Kraft-Phenix Cheese Corp. v. H. B. Smith Machine Co.

267 Ill. App. 539, 1932 Ill. App. LEXIS 362
CourtAppellate Court of Illinois
DecidedOctober 4, 1932
DocketGen. No. 35,895
StatusPublished
Cited by2 cases

This text of 267 Ill. App. 539 (Kraft-Phenix Cheese Corp. v. H. B. Smith Machine Co.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kraft-Phenix Cheese Corp. v. H. B. Smith Machine Co., 267 Ill. App. 539, 1932 Ill. App. LEXIS 362 (Ill. Ct. App. 1932).

Opinion

Mr. Justice Gridley

delivered the opinion of the court.

In an action in assumpsit to recover damages for claimed breach of contract for the manufacture and sale of certain special machines, there was a trial before a jury in January, 1932, resulting in a verdict and judgment against defendant for $1,290.16. The present appeal followed.

About two years after the commencement of the action plaintiff, on November 30, 1931, by leave of court; filed an amended declaration consisting of four special counts and the common counts. In the first special count plaintiff avers that on February 16,1929, plaintiff and defendant entered into a contract whereby the former promised to purchase of the latter “three certain machines with overhead arbors that could be used in sawing foraminous malted milk into rectangular bars of the dimensions 3" x IV2" x and defendant promised to manufacture, furnish and deliver to plaintiff such machines within 30 working days from the making of said contract”; that in consideration of defendant’s promises plaintiff promised to pay to defendant the sum of $3,700, — thereof ($1,233.34) at once and the balance within 30 days from the date of shipment of said machines”; that plaintiff paid $1,233.34 at the time of making the contract and has at all times since been ready to pay the balance when the same “should become due according to the terms of said contract”; that after the expiration of said 30 working days defendant tendered to plaintiff three machines as in compliance with said contract, which machines plaintiff accepted, but that the machines were not such as defendant had contracted to deliver, in that they ‘ ‘ did not have overhead arbors as it was provided they should have in. and by said contract”; that prior to the making of the contract plaintiff told defendant that the machines were being purchased by it “in order to conduct a business of manufacturing and selling foraminous malted milk bars of the dimensions set out hereinabove and that plaintiff then had a continuing offer from a customer for the purchase of all such malted milk bars as it might manufacture up to 1,000 pounds of such bars per day, from the filling of which orders it (plaintiff) could make large profits, which was in fact true ’ ’; that due to the failure of the machines furnished by defendant to comply with the contract, “plaintiff was obliged to procure other machines, with which to manufacture such malted milk bars, and pay the cost thereof, and was also prevented from commencing its business of manufacturing said bars for a period of, to wit, seven (7) months”; that the machines delivered could not be used by plaintiff ■ in sawing the malted milk into rectangular bars “because of the aforesaid respects in which they differed from the machines which defendant contracted to deliver to plaintiff”; that the machines from the time of delivery were and are “useless to plaintiff and without value, either for the purpose of its business or for the purpose of re-sale, or for any other purpose ’ ’; that plaintiff also incurred and paid certain costs and charges in connection with the shipping of the machines “in the amount of $56.82”; and that by reason of the aforesaid facts plaintiff has been damaged in the sum of $40,000, etc.

The averments of the second, third and fourth special counts are substantially the same as in the first. The particular breach assigned in the second count is that defendant “did not, within 30 working days from the making of said contract, deliver to plaintiff any machines, but did after said time deliver to plaintiff other machines, which plaintiff accepted but which were not in compliance with said contract, in that said machines could not be used in sawing foraminous malted milk with rectangular bars having the dimensions aforesaid.” The particular breach assigned in the third count is substantially the same as in the second. In the fourth special count the particular breach assigned is that the three machines, as tendered by defendant and accepted by plaintiff, “did not have overhead arbors, and could not be used ... so that all the sawing operations performed by the three machines would be effected as one continuous operation in the manufacture of said malted milk bars, — the second machine taking stock from the first machine and the third machine taking stock from the second machine.”

To this declaration defendant filed a plea of the general issue, and also a notice that upon the trial it would give in evidence, as against plaintiff’s claim, facts showing that it had fully complied with its contract and had delivered to plaintiff such machines as contracted for; that defendant had no knowledge of plaintiff’s alleged contract with a customer relative to the manufacture of 1,000 pounds of malted milk bars per day; that plaintiff was not obliged to and did not secure other machines to manufacturé said milk bars, and was not required to pay anything in expenses or otherwise for claimed improvements made on the machines; and that plaintiff is still indebted to defendant for the unpaid balance, $2,466.66, on the purchase price of the machines, which defendant will urge upon the trial should be set off as against plaintiff’s alleged claim.

On the trial considerable evidence, oral and documentary, was introduced by the parties. Plaintiff’s principal witness was Ernest E. Bellamy, who was in charge of the “malted milk division” of its business at its Chicago office. Its other witnesses were Frederick Beverly, in charge of its “milk plant” at Wausau, Wisconsin, and Edward Kraft, an assistant to the superintendent of said plant at Wausau. Defendant’s principal witness was William A. Whiting, manager of defendant corporation, which for many years had been engaged in Chicago in the manufacture and sale of special machinery. Five other witnesses also testified in defendant’s behalf.

Bellamy, plaintiff’s witness, testified that during January, 1929, he had several conversations with Whiting in Chicago as to defendant manufacturing machines for plaintiff, in which he told Whiting what particular machines were wanted and for what purposes, and that, for Whiting’s better understanding of the character and purpose of the machine, 'the witness and Whiting made a trip to plaintiff’s plant at Wausau, early in February, 1929, where they met Beverly and others, viewed the operation of certain machines and certain equipment and merchandise, and had further conversations. The witness then started to testify as to what Whiting then said as to defendant’s ability to furnish the machines desired and within what time and as to what the machines and equipment would do. Thereupon defendant’s attorney asked if plaintiff was relying upon a written or an oral contract, to which plaintiff’s attorney replied that it was relying upon the written contract embodied in four writings which passed between the parties during February, 1929. Thereupon defendant’s attorney objected to any testimony of the witness to prove a verbal contract at variance with the contract as written, or as tending to modify it. The court sustained the objection and said to plaintiff’s attorney: “Ton will have to rely on the written contract.” Thereupon plaintiff introduced in evidence, without objection, the four writings, as “Plaintiff’s Exhibits 2, 3, 4, 5.” Exhibit 2 is a letter or proposition, dated at Chicago, February 11, 1929, signed by defendant, per Whiting, and addressed to plaintiff at Chicago, as follows:

“As per conversation with your Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vulcan Corp. v. Cobden Machine Works
84 N.E.2d 173 (Appellate Court of Illinois, 1949)
Smith v. Rust
33 N.E.2d 723 (Appellate Court of Illinois, 1941)

Cite This Page — Counsel Stack

Bluebook (online)
267 Ill. App. 539, 1932 Ill. App. LEXIS 362, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kraft-phenix-cheese-corp-v-h-b-smith-machine-co-illappct-1932.