Kostelac v. United States

247 F.2d 723
CourtCourt of Appeals for the Ninth Circuit
DecidedJune 28, 1957
DocketNo. 15343
StatusPublished
Cited by6 cases

This text of 247 F.2d 723 (Kostelac v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kostelac v. United States, 247 F.2d 723 (9th Cir. 1957).

Opinion

DENMAN, Chief Judge.

These are appeals by both plaintiff, United States, and by defendants, Mike Kostelac and his surety, the Maryland Casualty Company, from a judgment of the district court for the western District ■of Washington, Southern Division, awarding $30,716.18 to the United States in its action against defendants for breach of contract to purchase garbage, •or food waste, for hog feed.

Most of the facts are stipulated. Prior to June, 1946, Kostelac, who was experienced in the hog raising business, and who had previously purchased food waste from military installations as hog feed, requested the contracting officer at Fort Lewis, Washington, to place his name on .a roster of bidders for a contract to haul food waste or garbage from the mess halls at that base. Subsequently bids were invited by the Fort Lewis authorities on a five-year contract to buy garbage, the contract price to be based on the per man per day production of waste —that is, the amount owed by the contractor was to be determined by multiplying a price rate by the number of men fed in the mess halls, rather than according to the weight of the garbage •collected. It appears that this system of determining the quantity was novel, and that its purpose was to eliminate the necessity of weighing the garbage collected each day. The Army contracting officer urged bidders to inspect the garbage containers prior to bidding and it appears that Kostelac very carefully did so. On the basis of his examination and of the representation made in good faith by the contracting officer that the quantity of garbage he . observed in the containers was a one-day accumulation. Kostelac estimated the quantity of waste produced per man per day and made a bid which was accepted by the Army.

Thereafter Kostelac began collecting the garbage and discovered that what he had seen in the containers was a two-day rather than a one-day accumulation. On July 10, Kostelac advised Sixth Army Headquarters of the mistake that had been made in estimating the amount of garbage produced per man per day. In the words of the pretrial order in which the parties stipulated most of the material facts, Kostelac thereafter “persistently pursued efforts to have the Government modify, adjust, or cancel his said contract, addressing his communications in that respect to both the military and congressional authorities, and during which time, on or about July 24, 1946, defendant Kostelac undertook renegotiation of his contract with the Contracting Officer at a reduced sliding scale submitted by him, which renegotiation was subject to its approval by the Headquarters Sixth Army; that, however, upon referral of the same to said Headquarters, on or about August 2, 1946, it was the determination of said Headquarters that, upon acceptance by the Contracting Officer of said contract, certain rights accrued to the Government of the United States, that the War Department was without authority to release these rights, and that accordingly said contract would be enforced in accordance with the provisions thereof.”

Kostelac, while continuing his efforts for renegotiation, picked up garbage at the Fort until December 15, 1946, without paying therefor. On that date a [726]*726substitute contract with another party went into effect for the remainder of the contract period.

Thereafter the Government began this action to recover the contract price of the garbage which Kostelac received, and damages in the amount of the difference between the price of the garbage for the remainder of the contract period (4y2 years) under the contract with Kostelac, and the lower price for the garbage during this period under the substitute contract. The district court gave judgment for the United States for the contract price of the garbage which Kostelac collected, but denied damages for the remainder of the contract period “under the peculiar circumstances of this case.”

It is apparent that this decision is inconsistent: (1) if the contract is valid, the United States was entitled not only to the contract price for the garbage which Kostelac took, but to compensation for loss incurred by reason of failure to pick up garbage after December 15, 1956; (2) if Kostelac is entitled to rescission he is liable only for the fair value of the garbage which he actually obtained.

The first question to be decided is whether the mistake was such as to entitle Kostelac to rescind the contract upon its discovery. The district court found that there was “no question but that Kostelac made an error * * * when he prepared his bid,” but concluded that it was unnecessary to decide whether Kostelac ever had such a right, because, if he did, he had waived it.

However, this question is not only material, it is the first question which must be decided. Since substanti-

ally all of the facts concerning the contract, the negotiations after the mistake was discovered, and Kostelac’s default were stipulated in the pretrial order,1 the question before this court would be whether the trial court’s finding on this point was supported by the record,2 if the trial court had made a finding. Since the court has made no finding and since the evidence on this question is written, as it was before the trial court, it is proper for this court from such undisputed written evidence to decide whether Kostelac was entitled to rescind the contract because of the mistake as to the quantity of garbage produced per man per day at the base.3

The trial court found that a mistake had been made and it is not contended here that the mistake was not material. The error was basic to the contract, since it resulted in giving Kostelac the impression that under the contract the unit for measuring the quantity of food waste consisted of twice the accumulation of waste that it was subsequently found to contain.4 This error clearly resulted from Kostelac's reliance upon the statement of the Army contracting officer who in good faith told him that the amount of waste in the containers which Kostelac inspected was only a one day’s accumulation when, in fact, it was an accumulation of two days’ waste. Hence Kostelac assumed that the number of men then at the Fort produced daily twice the amount of waste they actually produced, and his bid on the per man per day basis of the contract was founded upon the assumption that the per man per day rate of garbage production was double what it was in fact. Kostelac’s error so induced by the Government’s [727]*727representative is clearly a material mistake. See Rest. Contracts § 500.

The next question is whether this material mistake entitled Kostelac to rescission. There is substantial authority for the proposition that “rescission may be had on account of innocent misrepresentations of material facts on which the party seeking relief relied to his detriment.”5 There can be no doubt that Kostelac relied on this misrepresentation in making his bid. The district court impliedly so found when it rested its denial of relief to Kostelac solely on the ground that he had waived his right to rescind.

Under the above quoted principle Kostelac is entitled to rescind the contract unless, as the Government contends, other facts appear which prevent its application to this case.

First, the Government contends that under the terms of the contract Kostelac assumed the risk of the mistake which was made.

Free access — add to your briefcase to read the full text and ask questions with AI