Kortgardner Trucking Co. v. Crippen Construction Co.

12 Tenn. App. 141, 1930 Tenn. App. LEXIS 47
CourtCourt of Appeals of Tennessee
DecidedJune 20, 1930
StatusPublished

This text of 12 Tenn. App. 141 (Kortgardner Trucking Co. v. Crippen Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kortgardner Trucking Co. v. Crippen Construction Co., 12 Tenn. App. 141, 1930 Tenn. App. LEXIS 47 (Tenn. Ct. App. 1930).

Opinion

SENTER, J.

The complainant is a Kentucky corporation and sues the defendant on a claim of $1776.50, alleged retained percentage growing out of a road contract in the State of Kentucky. The bill alleges that in the year 1923 it entered into a contract with the defendant, Crippen Construction Co., to do certain road construction work for the defendant on a state and federal aid project in the State of Kentucky. The bill alleges that complainant was a subcontractor of the defendant, and under its contract was to receive ninety per cent of the amount of work on monthly estimates and to receive the balance, ten per cent retained percentage, when the work was completed. The bill further alleges that the total amount of work done by complainant for the defendant under its contract was $17,765, and that it had received from the defendant on the monthly estimates during the summer of 1923 the sum of $15,988.50, leaving the defendant due and owing to complainant, as of October 1, 1923, the time of the completion of the work, a balance of $1776.50, and for which amount it sues.

The defendant answered the bill, and the answer admits that it entered into a contract with complainant in 1923, to do certain road construction work in the state of Kentucky. The answer admits that the complainant did this work and that the amount alleged in the bill is correct as representing the unpaid balance. The answer admits that ten per cent of the total amount was to be retained until the completion of the work, but alleges that the ten per cent was retained by the state of Kentucky and' not by this defendant. The answer further alleges .that the ten per cent retainage was not to be paid to complainant until the defendant had collected the same. The answer alleges that the Wilmore Construction Company, of Kentucky, procured the contract from the state of Kentucky for the building of about sixteen miles of state and federal aid highway; that the defendant, in turn, contracted with the Wilmore Construction Company for the grading and draining of the sixteen miles of highway, and was the subcontractor to the Wilmore Construction Co.; that it sub-let to complainant the grading or fill of about 4,000 feet in length at a price ten per cent less than defendant was to receive from the *143 Wilmore Construction Co.; that the complainant was to receive ninety per cent on estimates as the work progressed, and would not receive the ten per cent retainage until the completion of the work and not until defendant had been paid the ten per cent retainage.

The answer further alleged that the state of Kentucky refused to make final settlement with Wilmore Construction Co., and finally the Wilmore Construction Co., the general contractor, with the aid of defendant, procured a special Act to be passed by the Kentucky legislature authorizing the Wilmore Construction Co. to sue the state or the State Highway Department for the alleged retained percentage; that pursuant to said enactment in 1927 the Wilmore Construction Co. filed suit on the claim for the retained percentage, and a claim for additional work amounting to about $95,000; that Wilmore Construction Company, without consulting defendant, compromised the suit with the state of Kentucky and as a compromise settlement, received the sum of $30,000; that notwithstanding the agreement between defendant and Wilmore Construction Co., that whatever amount was received or realized from said suit, or any compromise with the state of Kentucky, that defendant was to receive its pro rata portion of same on the basis of its claim as the same sustained to the amount of the claim of Wilmore Construction Co.; that the Wilmore Construction Co. had refused to pay the defendant any part of the amount realized in the compromise settlement, but was claiming that defendant was not entitled to any part of the same, but that the Wilmore Construction Co. asserted a claim against defendant for an alleged $17,000 because of the alleged failure of defendant to comply with its contract in the grading and drainage. The answer further alleged that under its contract with complainant it was not liable to complainant for the ten per cent retainage until it had collected the same from the state of Kentucky or Wilmore Construction Co., and that therefore the suit of complainant against defendant was premature.

Upon the hearing of the cause the Chancellor found the issues in favor of the defendant, and held that the suit had been prematurely brought by complainant, and that complainant would not be entitled to recover against the defendant for the. ten per cent retained until the- same had been collected by the defendant. From this decree complainant prayed and was granted an appeal to this court, which appeal has been duly perfected, and errors ■ assigned.

The several assignments of error are directed to the action of the Chancellor in holding and decreeing that complainant was not entitled to maintain the suit against the defendant until defendant had received from the Wilmore Construction Co. the retained percentage, and in holding that the suit was prematurely brought; and in holding that under the contract and the facts complainant would not be liable *144 to defendant for the retained percentage until it had collected the same from Wilmore Construction Co.

There seems to he no controversy between the parties on the question of the complainant having fully performed its contract in the matter of doing the grading and other work that it was required to do as the subcontractor under its contract with the defendant. It appears that this work was all performed and completed by complainant by October 1, 1923. It is contended by complainant that it did not agree or contract with the defendant to wait until the state of Kentucky had settled the ten per cent retainage with the defendant; that its contract was with the defendant alone.

The complainant took the deposition of George Kortgardner, Jr., the president of complainant corporation. This witness testified that he made the contract with the defendant for his corporation, whereby complainant became the subcontractor of defendant. He testified as to the total amount of work done, and that he completed his part of the contract in about six^months, or by October 1, 1923. He testified that complainant had received from defendant all of the contract price except the ten per cent retained until completion. He admitted that defendant would be entitled to have deducted as its 'profit ten per cent of the amount retained, and that the claim of complainant was for the sum of $1598.85 in place of $1776.50. This witness testified that there was a short memorandum of the contract in, writing. He denied that the complainant was to wait until defendant collected the ten per cent retained until the state of Kentucky settled with defendant. He stated that he knew nothing of the suit by the Wil-more Construction Co. against the state of Kentucky, and denied that he was not entitled to receive this retained percentage until the stat.e of Kentucky had settled with the contractor.

On cross-examination this witness admitted that this was the first contract for road construction work that his company had entered into. We think it appears with reasonable certainty that he knew and understood the custom that the retained percentage would not be paid until the completion of the road contract, and that the state would retain ten per cent of the estimates until the entire contract had been fully completed and accepted by the. State Highway Department. J. D.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
12 Tenn. App. 141, 1930 Tenn. App. LEXIS 47, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kortgardner-trucking-co-v-crippen-construction-co-tennctapp-1930.