Krause v. Reyelts

2002 SD 64, 646 N.W.2d 732, 2002 S.D. LEXIS 77
CourtSouth Dakota Supreme Court
DecidedJune 5, 2002
DocketNone
StatusPublished
Cited by3 cases

This text of 2002 SD 64 (Krause v. Reyelts) is published on Counsel Stack Legal Research, covering South Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Krause v. Reyelts, 2002 SD 64, 646 N.W.2d 732, 2002 S.D. LEXIS 77 (S.D. 2002).

Opinion

*733 ZINTER, Justice.

[¶ 1.] Wayne and Kathy Cooper-Krause (hereinafter referred to as Wayne, Kathy, or Krauses as the context requires), sued their general contractor, David Reyelts (Reyelts). They claimed Reyelts was directly and vicariously liable for construction defects in their house. Reyelts raised the affirmative defense of release. Reyelts claimed that he was released because Krauses released Reyelts’s subcontractor. The trial court agreed and granted summary judgment in favor of Reyelts. We affirm in part, reverse in part, and remand.

FACTS AND PROCEDURAL HISTORY

[¶ 2.] On March 5, 1993, Krauses entered into a contract with Reyelts for the construction of a home in Rapid City. Reyelts subcontracted with Melvin Geidel Excavation (Geidel) to perform the excavation work on the project. The excavation work included digging the foundation and footings, back filling, and final grading.

[¶ 3.] Construction was completed in August of 1993. About a month later, Krauses noticed heaving and cracking concrete in the basement. In October of 1993, a leaking sewage pipe was discovered under the driveway. The defect in the pipe was caused by Geidel’s improper backfill and compaction.

[¶ 4.] As the general contractor, Rey-elts attempted to fix the defects. Reyelts spent $18,712.32 between October 1993 and February 1995 repairing the problems caused by the cracked sewer pipe and the defective excavation work performed by Geidel. Notwithstanding those repairs, new problems began to appear in the basement, in the patio, and in the garage floor and foundation.

[¶ 5.] Geidel’s liability insurance company ultimately agreed to reimburse Rey-elts for the initial repairs. In return, Wayne Krause and Reyelts signed a release in favor of Geidel. The release provided:

Reyelts Construction and Wayne Krause ... hereby release and discharge Melvin Geidel Excavation ... from any and all claims, demands, damage, lawsuits, and causes of action arising from Melvin Geidel Excavation’s work ... which include:
1) A hole in the sewage pipe, which was back filled by Melvin Geidel Excavation ... and
2) Improper final grading north side of the garage....

(emphasis added). Kathy witnessed the release, but she did not sign it in her individual capacity.

[¶ 6.] After receiving the release, Gei-del’s insurer paid Reyelts for the repair work Reyelts performed. On the same day the release was signed, the Krauses entered into a separate contract in which Reyelts agreed to correct the new problems. The new repairs specifically included sealing a concrete wall, constructing two swales outside the west side of the garage, replacing a concrete section of the basement floor, monitoring a garage door for repair, installing drain tile, and inspecting for water after the tile was installed. Except for the replacement of a portion of the basement floor, Reyelts completed this additional work. 1

[¶ 7.] Even after Reyelts completed these additional repairs, Krauses continued to experience problems. Krauses claim that the following “additional” problems arose: cracking and heaving of the concrete in the basement; cracking of the concrete driveway; cracking of the south and west foundation walls of the garage; settling and cracking of the concrete patio; *734 pooling of water in the garage; cracking in the sheetrock; and doors not closing properly.

[¶ 8.] These latest problems were not fully repaired by Reyelts. Therefore, Krauses hired Ron Huntley (Huntley), a concrete contractor, to correct them. During those repairs, Huntley noticed more construction defects. Two of those defects included a void of at least four inches between the concrete and the fill in the basement, and a failure to construct a required footing.

[¶ 9.] Krauses sued Reyelts claiming negligence, breach of express warranty, breach of implied warranty of fitness for a particular purpose, breach of contract, and fraud. Reyelts raised the affirmative defense of release. Reyelts claimed that the release of Geidel (the subcontractor) released Reyelts (the general contractor). The trial court agreed and granted Rey-elts’s motion for summary judgment. Krauses appeal.

STANDARD OF REVIEW

[¶ 10.] Summary judgment is authorized “if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact, and that the moving party is entitled to judgment as a matter of law.” We will affirm only when there are no genuine issues of material fact and the legal questions have been correctly decided. All reasonable inferences drawn from the facts must be viewed in favor of the non-moving party. The burden is on the moving party to clearly show an absence of any genuine issue of material fact and an entitlement to judgment as a matter of law.

Jorgenson v. Vener, 2002 SD 20, ¶ 9, 640 N.W.2d 485, 487 (internal citations omitted).

[¶ 11.] The effect of the release is the dispositive issue in this appeal. Because Wayne signed the release and Kathy only witnessed it, we consider Wayne and Kathy’s claims separately.

DECISION

[¶ 12.] 1. Whether Wayne’s release of Geidel (the agent/subcontractor) released Reyelts (the principal/contractor).

[¶ 18.] Wayne notes that, on its face, the release only referred to Geidel. Wayne also submitted an affidavit indicating that the release was intended to release only Geidel, not Reyelts. Wayne points out that we have previously held that the parties’ intent governs the scope of a release. Maryland Cas. Co. v. Delzer, 283 N.W.2d 244, 248 (S.D.1979).

[¶ 14.] Reyelts, however, contends that Wayne’s intent is irrelevant. Reyelts argues that even if Wayne did not intend to release Reyelts, a release of the agent/subcontractor also releases any vicarious liability claim against the principal/general contractor. Reyelts therefore claims that Wayne’s suit is barred by the release.

[¶ 15.] In Estate of Williams v. Vandeberg, 2000 SD 155, 620 N.W.2d 187, we considered a release that attempted to expressly reserve a vicarious liability claim against the principal while releasing the agent. We acknowledged a split of authority on this issue. After considering both views, we held that “a release of an agent is a release of the principal even when the release contains an express reservation and where the claim is premised on the single act of the agent.” Id. at ¶ 15, 620 N.W.2d at 191. Therefore, Reyelts is correct that even if Wayne did not intend to release his vicarious liability claim against Reyelts, the language in Williams does not permit the parties’ intent to override the release of the vicarious liability claims.

[¶ 16.] Wayne, however, argues that Williams should not apply to a case involving contractual liability. Wayne contends that Williams

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lattanzio v. Ackerman
682 F. Supp. 2d 781 (E.D. Kentucky, 2010)
Harris v. Best Business Products, Inc.
2002 SD 115 (South Dakota Supreme Court, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
2002 SD 64, 646 N.W.2d 732, 2002 S.D. LEXIS 77, Counsel Stack Legal Research, https://law.counselstack.com/opinion/krause-v-reyelts-sd-2002.