Kosier v. Derosa

862 N.E.2d 159, 169 Ohio App. 3d 150, 2006 Ohio 5114
CourtOhio Court of Appeals
DecidedSeptember 29, 2006
DocketNo. WD-05-050.
StatusPublished
Cited by14 cases

This text of 862 N.E.2d 159 (Kosier v. Derosa) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kosier v. Derosa, 862 N.E.2d 159, 169 Ohio App. 3d 150, 2006 Ohio 5114 (Ohio Ct. App. 2006).

Opinion

{¶ 1} This appeal is from the June 16, 2005 judgment of the Wood County Court of Common Pleas, which granted final judgment to appellee, McMillan E. Kosier, in a breach-of-contract action. Upon consideration of the assignments of error, we reverse the decision of the lower court. Appellant, Frank DeRosa, asserts the following assignments of error on appeal: *Page 152

{¶ 2} "1. The trial court erred by claiming Appellant's actions constituted a repudiation and breach of the (oral) contract.

{¶ 3} "2. Trial Court erred by denying the Appellant's motion for Directed Verdict because it should have held: 1. The Appellee, as a matter of law, was the first to breach the party's agreement(s) and 2. Appellee failed to prove measurable damages to a reasonable degree of certainty.

{¶ 4} "3. The Trial court erred by shift the burden of proof to the Appellant concerning presentation of credible evidence of damages (lost profit).

{¶ 5} "4. Trial court erred, and its holding is an abuse of discretion and is arbitrary and capricious, when it claimed the Appellee's Labor expenses, to a reasonable degree of certainty, amount to 50% of the installation and finishing costs.

{¶ 6} "5. The Trial Court erred in failing to find the Parties entered into a new (written) contract which reformed the original agreement and that the Plaintiff/Appellee not Defendant/Appellant breached the agreement as a matter of law."

{¶ 7} Appellee, McMillan Kosier, sued appellant, alleging a breach of an oral contract, and sought foreclosure of a mechanic's lien. Kosier alleged that DeRosa has failed to pay Kosier for a hardwood floor he installed on the second story of DeRosa's home. In his answer to the complaint, DeRosa admitted that the parties had a contract for the installation of hardwood flooring at DeRosa's home.

{¶ 8} The parties stipulated to the following facts. In April 2002, Kosier and DeRosa entered into an oral contract. They agreed that Kosier would install hardwood flooring in DeRosa's home. Kosier was to be paid $4 per square foot for materials for the upstairs, and DeRosa would supply the flooring for the downstairs. Furthermore, Kosier was to be paid $2 per square foot for installation of all of the flooring and $2 per square foot to finish all of the flooring. The square footage for the project was 1,185 square feet for the upstairs flooring and 2,158.25 square feet for the downstairs.

{¶ 9} In May 2002, Kosier purchased the materials for the upstairs and, in July 2002, he installed nearly all of the hardwood floor on the second floor. He was unable to complete the installation of the flooring because the staircase to the second floor had not yet been installed. Kosier later attempted to remove the flooring in the upstairs hallway but discontinued after a small area had been removed. Kosier was also not able to complete the installation of the downstairs floor because DeRosa had not yet prepared the areas for flooring. The home is still not ready for installation of the downstairs flooring and DeRosa has not made the hardwood flooring available to Kosier. *Page 153

{¶ 10} In August 2002, Kosier invoiced DeRosa for the cost of the materials for the second floor and the labor to install the second-story flooring. DeRosa sent Kosier a letter on August 26, 2002, complaining that Kosier had not screwed down the subfloor and that the floors squeaked in numerous areas. He also complained that the workmanship was unacceptable because there was face nailing. DeRosa sent Kosier another letter on October 3, 2002, setting forth their mutual agreement regarding the options that were available to them. DeRosa wrote that they had agreed to the installation of four-inch thick oak floors at $8 a square foot and finished with three coats of a material supplied by Kosier. The great room and kitchen areas were to be installed with material supplied by DeRosa and finished for $4 per square foot. Payment was to be made after all of the flooring was laid and finished. DeRosa also complained again that the installation was poor, with glued one-inch pieces placed at the ends, squeaking, and face nailing. DeRosa agreed that Kosier could either tear out the floor that he had laid or complete the job and be paid at the end if the floors were professionally and satisfactorily installed.

{¶ 11} In an October 21, 2002 letter, Kosier told DeRosa that he had never complained about the workmanship during the four months between the time Kosier laid the floor and the time that he submitted his invoice. Kosier also stated that the two had met on September 13, 2002, and examined the floor. They found two squeaks near the staircase that would be eliminated when the floor was completed. Furthermore, DeRosa was unable to find any face nailing. Kosier also asserted that he never agreed to wait for payment when he was unable to complete the job, because DeRosa was acting as his own general contractor and was not proceeding to complete the home in a timely manner. Kosier agreed to accept DeRosa's option to remove the second story flooring.

{¶ 12} In an undated letter from DeRosa to Kosier, DeRosa asserted that Kosier had started to remove some of the flooring, but never completed the job. DeRosa sent Kosier subsequent letters dated December 2003, April 1, 2004, and July 26, 2004, requesting that Kosier complete removal of the flooring and remove the lien against DeRosa's property. DeRosa also indicated in the December letter that Kosier still had a key to DeRosa's property and that DeRosa would treat Kosier's presence on DeRosa's property as trespassing.

{¶ 13} Steve Drossel, of Drossco Custom Hardwood, examined the hardwood floor laid by Kosier and determined that it needed to be removed and replaced because of face nailing, improper cutting of board lengths, failure to use proper cutting tools, and cupping of the boards due to either a failure to acclimate the materials to their new surroundings or a failure to leave a one-fourth inch gap along the wall for the expansion. *Page 154

{¶ 14} At a trial to the bench, the following additional evidence was submitted. Kosier testified that he ordered the hardwood after DeRosa indicated that the home was ready for the flooring. He ordered the wood on May 2 and it was delivered a few days later. He installed all but 35-45 square feet beginning on May 7. However, he also recalled letting the wood acclimate to the house between three to seven days before installation. Kosier was unable to finish the job because the staircase to the second story had not yet been installed. Kosier was unable to install the downstairs flooring because DeRosa had not yet provided the hardwood as agreed.

{¶ 15} After Kosier sent DeRosa an invoice, DeRosa complained about the quality of Kosier's work. With respect to those complaints, Kosier testified that he never agreed to screw down the subfloor before installing the hardwood floor; he never agreed to avoid face nailing as it is always needed; and he only face nailed a few areas that needed to be tightened. Kosier met with DeRosa in September 2004, and they looked over the floor together. That day, they found only two squeaks, both near the staircase. Kosier believed that installation of the staircase and the remainder of the floor would resolve these squeaks. He also believed that the face nails would not be visible after the flooring was finished.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Yagour Group, L.L.C. v. Ciptak
2024 Ohio 73 (Ohio Court of Appeals, 2024)
Revolaze, L.L.C. v. Dentons US L.L.P.
2022 Ohio 1392 (Ohio Court of Appeals, 2022)
MRC Innovations, Inc. v. Lion Apparel, Inc.
2020 Ohio 694 (Ohio Court of Appeals, 2020)
Tackle Constr. Group, L.L.C. v. Pedtke Ents., Inc.
2018 Ohio 1859 (Ohio Court of Appeals, 2018)
Horter Investment Management, LLC v. Cutter
257 F. Supp. 3d 892 (S.D. Ohio, 2017)
Mcgowan & Co. v. Bogan
93 F. Supp. 3d 624 (S.D. Texas, 2015)
Ask Chemicals, LP v. Computer Packages, Inc.
593 F. App'x 506 (Sixth Circuit, 2014)
Eggert Agency Inc. v. NA Management Corporation
428 F. App'x 558 (Sixth Circuit, 2011)
Wrg Servs. v. Eilers, 2008-L-057 (11-7-2008)
2008 Ohio 5854 (Ohio Court of Appeals, 2008)
Nieman v. Bunnell Hill Dev. Co., Inc., Ca2007-07-174 (10-27-2008)
2008 Ohio 5541 (Ohio Court of Appeals, 2008)
Hanna v. Groom, 07ap-502 (2-26-2008)
2008 Ohio 765 (Ohio Court of Appeals, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
862 N.E.2d 159, 169 Ohio App. 3d 150, 2006 Ohio 5114, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kosier-v-derosa-ohioctapp-2006.