Kramer v. Carrabino

624 A.2d 648, 425 Pa. Super. 222, 1993 Pa. Super. LEXIS 1446
CourtSuperior Court of Pennsylvania
DecidedApril 28, 1993
DocketNo. 406
StatusPublished
Cited by1 cases

This text of 624 A.2d 648 (Kramer v. Carrabino) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kramer v. Carrabino, 624 A.2d 648, 425 Pa. Super. 222, 1993 Pa. Super. LEXIS 1446 (Pa. Ct. App. 1993).

Opinion

WIEAND, Judge.

In this appeal we are called upon to review a tripartite agreement, executed by an owner, a contractor and a lending institution, by the terms of which the lending institution agreed to hold all construction funds and make advances to the contractor as the work progressed. The trial court held that the lending institution by its agreement assumed no duty to the contractor and, in an action between contractor and [224]*224lending institution, entered summary judgment in favor of the lending institution. After careful review, we reverse.

Joseph Carrabino and Josephine, his wife, employed Wayne A. Kramer to construct a residential dwelling on a lot owned by the Carrabinos at Port Matilda, Centre County. United Federal Savings Bank agreed to make a construction loan in the amount of $147,500.00, to be secured by a mortgage and note executed by the Carrabinos. Additional moneys required for completion of the residence were to be deposited with the bank by the owners. All moneys were to be held by the bank in a “loans in process account” and were to be advanced by the Bank to Kramer as the work progressed in five installments of $27,000.00 each. The final payment was due when the residence was “completed and ready for occupancy and Declaration of Acceptance has been submitted to Lender.” With respect to this final disbursement, the tripartite loan agreement provided as follows:

“When the Contractor requests the final inspection, Lender will require that Owner and Contractor make a joint inspection of the dwelling and execute a ‘Declaration of Acceptance,’ as supplied by Lender, and submit this joint declaration to Lender prior to Lender making the 5th Stage Disbursement.”

In reliance upon this agreement, Kramer agreed to waive his right to file a mechanics’ lien.

From the “loans in process account” the bank drew moneys needed to make the first four installment payments to the contractor as the work progressed. When the residence was completed, United Federal made an inspection and authorized a final payment to Kramer. A declaration of acceptance was forwarded to the contractor who signed it and forwarded it to the Carrabinos. Apparently a dispute then arose concerning the construction of the residence between the owner and the contractor. In any event, the Carrabinos refused to sign the declaration of acceptance and instructed the bank not to release the final payment.

The bank, without making any attempt to have the owner and contractor conduct a joint inspection of the residence and [225]*225resolve their disagreement, refused to make any further payment to the contractor. Instead, the bank removed the remaining funds from the account which had been maintained for payment of the contractor and returned the funds to its general account. It also gave the owners credit for this amount against the face amount of the construction mortgage. Thereafter, the owners sold the property and satisfied the construction mortgage. As a consequence, the bank no longer has moneys in the special account with which to pay to the contractor the final installment.

Kramer filed an action against the Carrabinos and United Federal to recover the balance due under the construction agreement. Following the taking of depositions from Lawrence C. Saylor, the bank’s loan officer in charge of the Carrabino transaction, United Federal filed a motion for summary judgment. When the trial court granted it, Kramer appealed.

In Garbish v. Malvern Federal Savings and Loan Ass’n., 358 Pa.Super. 282, 517 A.2d 547 (1986), allocatur denied, 516 Pa. 641, 533 A.2d 712 (1987), the Court explored the duties of a lending institution to the owners with respect to the disbursement of a construction fund. The Court held that the lending institution had a fiduciary’s duty to disburse funds carefully and with the utmost good faith. We discern no basis for imposing any lesser duty on the lending institution with respect to the contractor where, as here, he has surrendered the right to file a mechanics’ lien in reliance upon the bank’s agreement with the contractor to hold and disburse those funds necessary to pay him for his work according to the parties’ agreement.

In determining the bank’s duties, of course, we must look to the terms of the construction loan agreement. In Henry v. First Federal Savings & Loan Association of Greene County, 313 Pa.Super. 128, 459 A.2d 772 (1983), the Court observed:

The interpretation of [a] construction loan agreement is a question of law for the court. While it is the court’s province to interpret the agreement, it is still inappropriate to enter a summary judgment if there are substantial [226]*226disputes as to the facts regarding the interpretation or application of its terms. Murray v. Yoe, 170 Pa.Super. 348, 85 A.2d 623 (1952). However, if the terms of the construction loan agreement are clear and unambiguous, we believe that summary judgment is appropriate if the court is able to apply those terms to the facts of the case because of the absence of substantial factual disputes.

Id. 313 Pa.Super. at 134-135, 459 A.2d at 775. When interpreting a contract, a court will “imply an agreement by the parties ... to do and perform those things that according to reason and justice they should do in order to carry out the purpose for which the contract was made and to refrain from doing anything that would destroy or injure the other party’s right to receive the fruits of the contract.” Slater v. Pearle Vision Center, Inc., 376 Pa.Super. 580, 586, 546 A.2d 676, 679 (1988).

Pursuant to the tripartite loan agreement in the instant case, the lending institution assumed responsibility for holding the construction moneys and advancing them to the contractor as the work progressed. The parties’ agreement was intended to protect both the owner and the contractor, as well as the bank’s security for its loan. When the contractor advised that the work had been completed, the lending institution had a duty to require the owner and the contractor to make a joint inspection of the residence and disburse the balance of the funds as the parties agreed.

It is correct, as the bank argues, that it could not be made to pay the remaining funds to the contractor without the consent of the owners. On the other hand, the bank could not return the remaining funds to the owners or otherwise act to defeat the contractor’s claim against the fund from which he was to be paid. Its duty to exercise good faith to protect the interests of the parties extended to both the owner and the contractor. When the bank took the proceeds intended to be used as final payment to the contractor, returned the proceeds to its general fund and gave the owners credit therefor against the amount the owners were required to pay, the bank breached its agreement with the contractor. It failed to exercise [227]*227that good faith in the performance of the contract which was an inherent part of its contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Melley v. Pioneer Bank, N.A.
834 A.2d 1191 (Superior Court of Pennsylvania, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
624 A.2d 648, 425 Pa. Super. 222, 1993 Pa. Super. LEXIS 1446, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kramer-v-carrabino-pasuperct-1993.