.3d 404 [203 Cal.Rptr. 800] (Huang) or the recent decision of Division Four of the Second District in Keru Investments, Inc. v. Cube Co. (1998) 63 Cal.App.4th 1412 [74 Cal.Rptr.2d 744] (Keru).

Huang

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Yavor v. City One Locksmith
C.D. California, 2020
Jones v. Awad
California Court of Appeal, 2019
The Estuary Owners Assn. v. Shell Oil Co.
California Court of Appeal, 2017
LTL Commercial v. Hammer IRP LTL Assoc. CA2/2
California Court of Appeal, 2016
Kizor v. Blackwood Assocs. CA1/3
California Court of Appeal, 2016
Fluor Corporation v. Super. Ct.
354 P.3d 302 (California Supreme Court, 2015)
Micah Investment Trust v. Atkinson CA1/2
California Court of Appeal, 2015
Stofer v. Shapell Industries, Inc.
233 Cal. App. 4th 176 (California Court of Appeal, 2015)
Keilholtz v. Lennox Hearth Products Inc.
268 F.R.D. 330 (N.D. California, 2010)
Jasmine Networks, Inc. v. Superior Court
180 Cal. App. 4th 980 (California Court of Appeal, 2009)
Standard Fire Ins. v. Spectrum Community Ass'n
46 Cal. Rptr. 3d 804 (California Court of Appeal, 2006)
Standard Fire Insurance v. Spectrum Community Ass'n
141 Cal. App. 4th 1117 (California Court of Appeal, 2006)
Reed v. Cloninger
2006 WY 37 (Wyoming Supreme Court, 2006)
Schauer v. Mandarin Gems of California, Inc.
23 Cal. Rptr. 3d 233 (California Court of Appeal, 2005)
Siegel v. Anderson Homes, Inc.
13 Cal. Rptr. 3d 462 (California Court of Appeal, 2004)
Henkel Corp. v. Hartford Accident & Indemnity Co.
62 P.3d 69 (California Supreme Court, 2003)
Aas v. Superior Court
12 P.3d 1125 (California Supreme Court, 2000)
Aas v. Superior Court of San Diego Cty.
24 Cal. 627 (California Supreme Court, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
97 Cal. Rptr. 2d 294, 81 Cal. App. 4th 995, Counsel Stack Legal Research, https://law.counselstack.com/opinion/krusi-v-sj-amoroso-construction-co-calctapp-2000.