Kreipl v. Philosophical Research Society, Inc.

212 Cal. App. 2d 588, 28 Cal. Rptr. 323, 1963 Cal. App. LEXIS 2885
CourtCalifornia Court of Appeal
DecidedFebruary 4, 1963
DocketCiv. No. 26393
StatusPublished
Cited by2 cases

This text of 212 Cal. App. 2d 588 (Kreipl v. Philosophical Research Society, Inc.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kreipl v. Philosophical Research Society, Inc., 212 Cal. App. 2d 588, 28 Cal. Rptr. 323, 1963 Cal. App. LEXIS 2885 (Cal. Ct. App. 1963).

Opinion

WOOD, P. J.

Action for damages for breach of contract. In a nonjury trial, the judgment was that plaintiff take nothing upon his complaint, and that defendant recover $2,000 upon its counterclaim. Plaintiff appeals from the judgment.

Appellant contends that the judgment was not supported by the evidence.

Plaintiff is an architect and general contractor. Defendant is a nonprofit corporation engaged in charitable, educational, and religious work.

On January 17, 1958, plaintiff and defendant entered into a written contract which provided: (in article 1) that plaintiff would furnish complete plans and specifications for, and would construct, an auditorium building for which the defendant would pay the total sum of $95,000; (in article 2) that the total contract sum shall be $95,000; (in article 3) that payments would be made as follows: at completion of the preliminary plans, $2,000; upon completion of working drawings and specifications, an additional $7,500, including a working capital of $2,000; at start of construction work, $10,000; during construction work, on the first of each month, such consecutive payments in amounts necessary to cover all labor and materials during such periods, but such amounts shall not be less than 20 per cent of the balance on the contract; the final balance shall be paid in accordance with article 5, subsections a, b, and c, of the contract (which article relates to substantial completion, notice of completion, etc.); that other than the $2,000 fee for the preliminary plans, the defendant shall be liable for “the balance of this Contract only” if a tentative loan commitment can be ob[590]*590tained by defendant in the approximate amount of $60,000, which is the balance between available cash funds and the total contract cost; (in article 7) that the amount mentioned in article 2 “is a guaranteed maximum and shall be subject to adjustments at the time of completion of working drawings and specifications and when the final estimate figures are complied [compiled].” Other provisions in the contract relate to items not included in contract, changes in the work, insurance, and amounts which plaintiff would allow the defendant to apply on its selections of lighting fixtures, landscaping, and finish hardware, but it will not be necessary to state the details of those provisions.

The contract was prepared by plaintiff and, as above shown, provided that defendant would pay $2,000 when the preliminary plans were completed. It is to be noted also that $7,500, “including a working capital of $2000.00,” was to be paid when the working plans and specifications were completed. This last provision was part of the basis for the controversy herein. Plaintiff asserts that the provision, “including a working capital of $2000.00,” meant that $2,000 in addition to the $7,500 was to be paid at the time the working plans and specifications were completed. In other words, plaintiff asserts that defendant was required to pay $2,000 when the preliminary plans were completed, and to pay $7,500 and $2,000 when the working plans and specifications were completed—making a total of $11,500 as of the time when the working plans and specifications were completed. Defendant asserts that the last $2,000 item was included in the $7,500.

Defendant paid the first $2,000 referred to (when the preliminary plans were completed), and also paid the $7,500 (when the working plans and specifications were completed) but did not pay an additional $2,000.

It is also to be noted that in the first part of the contract (article 2) it is stated that the total contract price shall be $95,000, and that in the latter part of the contract (article 7) it is stated that the amount mentioned in article 2 ($95,000) “is a guaranteed maximum and shall be subject to adjustments” when the final estimate figures are compiled. This provision was also a part of the basis for the controversy herein. Defendant asserts that $95,000 was the maximum amount that might be charged, and that when the bids of subcontractors were received and it was determined therefrom what the cost of material and labor would be, there would be [591]*591an adjustment downward of the amount to be paid under the contract so that in effect it was a contract for cost plus 10 per cent or other percentage. Plaintiff asserts that the contract was for a fixed amount or “package deal” of $95,000, which might be adjusted upward if there were extras.

Plaintiff testified that the final plans and specifications were approved by the defendant on September 2, 1958, and that thereafter he was ready, willing, and able to proceed with the performance of the contract; that defendant requested him to help obtain finances, and he obtained two tentative loan commitments for $60,000 at 6 per cent interest, with a charge of 1.5 per cent for the broker; he notified defendant regarding the commitments; the defendant notified plaintiff by letter that it (defendant) had obtained a tentative loan commitment ; the defendant never gave him permission to proceed with the construction of the building; the building was constructed by the Pozzo Construction Company, which used plaintiff’s plans with minor modifications (a copy of the plans was obtained from the city building department); the contract was for a fixed amount of $95,000; he never told defendant that when the final estimates were compiled he would adjust the guaranteed maximum downward; and he never told defendant that the contract would be cost plus a percentage or cost plus a fixed fee; he determined the cost of constructing the building by obtaining bids from reliable subcontractors and making a material and labor analysis; the final figure for completing the building was $67,715.42, which amount includes the $9,500 which he had received; he is suing for $27,248.58 ($27,284.58) as damages for breach of contract— being the profit, or difference between $95,000 and $67,715.42.

On October 11, 1957, while the parties were negotiating relative to entering into a building contract, the plaintiff sent a letter to defendant which stated: “As we are members of the A.I.A., we would not be in a position to bid on a competitive basis, thereby interfering with the ethics of said Institute. However, we are able to construct the building for you under either of the following conditions, provided there are no competitive bids taken, (a) Cost plus a percentage. (b) Cost plus a fixed fee.”

Mr. Drake, vice president of defendant, testified: That plaintiff, after writing said letter of October 11 relative to conditions under which he could make a contract, did not state [592]*592that he was mistaken as to those conditions and that he could enter into a contract for a fixed price. He (witness) explained to plaintiff that defendant was dependent upon gifts from friends and persons interested in defendant’s activities, and that in order to secure pledges of money from such persons for the church auditorium, the representatives of defendant wanted to know the most that the auditorium could possibly cost. During the negotiations the plaintiff stated that the words, “guaranteed maximum subject to adjustment,” meant adjustment downward. When the contract was submitted to defendant, a few days before it was executed, it did not contain the words, “including a working capital of $2000.00,” which are now at the end of subsection b of article 3;

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tahoe National Bank v. Phillips
480 P.2d 320 (California Supreme Court, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
212 Cal. App. 2d 588, 28 Cal. Rptr. 323, 1963 Cal. App. LEXIS 2885, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kreipl-v-philosophical-research-society-inc-calctapp-1963.