Krizan Associates v. Pereira CA4/1

CourtCalifornia Court of Appeal
DecidedAugust 26, 2022
DocketD079496
StatusUnpublished

This text of Krizan Associates v. Pereira CA4/1 (Krizan Associates v. Pereira CA4/1) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Krizan Associates v. Pereira CA4/1, (Cal. Ct. App. 2022).

Opinion

Filed 8/26/22 Krizan Associates v. Pereira CA4/1

NOT TO BE PUBLISHED IN OFFICIAL REPORTS California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication or ordered published for purposes of rule 8.1115.

COURT OF APPEAL, FOURTH APPELLATE DISTRICT

DIVISION ONE

STATE OF CALIFORNIA

KRIZAN ASSOCIATES, INC., D079496

Plaintiff and Respondent, (Super. Ct. No. v. 37-2019-00017335-CU-BC-CTL)

JOSEPH PEREIRA,

Defendant and Appellant.

APPEAL from a judgment of the Superior Court of San Diego County, Richard S. Whitney, Judge. Affirmed. Jerome R. Moe for Plaintiff and Respondent. Navigato & Battin, Michael W. Battin and Sandip S. Randhawa for Defendant and Appellant. Appellant Joseph Pereira contracted with respondent Krizan Associates, Inc. (Krizan), for it to provide landscape services at his home. Krizan sued Pereira for breach of contract. Following a bench trial, the court found for Krizan, and ordered Pereira to pay damages. Pereira contends the trial court prejudicially erred, as it failed to issue a tentative decision or give the parties an opportunity to request a statement of decision before issuing its final statement of decision, violating Code of Civil Procedure 1 section 632 and California Rules of Court, rule 3.1590. He contends that absent that error, the court would have found for him by recalculating the damage award, and by recognizing that Krizan failed to issue a change order for “out of scope” work it performed in breach of the parties’ contract. We affirm. FACTUAL AND PROCEDURAL BACKGROUND Pereira and Krizan entered into an agreement about landscape

architectural design and related services.2 During a bench trial on their ensuing breach of contract dispute, Pereira argued that Krizan breached the agreement in several ways: “The agreement required that Krizan provide all of the services in ‘task one’ and ‘task two’ within 12 weeks (or around the end of October, 2018). Krizan breached the agreement by failing to provide the services at all but, even as to the incomplete services, they were not provided until late February of the next year. [¶] Krizan agreed that the fees on all of the tasks were ‘not to exceed $9,500.00.’ Yet in breach of the agreement, Krizan charged $14,757.50 in fees—without even attempting to start [‘]task three.[’] [¶] Krizan agreed to provide an invoice monthly, if reasonably possible, by the first of the month. Krizan breached the agreement by failing to provide an invoice for over [six] months. This breach is particularly material because, had Krizan complied and invoiced monthly, the overcharging issue could have been dealt with before the relationship had broken down. Krizan then breached the agreement by demanding payment

1 Undesignated statutory references are to the Code of Civil Procedure.

2 The parties’ agreement listed three tasks that Krizan would complete: task one was “conceptual landscape master plan”; task two was “landscape design development and cost calculations”; and task three was “construction administration/design build process.” (Capitalization omitted.) 2 to which it was not entitled and by withholding performance unless Pereira paid the king’s ransom.” (Some capitalization omitted.) Following trial, the court requested the parties submit closing briefs in lieu of oral argument. Pereira argued in his closing brief that Krizan had breached the agreement in certain ways: “In multiple places, the [a]greement required Krizan to submit monthly invoices (with a corollary requirement that Pereira pay those invoices within 30 days). . . . Yet, it is undisputed that Krizan failed to provide monthly invoices. Had Krizan provided monthly invoices, the issue of what was ‘in scope’ would have surfaced in September when the amounts were small, not February, and this whole dispute would likely have been resolved without litigation.” Pereira further argued: “Krizan claims that there was substantial work done in excess of the scope reflected in the agreement—and, hence, in excess of the ‘not to exceed amount’—and that it should get paid for that extra work. Yet, as the evidence showed, the scope as reflected in the agreement (the wording of which was prepared by Krizan) easily encompassed all of the work Krizan claims it did.” (Some capitalization omitted.) In its closing brief, Krizan explained the basis of the “additional service” fees it charged Pereira: “Mr. Krizan, principal of plaintiff, testified that the additional service fees resulted from: 1) [Krizan’s] need to create ‘base sheets’ since [Pereira] failed to provide current layout maps of the property as required in the first of the assumptions set forth in the agreement; 2) [Krizan’s] interaction with the structural engineer and incorporation of his calculations into [Krizan’s] plans; and 3) [Krizan’s] interaction with the city, in obtaining permits. The three categories of additional services were clearly designated as additional services in the agreement, and the additional service fees totaled $5,437.50 (before the 20

3 [percent] discount of $2,951.50, which Mr. Krizan testified was entirely applicable to the additional service fees, thereby reducing the demand for additional service fees to $2,486).” (Some capitalization omitted.) Krizan further argued that Pereira could have timely challenged the additional fees based on Pereira’s expertise: “Mr. Pereira testified to his having been a general contractor of at least 14 years’ experience at the time of the agreement, including having owned his own construction company since 2008, preceded by several years’ working with his father, also a general contractor. He further testified as to having seen a multitude of construction contracts prior to reviewing [Krizan’s]. It is fair to assume that, as such, Pereira knew what a change order was; was aware that none were required by the agreement; he was able to read and understand what was and was not required by the agreement; and was capable of stating any objections, or requested additions, that he thought were appropriate in response to the agreement proposed by [Krizan].” (Some capitalization omitted.) The court in a February 22, 2021, “Statement of Decision” explained the parties’ claims and the state of the record: “The overview and allegations is that [Pereira] did not pay [Krizan] in a timely manner for services and terminated/breached the contract due to poor performance by [Krizan] and failing to meet deadlines and specifications required. Both sides claim the other materially breached the contract through various acts described in the admitted evidence. The court notes the evidence was confusing and somewhat jumbled on both sides with very little clear direction for the court to follow. The court relied upon the most credible and verifiable evidence introduced to determine whether a breach of contract occurred by one or more party and whether damages, if any, were appropriate.” (Some capitalization omitted.)

4 The court set forth the basis for its conclusion Pereira breached the contract: “It is clear . . . that both parties failed to adhere to the strict interpretation of the contract. There were informal modifications made to the contract that were not properly documented as amendments to the contract. The court does recognize that building plans change and slight modifications are foreseeable as well as laxed adherence to the strict terms of the contract like failing to provide monthly statements/billing by [Krizan]. . . . [¶] . . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Marriage of Hoffmeister
191 Cal. App. 3d 351 (California Court of Appeal, 1987)
Whittington v. McKinney
234 Cal. App. 3d 123 (California Court of Appeal, 1991)
Bay World Trading, Ltd. v. Nebraska Beef, Inc.
123 Cal. Rptr. 2d 632 (California Court of Appeal, 2002)
Paterno v. State
6 Cal. Rptr. 3d 854 (California Court of Appeal, 2003)
Thompson v. Asimos
6 Cal. App. 5th 970 (California Court of Appeal, 2016)
F.People v. Monier
405 P.3d 1076 (California Supreme Court, 2017)
Metis Development LLC v. Bohacek
200 Cal. App. 4th 679 (California Court of Appeal, 2011)
Ribakoff v. City of Long Beach
238 Cal. Rptr. 3d 81 (California Court of Appeals, 5th District, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
Krizan Associates v. Pereira CA4/1, Counsel Stack Legal Research, https://law.counselstack.com/opinion/krizan-associates-v-pereira-ca41-calctapp-2022.