Korner Roofing & Sheet Metal Co. v. Smylie Bros.

188 N.E.2d 802, 118 Ohio App. 461, 92 Ohio Law. Abs. 100, 25 Ohio Op. 2d 360, 1963 Ohio App. LEXIS 814
CourtOhio Court of Appeals
DecidedMarch 14, 1963
Docket26269
StatusPublished
Cited by1 cases

This text of 188 N.E.2d 802 (Korner Roofing & Sheet Metal Co. v. Smylie Bros.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Korner Roofing & Sheet Metal Co. v. Smylie Bros., 188 N.E.2d 802, 118 Ohio App. 461, 92 Ohio Law. Abs. 100, 25 Ohio Op. 2d 360, 1963 Ohio App. LEXIS 814 (Ohio Ct. App. 1963).

Opinion

Artl, J.

This is an appeal on questions of law from a judgment of the Municipal Court of Cleveland rendered in favor of the plaintiff upon its petition and in favor of the plaintiff upon defendant’s cross-petition.

The appellant’s assignments of error are five in number and are as follows:

1. The Court erred in its Conclusions of law “that Plaintiff, by a preponderance of the evidence, was required to install only those items of sheet metal work set forth and enumerated in the Defendant’s Exhibit 3.”

2. The Court erred in referring to two documents whose terms vary as constituting an offer and an acceptance.

3. The Court erred in overruling defendant’s motions submitted following all of the testimony and evidence offered by the plaintiff corporation.

*101 4. The Court erred in disregarding defendant’s evidence as to the additional costs to him of the job resulting from plaintiff’s refusal to perform, under the contract.

5. The verdict is contrary to law, and contrary to the weight of the evidence.

The parties will be referred to herein as plaintiff and defendant as in the trial court. The plaintiff, a corporation, filed its action upon an account, in the short form, based upon an alleged contract with the defendant to furnish certain sheet metal work in the construction of the Bay Village High School for a price of $19,257.00. The account as set forth in its petition included extras in the amount of $142.65 and acknowledges receipt of payment in the amount of $17,151.30 and prays for judgment in the sum of $2248.35, with interest at 6% from April 13, 1960.

The defendant filed its answer and counterclaim. By its answer, defendant, a corporation, denies that it owes plaintiff the sum prayed for, or any other sum whatsoever, and further denies each and every allegation contained in the petition not specifically admitted to be true.

For its counterclaim, defendant claims there is due it on an account arising out of the Bay Village High School contract the sum of $2111.30, together with a yet undetermined amount by way of credit, as per account attached and prays for judgment accordingly.

The factual situation developed in the record indicates that the plaintiff corporation, a roofing and sheet metal contractor, received an invitation to bid upon the sheet metal work in connection with the construction of the Bay Village Junior High School and had several phone conversations with the defendant who subsequently became the prime contractor for this construction. A quotation and a revised quotation outlining the work to be done were forwarded to the defendant. (Plaintiff’s Exhibit C 1; Defendant’s Exhibit 2; Defendant’s Exhibit 3.) Defendant, having submitted its total bid to the awarding authority, knew on March 31, 1959, that it was the low bidder; the defendant received its contract for the job and on May 20, 1959, forwarded to the plaintiff its purchase order setting forth the contract price and authorized the plaintiff to proceed. (Plaintiff’s Exhibit O.)

*102 Plaintiff proceeded under its contract, billed periodically for material and services rendered, and on August 31, 1960, submitted its final bill for tbe balance due on tbe contract. (Plaintiff’s Exhibit B.) Construction was completed and the building accepted in 1961.

Plaintiff’s Exhibit C 1, its revised quotation, is as follows:

“We hereby propose to furnish the following Sheet Metal
Work for Bay Jr. High School, Bay Village, Ohio
“Our bid consists of the following items:
Furnish and install all required sheet metal ducts.
Furnish and install the required grilles, registers and
ceiling outlets.
Furnish and install the required louvers.
Furnish and install the required fire dampers.
Furnish and install the required sound insulation.
Furnish and install the required boiler breeching.
“Install only the required book cases.
‘ ‘ Our charge for the above mentioned items .... $16,828.00
2,129
$19,257
$20,257”

Plaintiff’s Exhibit C. Defendant’s purchase order to the plaintiff, is as follows:

“To furnish and install all sheetmetal work, as per plans and specifications for Bay Village School.
“Subject to Engineer approval
“Price $19,257.00”

The dispute involved herein develops from a claim by the defendant that plaintiff failed and refused to fulfill its obligation under its contract to install fin tubes, backings and covers, and, therefore, defendant refused to pay the balance of the contract price. The defendant’s claim is also that its purchase order of May 20, 1959, bound the plaintiff to install all sheet metal work indicated on the plans and specifications, including the fin tubes, backings and covers, since the plaintiff’s quotations did not exclude this work.

The plaintiff claims that its contract encompassed only *103 those items set forth in its quotations, and that to have been included under its contract, its quotation would have had to indicate, for practical reasons and by custom, the installation of fin tubes, backings and covers on a per foot basis.

The trial court set forth its findings of fact and conclusions of law and entered judgment accordingly. The essence of the court’s finding is as follows:

“CONCLUSIONS OF LAW
“After hearing all the testimony, some of which was not pertinent to the issue and was disregarded by the court, it is the opinion of the court that the plaintiff by preponderance of the evidence, was required to install only those items of sheet metal work set forth and enumerated in the defendant’s Exhibit 3 and that there is due the plaintiff from the defendant the sum of $2234.79 (some deduction from the amount prayed for was allowed by stipulation of the parties).
“Judgment is therefore rendered for plaintiff on its petition in the sum of $2234.79 and costs and judgment for the plaintiff on the defendant’s counterclaim.”

The record discloses that these two corporations were not strangers to one another. They have done business together in the past. We note further that the negotiations on behalf of the plaintiff, including the estimating of the job, the issuance of the respective quotations, and conversations relative thereto were handled by the salesman and estimator of the plaintiff, a Mr. William Bartelheim.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Steen Elec., Inc. v. Haas Orthodontic Arts, Inc.
2016 Ohio 5025 (Ohio Court of Appeals, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
188 N.E.2d 802, 118 Ohio App. 461, 92 Ohio Law. Abs. 100, 25 Ohio Op. 2d 360, 1963 Ohio App. LEXIS 814, Counsel Stack Legal Research, https://law.counselstack.com/opinion/korner-roofing-sheet-metal-co-v-smylie-bros-ohioctapp-1963.