Kotlarz v. Olson Bros., Inc.

740 N.W.2d 807, 16 Neb. Ct. App. 1
CourtNebraska Court of Appeals
DecidedOctober 9, 2007
DocketA-05-1247
StatusPublished
Cited by25 cases

This text of 740 N.W.2d 807 (Kotlarz v. Olson Bros., Inc.) is published on Counsel Stack Legal Research, covering Nebraska Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kotlarz v. Olson Bros., Inc., 740 N.W.2d 807, 16 Neb. Ct. App. 1 (Neb. Ct. App. 2007).

Opinion

740 N.W.2d 807 (2007)
16 Neb. App. 1

Mary KOTLARZ and David Kotlarz, Appellants and Cross-Appellees
v.
OLSON BROS., INC., a Nebraska corporation, Appellee and Cross-Appellee, and Powers-Meyers-Carlisle, a project-specific joint venture, Appellee and Cross-Appellant.

No. A-05-1247.

Court of Appeals of Nebraska.

October 9, 2007.

*809 James E. Harris, Britany S. Shotkoski, and Michaela Skogerboe, of Harris Kuhn Law Firm, L.L.P., Omaha, for appellants.

Jerry W. Katskee and Melvin R. Katskee, of Katskee, Henatsch & Suing, Omaha, for appellee Olson Bros., Inc.

P. Shawn McCann, of Sodoro, Daly & Sodoro, P.C., Omaha, for appellee Powers-Meyers-Carlisle.

IRWIN, SIEVERS, and CASSEL, Judges.

*810 SIEVERS, Judge.

Mary Kotlarz and David Kotlarz appeal the order of the district court for Douglas County granting summary judgment in favor of Olson Bros., Inc. (Olson), and Powers-Meyers-Carlisle, a project-specific joint venture (PMC) (collectively Appellees). We find that summary judgment was not proper as to defendant Olson, and therefore, we reverse, and remand the cause as to such defendant. With respect to defendant PMC, we sustain the grant of summary judgment and dismissal of the cause, although on the basis of the statute of limitations as raised in PMC's cross-appeal.

FACTUAL BACKGROUND

Viewed in a light most favorable to the Kotlarzes, the record reflects the following facts: On March 30, 1999, Mary attended a physical therapy session at Alegent Health Lakeside Clinic (the Clinic) located in Omaha. The property was under construction, but it was open to the public. On March 30, there was no construction work being performed on the premises, or in the area where Mary parked, because it was an extremely windy day with wind gusts of around 45 miles per hour.

Around 5 p.m., after her physical therapy appointment, Mary, carrying a traction device, walked to her car, opened her trunk with a key, and placed the traction device in her car. Mary's car was facing north at the time. During this time, Mary did not notice anything blowing around in the wind. As she was closing the trunk, there was a gust of wind, and Mary felt a sharp blow to the base of her neck on the left side and then "excruciating pain." Mary did not know where the object came from, she did not see what hit her, and there were no eyewitnesses. Nevertheless, immediately after she felt the sharp blow to her neck, she saw a piece of 4-by 8-foot foam sheet, which did not appear to be damaged, fly through the air in front of her. Mary then walked back to the Clinic, and while she was walking back, she saw three foam sheets in the parking area which appeared to be the same as the foam sheet that she saw after she was struck. Mary went inside the Clinic, reported that she had been hit and that there was debris flying around outside, and then was treated for her injuries. Mary's son arrived shortly thereafter and retrieved a piece of foam sheet he found in the parking lot. Mary said that the piece of foam sheet recovered by her son was the same composition as the foam sheet that she saw right after being struck, as well as being the same as the three foam sheets Mary observed as she returned to the Clinic after the incident.

PMC was the general contractor for the building project at Alegent Health Lakeside Wellness Center (Alegent), which was located adjacent to the Clinic. PMC is a project-specific joint venture between Power Construction Company, an Illinois corporation, and Meyers-Carlisle Construction Company, a corporation qualified to do business in Nebraska. Olson was the roofing subcontractor for the building project.

PROCEDURAL BACKGROUND

On March 26, 2003, the Kotlarzes filed a complaint in the district court for Douglas County alleging that the Appellees' negligence caused injuries to Mary and that David suffered from a resulting loss of consortium due to Mary's injuries. The complaint named Olson and "Meyers-Carlisle-Leapley Construction Co., Inc[.,] f/k/a Powers-Meyers-Carlisle" as defendants. The complaint alleged that on March 30, 1999, Mary was injured by a piece of construction material, a "4' × 8' piece of foam board," which was not properly *811 secured at the construction site and which was blowing around due to strong winds at the time Mary was closing the trunk of her car. Among the allegations of negligence, the complaint stated that the Appellees failed to take and enforce adequate safety precautions and to properly secure the roofing materials.

"Meyers-Carlisle-Leapley Construction Company, Inc., f/k/a Powers-Meyers-Carlisle," filed an answer to the complaint denying any negligence. Olson's answer admitted that the winds on March 30, 1999, were "unusually strong" and that it was engaged in roofing work at the Alegent site, but Olson denied any negligence.

On August 4, 2003, the Kotlarzes and "Meyers-Carlisle-Leapley Construction Company, Inc., f/k/a Powers-Meyers-Carlisle," filed a stipulation agreeing that such party name was a misnomer and stating that "`Powers-Meyers-Carlisle, a Project-Specific Joint Venture'"—PMC—should be substituted in its place. Part of the stipulation provided that PMC was making a voluntary appearance and waiving service of process, and it was provided that PMC would have 14 days in which to answer the suit. The district court granted the stipulation.

In late August 2004, Olson filed a motion for summary judgment. On September 3, PMC filed a motion for summary judgment, alleging both that the Kotlarzes were not entitled to judgment as a matter of law and that the Kotlarzes' complaint was barred by the applicable statute of limitations. Also on September 3, PMC filed an answer and cross-claim admitting that it was the general contractor for the Alegent project; denying any negligence on its part; admitting that on March 30, 1999, Mary was attending a physical therapy appointment at the Clinic; and asserting that all construction material had been secured on the day of her appointment. PMC cross-claimed against Olson, stating that PMC had entered into a subcontract agreement with Olson for the roofing work at the premises, and prayed for contribution or indemnity against Olson in the event that PMC was found liable for all or part of the Kotlarzes' damages.

Additionally, the affidavit of Stanley Stanek, an Olson employee, was received into evidence. Stanek said that on March 30, 1999, construction was postponed because of high winds, and that in the morning, he and another employee secured "all Olson roofing materials stacked near the southwest corner of the building," making certain that the materials were "covered by a tarp and weighted by tires." Stanek also said that there was ongoing construction at properties around the Alegent site, but that he did not know whether construction was ceased at those sites on March 30. Stanek further stated he could not say that the "broken piece of foam board" recovered by Mary's son "was product that we used on the subject project or that it came from an area of the construction site under Olson's control or that of the general contractor, PMC." In attempting to contradict PMC's affirmative defense that the "accident that occurred was a result of the negligence of other persons or entities" and in response to Stanek's affidavit stating that there was construction ongoing at the properties around and adjacent to the Alegent site, Mary produced a report from a consulting meteorologist stating, within a "reasonable degree of meteorological certainty," that on March 30, the wind was from the south, gusting to around 45 miles per hour.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Clark v. Scheels All Sports
989 N.W.2d 39 (Nebraska Supreme Court, 2023)
Davis v. Ridder
309 Neb. 865 (Nebraska Supreme Court, 2021)
Hughes v. School Dist. of Aurora
290 Neb. 47 (Nebraska Supreme Court, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
740 N.W.2d 807, 16 Neb. Ct. App. 1, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kotlarz-v-olson-bros-inc-nebctapp-2007.